*Purpose of act, and basis of orders of commission. 89 C. 528. State may control railroads by commission. 151 U.S. 556. Commission has full power over street railways; power of municipalities to make local regulations. 103 C. 203. Is an administrative body. 91 C. 697. Statute is constitutional; power is properly vested in public utilities commission; penalty covers violation of provision of act as well as violation of rule of commission made in carrying out provisions of act. 97 C. 732, 733, 735. Commission may select one of several applicants to operate over a particular route; statute providing for appeals covers only judicial or quasi-judicial questions; held to be no appeal from selection of a particular applicant, since this is a purely administrative function; power of legislature to commit nonjudicial questions to courts for determination or review. Id., 458, 459. Cited. 219 C. 121.
Cited. 40 CS 520.
Sec. 16-1b. Department of Public Utility Control. Department head.
Sec. 16-2. Public Utilities Regulatory Authority. Utility commissioners. Staff.
Sec. 16-2a. Office of Consumer Counsel. Office of State Broadband. Consumer Counsel. Staff.
Sec. 16-2c. Division of Adjudication.
Sec. 16-2d. Office of energy efficient businesses.
Sec. 16-3a. Appointment of initial members. Transfer of business between commission and authority.
Sec. 16-6. Office and records.
Sec. 16-6a. Participation in proceedings before federal agencies and federal courts. Expenses.
Sec. 16-6c. Power to delay implementation of electric suppliers' generation portfolio standards.
Sec. 16-7. Right of entry. Penalty.
Sec. 16-7a. Power to stop work.
Sec. 16-8. Examination of witnesses and documents. Hearing officers. Management audits.
Sec. 16-9a. Party status in proceedings before authority.
Sec. 16-10. Enforcement of statutes and orders.
Sec. 16-10a. Revocation of franchises. Procedure. Reassignment.
Sec. 16-11. Safety of public and employees. Powers.
Sec. 16-11a. Nuclear Energy Advisory Council; composition; duties.
Sec. 16-12. Complaints as to dangerous conditions.
Sec. 16-13. Procedure upon complaint.
Sec. 16-14. Powers concerning electrolysis or escape of electricity.
Sec. 16-15. Compliance with orders. Penalty.
Sec. 16-16. Report of accidents.
Sec. 16-17. Duties as to accidents.
Sec. 16-18. Powers concerning poles and wires.
Sec. 16-18a. Consultants: Retention, expenses, findings and recommendations.
Sec. 16-19c. Investigation of fuel cost adjustment and purchased gas adjustment charges.
Sec. 16-19g. Penalty for failure to report nuclear incident not an operating expense.
Sec. 16-19h. Reopening of water company rate proceedings.
Sec. 16-19i. Electric company residential customer service charge indicated on bill.
Sec. 16-19j. Portion of authority staff to be made party to certain rate proceedings.
Sec. 16-19l. Authorization of rates that promote water conservation.
Sec. 16-19x. Phase-in of costs of certain large electric generating facilities.
Sec. 16-19y. Rate treatment of enhanced 9-1-1 service costs.
Sec. 16-19bb. Application or refund of electric distribution company rate moderation funds.
Sec. 16-19dd. Conservation and load management programs for agricultural customers.
Sec. 16-19ff. Submetering. Regulations. Application process.
Sec. 16-19gg. Factors to be considered during a rate proceeding.
Sec. 16-19ii. Use of electric resistance space heating. Differential rates.
Sec. 16-19jj. Alternative dispute resolution mechanisms.
Sec. 16-19mm. Consideration of external costs and benefits.
Sec. 16-19nn. Encouragement of specific end uses of electricity and gas.
Sec. 16-19pp. Uncontested proceedings before the authority. Participating parties.
Sec. 16-19ss. Solicitations for the provision of temporary electric generation facilities.
Sec. 16-19tt. Gas and electric distribution companies' distribution revenue decoupling.
Sec. 16-19vv. Public service companies' customer deposits.
Sec. 16-19xx. Deferral of public service company tax expense increase.
Secs. 16-19aaa to 16-19ddd. Reserved
Sec. 16-19fff. Electric vehicle charging load projections.
Sec. 16-19ggg. Public electric vehicle charging stations. Parking restrictions.
Sec. 16-21. Change of rates fixed pursuant to charter or contract.
Sec. 16-22. Rates; transfer of assets or franchise; burden of proof.
Sec. 16-23. Regulations and service prescribed by authority deemed reasonable.
Sec. 16-24. Classification of service.
Sec. 16-24a. Low-income discounted rates for electric and gas service.
Sec. 16-25. Time and place of hearings. Notice.
Sec. 16-25a. Hearings on Office of Consumer Counsel petitions.
Sec. 16-26. Public hearing to be held in locality affected.
Sec. 16-28. Correction of returns and reports.
Sec. 16-29. Reports from municipalities.
Sec. 16-30. Returns from motor bus companies. Penalty.
Sec. 16-31. Remission of forfeitures by the Attorney General.
Sec. 16-32. Annual audit report.
Sec. 16-32a. Filing re procurement practices. Public hearing. Regulations re competitive bidding.
Sec. 16-32b. Regional water authority or water district to submit annual report.
Sec. 16-32c. Water company rate adjustments. Application. Notice to customers.
Sec. 16-32d. Reserved
Sec. 16-32f. Gas company supply and demand forecast reports.
Sec. 16-32g. Electric wire maintenance plans. Regulations.
Sec. 16-32j. Procedures for expedited road clearing after emergencies.
Sec. 16-32k. Vegetation management practices review. Report.
Sec. 16-33. Obstructing authority; false entries and returns to; penalty.
Sec. 16-34. Annual reports to Governor.
Sec. 16-34a. Annual report re lost and unaccounted for gas. Docket to investigate.
Secs. 16-36 to 16-39. Venue. Procedure on appeal. Notice when parties are numerous. Supersedeas.
Sec. 16-40. Rights and duties of trustees and receivers.
Sec. 16-41. Imposition of civil penalties by authority.
Sec. 16-42. Not to affect labor contracts.
Sec. 16-43a. Validity of securities issued pursuant to order of authority.
Sec. 16-43b. Definitions applicable to apportionment of land sales benefits.
Sec. 16-43d. Sale of existing electric generation plants.
Sec. 16-44a. Disclosure of salaries of directors and officers of public service companies.
Sec. 16-45. Increase or reduction of capital stock by public service companies.
Sec. 16-47a. Code of conduct for gas company transactions with affiliates.
Sec. 16-48. Electricity and gas; transmission between this state and other states.
Sec. 16-48a. Consumer Counsel and Public Utility Control Fund established.
Sec. 16-49d. Applications for sales of water company lands submitted prior to June 25, 1975.
Sec. 16-50. Employees. Consultants.
Sec. 16-50a. Local filing of maps on acquisition of property.
Sec. 16-50b. Declaration of policy.
Sec. 16-50d. Action to acquire property.
Sec. 16-50e. Notices to town clerk.
Sec. 16-1. Definitions. (a) Terms used in this title and in chapters 244, 244a, 244b, 245, 245a and 245b shall be construed as follows, unless another meaning is expressed or is clearly apparent from the language or context:
(1) “Authority” means the Public Utilities Regulatory Authority and “department” means the Department of Energy and Environmental Protection;
(2) “Utility commissioner” means a member of the Public Utilities Regulatory Authority;
(3) “Public service company” includes electric distribution, gas, telephone, pipeline, sewage, water and community antenna television companies and holders of a certificate of cable franchise authority, owning, leasing, maintaining, operating, managing or controlling plants or parts of plants or equipment, but shall not include towns, cities, boroughs, any municipal corporation or department thereof, whether separately incorporated or not, a private power producer, as defined in section 16-243b, or an exempt wholesale generator, as defined in 15 USC 79z-5a;
(4) “Plant” includes all real estate, buildings, tracks, pipes, mains, poles, wires and other fixed or stationary construction and equipment, wherever located, used in the conduct of the business of the company;
(5) “Gas company” includes every person owning, leasing, maintaining, operating, managing or controlling mains, pipes or other fixtures, in public highways or streets, for the transmission or distribution of gas for sale for heat or power within this state, or engaged in the manufacture of gas to be so transmitted or distributed for such purpose, but shall not include (A) a person manufacturing gas through the use of a biomass gasification plant provided such person does not own, lease, maintain, operate, manage or control mains, pipes or other fixtures in public highways or streets, (B) a municipal gas utility established under chapter 101 or any other gas utility owned, leased, maintained, operated, managed or controlled by any unit of local government under any general statute or any public or special act, or (C) an entity approved to submeter pursuant to section 16-19ff;
(6) “Water company” includes every person owning, leasing, maintaining, operating, managing or controlling any pond, lake, reservoir, stream, well or distributing plant or system employed for the purpose of supplying water to fifty or more consumers. A water company does not include homeowners, condominium associations providing water only to their members, homeowners associations providing water to customers at least eighty per cent of whom are members of such associations, a municipal waterworks system established under chapter 102, a district, metropolitan district, municipal district or special services district established under chapter 105, chapter 105a or any other general statute or any public or special act which is authorized to supply water, or any other waterworks system owned, leased, maintained, operated, managed or controlled by any unit of local government under any general statute or any public or special act;
(7) “Consumer” means any private dwelling, boardinghouse, apartment, store, office building, institution, mechanical or manufacturing establishment or other place of business or industry to which water is supplied by a water company;
(8) “Sewage company” includes every person owning, leasing, maintaining, operating, managing or controlling, for general use in any town, city or borough, or portion thereof, in this state, sewage disposal facilities which discharge treated effluent into any waterway of this state;
(9) “Pipeline company” includes every person owning, leasing, maintaining, operating, managing or controlling mains, pipes or other fixtures through, over, across or under any public land, water, parkways, highways, parks or public grounds for the transportation, transmission or distribution of petroleum products for hire within this state;
(10) “Community antenna television company” includes every person owning, leasing, maintaining, operating, managing or controlling a community antenna television system, in, under or over any public street or highway, for the purpose of providing community antenna television service for hire and shall include any municipality which owns or operates one or more plants for the manufacture or distribution of electricity pursuant to section 7-213 or any special act and seeks to obtain or obtains a certificate of public convenience and necessity to construct or operate a community antenna television system pursuant to section 16-331 or a certificate of cable franchise authority pursuant to section 16-331q. “Community antenna television company” does not include a certified competitive video service provider;
(11) “Community antenna television service” means (A) the one-way transmission to subscribers of video programming or information that a community antenna television company makes available to all subscribers generally, and subscriber interaction, if any, which is required for the selection of such video programming or information, and (B) noncable communications service. “Community antenna television service” does not include video service provided by a certified competitive video service provider;
(12) “Community antenna television system” means a facility, consisting of a set of closed transmission paths and associated signal generation, reception and control equipment that is designed to provide community antenna television service which includes video programming and which is provided in, under or over any public street or highway, for hire, to multiple subscribers within a franchise, but such term does not include (A) a facility that serves only to retransmit the television signals of one or more television broadcast stations; (B) a facility that serves only subscribers in one or more multiple unit dwellings under common ownership, control or management, unless such facility is located in, under or over a public street or highway; (C) a facility of a common carrier which is subject, in whole or in part, to the provisions of Subchapter II of Chapter 5 of the Communications Act of 1934, 47 USC 201 et seq., as amended, except that such facility shall be considered a community antenna television system and the carrier shall be considered a public service company to the extent such facility is used in the transmission of video programming directly to subscribers; or (D) a facility of an electric distribution company which is used solely for operating its electric distribution company systems. “Community antenna television system” does not include a facility used by a certified competitive video service provider to provide video service;
(13) “Video programming” means programming provided by, or generally considered comparable to programming provided by, a television broadcast station;
(14) “Noncable communications service” means any telecommunications service, as defined in section 16-247a, and which is not included in the definition of “cable service” in the Communications Act of 1934, 47 USC 522, as amended. Nothing in this definition shall be construed to affect service which is both authorized and preempted pursuant to federal law;
(15) “Cogeneration technology” means the use for the generation of electricity of exhaust steam, waste steam, heat or resultant energy from an industrial, commercial or manufacturing plant or process, or the use of exhaust steam, waste steam or heat from a thermal power plant for an industrial, commercial or manufacturing plant or process, but shall not include steam or heat developed solely for electrical power generation;
(16) “Renewable fuel resources” means energy sources described in subdivisions (20) and (21) of this subsection;
(17) “Telephone company” means a telecommunications company that provides one or more noncompetitive or emerging competitive services, as defined in section 16-247a;
(18) “Domestic telephone company” includes any telephone company which has been chartered by or organized or constituted within or under the laws of this state;
(19) “Telecommunications company” means a person that provides telecommunications service, as defined in section 16-247a, within the state, but shall not mean a person that provides only (A) private telecommunications service, as defined in section 16-247a, (B) the one-way transmission of video programming or other programming services to subscribers, (C) subscriber interaction, if any, which is required for the selection of such video programming or other programming services, (D) the two-way transmission of educational or instructional programming to a public or private elementary or secondary school, or a public or independent institution of higher education, as required by the authority pursuant to a community antenna television company franchise agreement, or provided pursuant to a contract with such a school or institution which contract has been filed with the authority, or (E) a combination of the services set forth in subparagraphs (B) to (D), inclusive, of this subdivision;
(20) “Class I renewable energy source” means (A) electricity derived from (i) solar power, (ii) wind power, (iii) a fuel cell, (iv) geothermal, (v) landfill methane gas, anaerobic digestion or other biogas derived from biological sources, (vi) thermal electric direct energy conversion from a certified Class I renewable energy source, (vii) ocean thermal power, (viii) wave or tidal power, (ix) low emission advanced renewable energy conversion technologies, including, but not limited to, zero emission low grade heat power generation systems based on organic oil free rankine, kalina or other similar nonsteam cycles that use waste heat from an industrial or commercial process that does not generate electricity, (x) (I) a run-of-the-river hydropower facility that began operation after July 1, 2003, and has a generating capacity of not more than thirty megawatts, or (II) a run-of-the-river hydropower facility that received a new license after January 1, 2018, under the Federal Energy Regulatory Commission rules pursuant to 18 CFR 16, as amended from time to time, and provided a facility that applies for certification under this clause after January 1, 2013, shall not be based on a new dam or a dam identified by the commissioner as a candidate for removal, and shall meet applicable state and federal requirements, including applicable site-specific standards for water quality and fish passage, or (xi) a biomass facility that uses sustainable biomass fuel and has an average emission rate of equal to or less than .075 pounds of nitrogen oxides per million BTU of heat input for the previous calendar quarter, except that energy derived from a biomass facility with a capacity of less than five hundred kilowatts that began construction before July 1, 2003, may be considered a Class I renewable energy source, or (B) any electrical generation, including distributed generation, generated from a Class I renewable energy source, provided, on and after January 1, 2014, any megawatt hours of electricity from a renewable energy source described under this subparagraph that are claimed or counted by a load-serving entity, province or state toward compliance with renewable portfolio standards or renewable energy policy goals in another province or state, other than the state of Connecticut, shall not be eligible for compliance with the renewable portfolio standards established pursuant to section 16-245a;
(21) “Class II renewable energy source” means electricity derived from a trash-to-energy facility that has obtained a permit pursuant to section 22a-208a and section 22a-174-33 of the regulations of Connecticut state agencies;
(22) “Electric distribution services” means the owning, leasing, maintaining, operating, managing or controlling of poles, wires, conduits or other fixtures along public highways or streets for the distribution of electricity, or electric distribution-related services;
(23) “Electric distribution company” or “distribution company” means any person providing electric transmission or distribution services within the state, but does not include: (A) A private power producer, as defined in section 16-243b; (B) a municipal electric utility established under chapter 101, other than a participating municipal electric utility; (C) a municipal electric energy cooperative established under chapter 101a; (D) an electric cooperative established under chapter 597; (E) any other electric utility owned, leased, maintained, operated, managed or controlled by any unit of local government under any general statute or special act; (F) an electric supplier; (G) an entity approved to submeter pursuant to section 16-19ff; or (H) a municipality, state or federal governmental entity authorized to distribute electricity across a public highway or street pursuant to section 16-243aa;
(24) “Electric supplier” means any person, including an electric aggregator or participating municipal electric utility that is licensed by the Public Utilities Regulatory Authority in accordance with section 16-245, that provides electric generation services to end use customers in the state using the transmission or distribution facilities of an electric distribution company, regardless of whether or not such person takes title to such generation services, but does not include: (A) A municipal electric utility established under chapter 101, other than a participating municipal electric utility; (B) a municipal electric energy cooperative established under chapter 101a; (C) an electric cooperative established under chapter 597; or (D) any other electric utility owned, leased, maintained, operated, managed or controlled by any unit of local government under any general statute or special act;
(25) “Electric aggregator” means (A) a person, municipality or regional water authority that gathers together electric customers for the purpose of negotiating the purchase of electric generation services from an electric supplier, or (B) the Materials Innovation and Recycling Authority, if it gathers together electric customers for the purpose of negotiating the purchase of electric generation services from an electric supplier, provided such person, municipality or authority is not engaged in the purchase or resale of electric generation services, and provided further such customers contract for electric generation services directly with an electric supplier, and may include an electric cooperative established pursuant to chapter 597;
(26) “Electric generation services” means electric energy, electric capacity or generation-related services;
(27) “Electric transmission services” means electric transmission or transmission-related services;
(28) “Generation entity or affiliate” means a corporate affiliate or a separate division of an electric distribution company that provides electric generation services;
(29) “Participating municipal electric utility” means a municipal electric utility established under chapter 101 or any other electric utility owned, leased, maintained, operated, managed or controlled by any unit of local government under any general statute or any public or special act, that is authorized by the authority in accordance with section 16-245c to provide electric generation services to end use customers outside its service area, as defined in section 16-245c;
(30) “Person” means an individual, business, firm, corporation, association, joint stock association, trust, partnership or limited liability company;
(31) “Regional independent system operator” means the “ISO - New England, Inc.”, or its successor organization as approved by the Federal Energy Regulatory Commission;
(32) “Certified telecommunications provider” means a person certified by the authority to provide intrastate telecommunications services, as defined in section 16-247a, pursuant to sections 16-247f to 16-247h, inclusive;
(33) “Gas registrant” means a person registered to sell natural gas pursuant to section 16-258a;
(34) “Customer-side distributed resources” means (A) the generation of electricity from a unit with a rating of not more than sixty-five megawatts on the premises of a retail end user within the transmission and distribution system including, but not limited to, fuel cells, photovoltaic systems or small wind turbines, or (B) a reduction in the demand for electricity on the premises of a retail end user in the distribution system through methods of conservation and load management, including, but not limited to, peak reduction systems and demand response systems;
(35) “Federally mandated congestion charges” means any cost approved by the Federal Energy Regulatory Commission as part of New England Standard Market Design including, but not limited to, locational marginal pricing, locational installed capacity payments, any cost approved by the Public Utilities Regulatory Authority to reduce federally mandated congestion charges in accordance with section 7-233y, this section, sections 16-32f, 16-50i, 16-50k, 16-50x, 16-243i to 16-243q, inclusive, 16-244c, 16-245m, 16-245n and 16-245z, section 21 of public act 05-1 of the June special session*, subsection (f) of section 16a-3j and reliability must run contracts;
(36) “Combined heat and power system” means a system that produces, from a single source, both electric power and thermal energy used in any process that results in an aggregate reduction in electricity use;
(37) “Grid-side distributed resources” means the generation of electricity from a unit with a rating of not more than sixty-five megawatts that is connected to the transmission or distribution system, which units may include, but are not limited to, units used primarily to generate electricity to meet peak demand;
(38) “Class III source” means the electricity output from combined heat and power systems with an operating efficiency level of no less than fifty per cent that are part of customer-side distributed resources developed at commercial and industrial facilities in this state on or after January 1, 2006, a waste heat recovery system installed on or after April 1, 2007, that produces electrical or thermal energy by capturing preexisting waste heat or pressure from industrial or commercial processes, or the electricity savings created in this state from conservation and load management programs begun on or after January 1, 2006, provided on and after January 1, 2014, no such programs supported by ratepayers, including programs overseen by the Energy Conservation Management Board or third-party programs pursuant to section 16-245m, shall be considered a Class III source, except that any demand-side management project awarded a contract pursuant to section 16-243m shall remain eligible as a Class III source for the term of such contract;
(39) “Sustainable biomass fuel” means biomass that is cultivated and harvested in a sustainable manner. “Sustainable biomass fuel” does not mean construction and demolition waste, as defined in section 22a-208x, finished biomass products from sawmills, paper mills or stud mills, organic refuse fuel derived separately from municipal solid waste, or biomass from old growth timber stands, except where (A) such biomass is used in a biomass gasification plant that received funding prior to May 1, 2006, from the Clean Energy Fund established pursuant to section 16-245n, or (B) the energy derived from such biomass is subject to a long-term power purchase contract pursuant to subdivision (2) of subsection (j) of section 16-244c entered into prior to May 1, 2006;
(40) “Video service” means video programming services provided through wireline facilities, a portion of which are located in the public right-of-way, without regard to delivery technology, including Internet protocol technology. “Video service” does not include any video programming provided by a commercial mobile service provider, as defined in 47 USC 332(d), any video programming provided as part of community antenna television service in a franchise area as of October 1, 2007, any video programming provided as part of and via a service that enables users to access content, information, electronic mail or other services over the public Internet;
(41) “Certified competitive video service provider” means an entity providing video service pursuant to a certificate of video franchise authority issued by the authority in accordance with section 16-331e. “Certified competitive video service provider” does not mean an entity issued a certificate of public convenience and necessity in accordance with section 16-331 or the affiliates, successors and assigns of such entity or an entity issued a certificate of cable franchise authority in accordance with section 16-331p or the affiliates, successors and assignees of such entity;
(42) “Certificate of video franchise authority” means an authorization issued by the Public Utilities Regulatory Authority conferring the right to an entity or person to own, lease, maintain, operate, manage or control facilities in, under or over any public highway to offer video service to any subscribers in the state;
(43) “Certificate of cable franchise authority” means an authorization issued by the Public Utilities Regulatory Authority pursuant to section 16-331q conferring the right to a community antenna television company to own, lease, maintain, operate, manage or control a community antenna television system in, under or over any public highway to (A) offer community antenna television service in a community antenna television company's designated franchise area, or (B) use the public rights-of-way to offer video service in a designated franchise area. The certificate of cable franchise authority shall be issued as an alternative to a certificate of public convenience and necessity pursuant to section 16-331 and shall only be available to a community antenna television company under the terms specified in sections 16-331q to 16-331aa, inclusive;
(44) “Thermal energy transportation company” means any person authorized under any provision of the general statutes or special act to furnish heat or air conditioning or both, by means of steam, heated or chilled water or other medium, to lay and maintain mains, pipes or other conduits, and to erect such other fixtures necessary or convenient in and on the streets, highways and public grounds of any municipality to carry steam, heated or chilled water or other medium from such plant to the location to be served and to return the same;
(45) “The Connecticut Television Network” means the General Assembly's state-wide twenty-four-hour state public affairs programming service, separate and distinct from community access channels;
(46) “Commissioner of Energy and Environmental Protection” means the Commissioner of Energy and Environmental Protection appointed pursuant to title 4, or the commissioner's designee;
(47) “Large-scale hydropower” means any hydropower facility that (A) began operation on or after January 1, 2003, (B) is located in the New England Power Pool Generation Information System geographic eligibility area in accordance with Rule 2.3 of said system or an area abutting the northern boundary of the New England Power Pool Generation Information System geographic eligibility area that is not interconnected with any other control area that is not a part of the New England Power Pool Generation Information System geographic eligibility area, (C) delivers power into such geographic eligibility area, and (D) has a generating capacity of more than thirty megawatts;
(48) “Energy storage system” means any commercially available technology that is capable of absorbing energy, storing it for a period of time and thereafter dispatching the energy, and that is capable of either: (A) Using mechanical, chemical or thermal processes to store electricity that is generated at one time for use at a later time; (B) storing thermal energy for direct use for heating or cooling at a later time in a manner that avoids the need to use electricity at a later time; (C) using mechanical, chemical or thermal processes to store electricity generated from renewable energy sources for use at a later time; or (D) using mechanical, chemical or thermal processes to capture or harness waste electricity and to store such electricity generated from mechanical processes for delivery at a later time;
(49) “Distributed energy resource” means any (A) customer-side distributed resource or grid-side distributed resource that generates electricity from a Class I renewable energy source or Class III source, and (B) customer-side distributed resource that reduces demand for electricity through conservation and load management, energy storage system which is located on the customer-side of the meter or is connected to the distribution system or microgrid; and
(50) “Grid-side system enhancement” means an investment in distribution system infrastructure, technology and systems designed to enable the deployment of distributed energy resources and allow for grid management and system balancing, including, but not limited to, energy storage systems, distribution system automation and controls, intelligent field systems, advanced distribution system metering, and communication and systems that enable two-way power flow.
(b) Notwithstanding any provision of the general statutes, the terms “utility”, “public utility” and “public service company” shall be deemed to include a community antenna television company and a holder of a certificate of cable franchise authority, except (1) as otherwise provided in sections 16-8, 16-27, 16-28 and 16-43, (2) that no provision of the general statutes, including but not limited to, the provisions of sections 16-6b and 16-19, shall subject a community antenna television company to regulation as a common carrier or utility by reason of providing community antenna television service, other than noncable communications service, as provided in Subchapter V-A of Chapter 5 of the Communications Act of 1934, 47 USC 521 et seq., as amended, and (3) that no provision of the general statutes, including but not limited to, sections 16-6b and 16-19, shall apply to community antenna television companies to the extent any such provision is preempted pursuant to any other provision of the Communications Act of 1934, 47 USC 151 et seq., as amended, any other federal act or any regulation adopted thereunder.
(c) An owner of an electric vehicle charging station, as defined in section 16-19f, shall not be deemed to be a utility, public utility or public service company solely by virtue of the fact that such owner is an owner of an electric vehicle charging station.
(1949 Rev., S. 5390; February, 1965, P.A. 175, S. 1; 1967, P.A. 546, S. 1; 691, S. 1; 1969, P.A. 768, S. 208; P.A. 73-267; P.A. 75-486, S. 2, 69; P.A. 77-614, S. 162, 587, 610; P.A. 78-303, S. 85, 136; P.A. 79-214, S. 1; 79-610, S. 7; P.A. 80-482, S. 39, 348; 80-483, S. 65, 186; P.A. 81-297, S. 3; 81-329, S. 1, 11; 81-358, S. 2; 81-439, S. 2, 14; P.A. 85-246, S. 8; 85-509, S. 1, 11; P.A. 86-403, S. 33, 132; P.A. 87-323, S. 4; 87-415, S. 7, 13; P.A. 91-310, S. 3; P.A. 92-137, S. 2; P.A. 93-149; P.A. 94-83, S. 1, 16; P.A. 95-79, S. 47, 189; P.A. 98-28, S. 1, 117; P.A. 99-222, S. 1, 19; 99-286, S. 1, 19; P.A. 00-53, S. 11, 12; P.A. 01-49, S. 1; 01-204, S. 7, 29; June Sp. Sess. P.A. 01-9, S. 73, 131; P.A. 03-135, S. 1, 2; 03-163, S. 2; 03-221, S. 1, 2; June Sp. Sess. P.A. 05-1, S. 1, 2; P.A. 06-74, S. 1, 2; P.A. 07-242, S. 44; 07-253, S. 1; June Sp. Sess. P.A. 07-5, S. 58; P.A. 08-77, S. 1; 08-185, S. 4; Sept. Sp. Sess. P.A. 09-7, S. 186; P.A. 11-80, S. 1, 14; P.A. 13-5, S. 1, 30, 31; 13-298, S. 1, 2, 38; 13-303, S. 1–4; P.A. 14-94, S. 1; 14-134, S. 1; P.A. 15-107, S. 2, 3; June Sp. Sess. P.A. 15-5, S. 102; P.A. 16-135, S. 3; P.A. 17-144, S. 2; P.A. 18-50, S. 27.)
*Note: Section 21 of public act 05-1 of the June special session is special in nature and therefore has not been codified but remains in full force and effect according to its terms.
History: 1965 act added definition of community antenna television company; 1967 acts included sewage plants in definition of “public service company” and defined “sewage company”, redefined “water company” to include companies owning, controlling etc. streams and wells and to delete phrase “for general domestic use in any town, city or borough ... within this state” and defined “consumer”; 1969 act defined “commissioner of transportation”; P.A. 73-267 included motor bus companies in definition of “public service company”; P.A. 75-486 replaced definition of “commission” with definition of “authority”; P.A. 77-614 and P.A. 78-303 included definition of division of public utility control, effective January 1, 1979; P.A. 79-214 defined “cogeneration technology” and excluded persons owning or operating facilities producing one or less megawatt from definition of “public service company”; P.A. 79-610 defined “department”, deleted railroad and motor bus companies from definition of “public service company” and added reference to leasing in definitions of “railroad company” and “water company”; P.A. 80-482 replaced definition of “division” with definition of “department” re public utility control, deleting previous definition of “department” as “department of transportation”; P.A. 80-483 added reference to leasing in definitions of “street railway company” and “sewage company”; P.A. 81-297 excluded telegraph company functions concerning intrastate money order service from definition of public service company; P.A. 81-329 added definitions of “telephone company” and “domestic telephone company”; P.A. 81-358 excluded homeowners and condominium associations providing water to members only from definition of water company; P.A. 81-439 excluded private power producers from definitions of public service company and electric company; P.A. 85-246 redefined “public service company” to omit references to street railway companies and deleted a reference to street railway companies in definition of “motor bus”; P.A. 85-509 made existing section Subsec. (a), added definitions of “community antenna television service”, “community antenna television system”, “video programming” and “noncable communications service” in Subsec. (a), clarified definition of “community antenna television company” to apply to an antenna television system and added Subsec. (b) re the meaning of the terms “utility”, “public utility” and “public service company”; P.A. 86-403 made a technical change to Subsec. (a); (Revisor's note: In 1987 the definitions in Subsec. (a) were numbered editorially by the Revisors for ease of reference); P.A. 87-323 redefined “water company” to specifically exclude certain homeowners associations; P.A. 87-415 redefined “telephone company” to exclude entities which provide only those telecommunications services authorized under Secs. 16-247f to 16-247h, inclusive; P.A. 91-310 redefined “electric company”, “gas company” and “water company” to specifically exclude municipal utilities; P.A. 92-137 redefined “community antenna television company” to include municipalities which own or operate electric plants; P.A. 93-149 redefined “community antenna television system” to include municipalities which own or operate electric plants only if they obtain a certificate of public convenience and necessity for a community antenna television system; P.A. 94-83 amended Subsec. (a) by clarifying reference to the Communications Act of 1934 in Subdivs. (16) and (18), redefined “telephone company” in Subdiv. (23) and adding new Subdiv. (25) defining “telecommunications company”, and amended Subsec. (b) by clarifying reference to the Communications Act of 1934, effective July 1, 1994; P.A. 95-79 redefined “telecommunications company” to include a limited liability company, effective May 31, 1995; P.A. 98-28 amended Subsec. (a), redefining “public service company” by adding electric distribution companies and exempting wholesale generators, by making minor changes in definitions of “electric company” and “renewable fuel resources” and added new Subdivs. (26) to (37), defining “class I renewable energy source”, “class II renewable energy source”, “electric distribution services”, “electric distribution company”, “electric supplier”, “electric aggregator”, “electric generation services”, “electric transmission services”, “generation entity or affiliate”, “participating municipal electric utility”, “person” and “regional independent system operator”, effective July 1, 1998 (Revisor's note: In Subdiv. (22) the Revisors editorially changed the phrase “... subdivisions (26) and (27) of this section” to “... subdivisions (26) and (27) of this subsection”); P.A. 99-222 amended Subsec. (a) by inserting new Subdiv. (38) defining “certified telecommunications provider”, effective June 29, 1999; P.A. 99-286 amended Subsec. (a) by making technical changes and by defining “certified telecommunications provider” in words identical to those in P.A. 99-222, effective July 19, 1999; P.A. 00-53 amended Subsec. (a) by redefining “electric aggregator” in Subdiv. (31) to include regional water authorities, and by adding a new Subdiv., designated as (39), defining “gas registrant”; P.A. 01-49 amended Subsec. (a) by making technical changes in Subdivs. (15) and (16); P.A. 01-204 amended Subsec. (a) by redefining “Class I renewable energy source” in Subdiv. (26) to include biomass gasification plants, effective July 11, 2001; June Sp. Sess. P.A. 01-9 revised effective date of P.A. 01-204 but without affecting this section; P.A. 03-135 redefined “Class I renewable energy source” in Subdiv. (26) to include “ocean thermal power, wave or tidal power, low emission advanced renewable energy conversion technologies” and certain run-of-the-river hydropower facilities, to revise the type of biomass that falls under the definition and include, as an exception, “energy derived from a biomass facility that began operation before July 1, 1998” provided “the average emission rate for such facility is equal to or less than .075 pounds of nitrogen oxides per million BTU of heat input for the previous calendar quarter”, and to include “any electrical generation, including distributed generation, generated from a Class I renewable energy source”, redefined “Class II renewable energy source” in Subdiv. (27) to limit the type of biomass facility included in the definition to a facility “that began operation before July 1, 1998, provided the average emission rate for such facility is equal to or less than .2 pounds of nitrogen oxides per million BTU of heat input for the previous calendar quarter” and to change the type of hydropower facility included in the definition to certain run-of-the-river hydropower facilities, and added new Subdivs. (40) and (41), defining “distributed generation” and “federally mandated congestion costs”, effective July 1, 2003; P.A. 03-163 redefined “gas company” in Subdiv. (9) to exclude a person manufacturing gas through the use of a biomass gasification plant, effective June 26, 2003; P.A. 03-221 redefined “Class I renewable energy source” in Subdiv. (26) to delete provisions re the date that a biomass facility began operation, to make the emission rate applicable to all biomass facilities, and to add an exception for biomass facilities with a capacity of less than five hundred kilowatts, and redefined “federally mandated congestion costs” in Subdiv. (41) by replacing “imposed” with “approved” and adding “including, but not limited to, locational marginal pricing and reliability must run contracts”, effective July 1, 2003; June Sp. Sess. P.A. 05-1 amended Subsec. (a) by amending Subdiv. (40) to change the definition of “distributed generation” to “customer-side distributed resources”, to designate existing language as Subpara. (A), to add a unit rating limit in Subpara. (A), and to add Subpara. (B) re reduction in demand, by amending Subdiv. (41) to change the definition of “federally mandated congestion costs” to “federally mandated congestion charges” and to add additional qualifying payments and costs, and by adding Subdivs. (42) to (44), inclusive, defining “combined heat and power system”, “grid-side distributed resources” and “Class III renewable energy source”, effective July 21, 2005; P.A. 06-74 amended Subsec. (a)(26) to insert “sustainable” prior to each occurrence of “biomass facility”, to delete language re biomass gasification plants, to make conforming changes, and to delete language within exception for biomass facilities re biomass cultivated and harvested in a sustainable manner, and added new Subdiv. (45) in Subsec. (a) defining “sustainable biomass”; P.A. 07-242 amended Subsec. (a)(44) to change term from “Class III renewable energy source” to “Class III source” and redefine the term, effective June 4, 2007; P.A. 07-253 redefined “public service company”, “community antenna television company”, “community antenna television service” and “community antenna television system”, defined “video service”, “certified competitive video service provider”, “certificate of video franchise authority” and “certificate of cable franchise authority” and made technical changes in Subsec. (a), and added holder of a certificate of cable franchise authority and made technical changes in Subsec. (b); June Sp. Sess. P.A. 07-5 amended Subsec. (a)(45)(C) to change exception from biomass used in a facility approved before October 1, 2005, to biomass used in a facility certified as a Class I renewable energy source until department certifies that a biomass gasification plant is operational, effective October 6, 2007; P.A. 08-77 added Subsec. (a)(50) defining “thermal energy transportation company”, effective April 30, 2008; P.A. 08-185 redefined “sustainable biomass” in Subsec. (a)(45) by adding as exception renewable energy facilities certified prior to December 31, 2007, and volume-reduction facilities in Subpara. (C), adding Subpara. (D) re certain other renewable energy facilities, and adding provision re amount of biomass shall not apply to a biomass gasification plant, effective June 12, 2008; Sept. Sp. Sess. P.A. 09-7 added Subsec. (a)(51) defining “the Connecticut Television Network”, effective October 5, 2009; P.A. 11-80 amended Subsec. (a)(1) to redefine “authority” as Public Utilities Regulatory Authority and “department” as Department of Energy and Environmental Protection, rather than Public Utilities Control Authority and Department of Public Utility Control, amended Subsec. (a)(2) to replace “commissioner” with “director” as the defined term, amended Subsec. (a)(30), (41), (48) and (49) to replace “Department of Public Utility Control” with “Public Utilities Regulatory Authority”, amended Subsec. (a)(35), (38), (45) and (47) to replace “department” with “authority”, amended Subsec. (a)(45)(A) to replace “Renewable Energy Investment Fund” with “Clean Energy Fund”, and added Subsec. (a)(52) defining “Commissioner of Energy and Environmental Protection”, effective July 1, 2011; P.A. 13-5 amended Subsec. (a)(25) to redefine “telecommunications company” by replacing “department” with “authority”, amended Subsec. (a)(30) to redefine “electric supplier” by deleting former Subpara. (E) re electric distribution company in its provision of electric generation services and amended Subsec. (a)(41) to make a technical change in definition of “federally mandated congestion charges”, effective May 8, 2013; P.A. 13-298 amended Subsec. (a)(8) to redefine “electric company” by adding Subparas. (G) and (H) re entity approved to submeter and municipality, state or federal governmental entity authorized to distribute electricity across a public highway or street and amended Subsec. (a)(9) to redefine “gas company” by adding Subpara. (A) and (B) designators in existing provisions re person manufacturing gas through use of a biomass gasification plant and re municipal gas utility and adding Subpara. (C) re entity approved to submeter, effective July 1, 2013, and amended Subsec. (a)(2) to replace “director” with “utility commissioner” and make a technical change and amended Subsec. (a)(52) to add “or the commissioner's designee” in definition of “Commissioner of Energy and Environmental Protection”, effective July 8, 2013; P.A. 13-303 amended Subsec. (a)(26) to redefine “Class I renewable energy source” by replacing “energy derived from” with “electricity derived from”, inserting clause designators, including geothermal, anaerobic digestion or other biogas derived from biological sources and thermal electric direct energy conversion from a certified Class I renewable energy source, revising the type of run-of-the-river hydropower facility and biomass facility that fall under the definition and adding provision re eligibility of any megawatt hours of electricity claimed or counted by a load-serving entity, province or state towards compliance with renewable portfolio standards or renewable energy policy goals in another province or state other than Connecticut, amended Subsec. (a)(44) to redefine “Class III source” by adding provision re eligibility of programs supported by ratepayers, amended Subsec. (a)(45) to replace “sustainable biomass” with “sustainable biomass fuel” and to delete former Subparas. (C) and (D) re eligibility as sustainable biomass and added Subsec. (a)(53) defining “large-scale hydropower”, effective June 5, 2013; pursuant to P.A. 14-94, “Connecticut Resources Recovery Authority” was changed editorially by the Revisors to “Materials Innovation and Recycling Authority” in Subsec. (a)(31), effective June 6, 2014; P.A. 14-134 amended Subsec. (a) by deleting former Subdivs. (3), (6) to (8), (19) and (20) re definitions of “Commissioner of Transportation”, “railroad company”, “street railway company”, “electric company”, “public service motor vehicle” and “motor bus”, redesignating existing Subdivs. (4), (5), (9) to (18) and (21) to (53) as Subdivs. (3) to (47), redefining “public service company” in redesignated Subdiv. (3), replacing “electric company” with “electric distribution company” in redesignated Subdiv. (12)(D), redefining “electric distribution company” or “distribution company” in redesignated Subdiv. (23), redefining “generation entity or affiliate” in redesignated Subdiv. (28), and making conforming changes, effective June 6, 2014; P.A. 15-107 amended Subsec. (a)(35) by adding “subsection (f) of section 16a-3j and” and added Subsec. (a)(48) to define “energy storage system”, effective June 19, 2015; June Sp. Sess. P.A. 15-5 amended Subsec. (a) by adding Subdiv. (49) defining “distributed energy resource” and Subdiv. (50) defining “grid-side system enhancement”, effective July 1, 2015; P.A. 16-135 added Subsec. (c) re owner of electric vehicle charging station, effective July 1, 2016; P.A. 17-144 amended Subsec. (a)(21) to redefine “Class II renewable energy source,” effective June 27, 2017; P.A. 18-50 amended Subsec. (a)(20) by redefining “Class I renewable energy source”.
See Sec. 25-32n re exclusion of municipality with well water service to a school administration building from consideration as a water company.
Cited. 147 C. 229; 152 C. 563; 159 C. 327; 162 C. 51; 166 C. 232; 169 C. 344; 174 C. 556; 183 C. 128; 214 C. 609; 216 C. 627.
Cited. 12 CA 499; 20 CA 474; 43 CA 196.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-1a. Reference to Public Utilities Commission deemed to mean Public Utilities Control Authority. Obsolete.
(P.A. 75-486, S. 1, 69.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-1b. Department of Public Utility Control. Department head. Section 16-1b is repealed, effective July 1, 2011.
(P.A. 77-614, S. 162, 610; P.A. 78-303, S. 79, 136; P.A. 80-482, S. 40, 348; P.A. 84-342, S. 3, 13; P.A. 11-80, S. 140.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-2. Public Utilities Regulatory Authority. Utility commissioners. Staff. (a) There shall continue to be a Public Utilities Regulatory Authority within the Department of Energy and Environmental Protection, which shall consist of five electors of this state, appointed by the Governor with the advice and consent of both houses of the General Assembly. Not more than three members of said authority in office at any one time shall be members of any one political party. The Governor shall appoint five members to the authority. The procedure prescribed in section 4-7 shall apply to such appointments, except that the Governor shall submit each nomination on or before May first, and both houses shall confirm or reject it before adjournment sine die. Any utility commissioner appointed by the Governor and confirmed by both chambers of the General Assembly between February 1, 2019, and June 1, 2019, shall serve a term expiring on March 1, 2024. Any utility commissioner appointed by the Governor and confirmed by both houses of the General Assembly between February 1, 2018, and June 1, 2018, shall serve a term expiring on March 1, 2022. Between July 1, 2019, and May 1, 2020, the Governor shall appoint three utility commissioners, provided one such commissioner shall serve a term expiring on March 1, 2021, and two such commissioners shall serve terms expiring on March 1, 2023. Any utility commissioner appointed on or after May 1, 2020, shall serve a term of four years. The utility commissioners shall be sworn to the faithful performance of their duties.
(b) The authority shall elect a chairperson and vice-chairperson each June for one-year terms starting on July first of the same year. The vice-chairperson shall perform the duties of the chairperson in his or her absence.
(c) Any matter coming before the authority may be assigned by the chairperson to a panel of three or more utility commissioners. Except as otherwise provided by statute or regulation, the panel shall determine whether a public hearing shall be held on the matter, and may designate one or more of its members to conduct such hearing or may assign a hearing officer to ascertain the facts and report thereon to the panel. The decision of the panel, if unanimous, shall be the decision of the authority. If the decision of the panel is not unanimous, the matter shall be approved by a majority vote of the utility commissioners.
(d) The utility commissioners of the Public Utilities Regulatory Authority shall serve full time and shall file a statement of financial interests with the Office of State Ethics in accordance with section 1-83. Each utility commissioner shall receive annually a salary equal to that established for management pay plan salary group seventy-five by the Commissioner of Administrative Services, except that the chairperson shall receive annually a salary equal to that established for management pay plan salary group seventy-seven.
(e) To insure the highest standard of public utility regulation, on and after October 1, 2007, any newly appointed utility commissioner of the authority shall have education or training and three or more years of experience in one or more of the following fields: Economics, engineering, law, accounting, finance, utility regulation, public or government administration, consumer advocacy, business management, and environmental management. On and after July 1, 1997, at least three of these fields shall be represented on the authority by individual utility commissioners at all times. Any time a utility commissioner is newly appointed, at least one of the utility commissioners shall have experience in utility customer advocacy.
(f) (1) The chairperson of the authority, with the approval of the Commissioner of Energy and Environmental Protection, shall prescribe the duties of the staff assigned to the authority in order to (A) conduct comprehensive planning with respect to the functions of the authority; (B) cause the administrative organization of the authority to be examined with a view to promoting economy and efficiency; and (C) organize the authority into such divisions, bureaus or other units as necessary for the efficient conduct of the business of the authority and may from time to time make recommendations to the Commissioner of Energy and Environmental Protection regarding staff and resources.
(2) The chairperson of the Public Utilities Regulatory Authority, in order to implement the comprehensive planning and organizational structure established pursuant to subdivision (1) of this subsection, shall (A) coordinate the activities of the authority and prescribe the duties of the staff assigned to the authority; (B) for any proceeding on a proposed rate amendment in which staff of the authority are to be made a party pursuant to section 16-19j, determine which staff shall appear and participate in the proceedings and which shall serve the members of the authority; (C) enter into such contractual agreements, in accordance with established procedures, as may be necessary for the discharge of the authority's duties; (D) subject to the provisions of section 4-32, and unless otherwise provided by law, receive any money, revenue or services from the federal government, corporations, associations or individuals, including payments from the sale of printed matter or any other material or services; and (E) require the staff of the authority to have expertise in public utility engineering and accounting, finance, economics, computers and rate design.
(g) No utility commissioner of the Public Utilities Regulatory Authority or employee of the Department of Energy and Environmental Protection assigned to work with the authority shall have any interest, financial or otherwise, direct or indirect, or engage in any business, employment, transaction or professional activity, or incur any obligation of any nature, which is in substantial conflict with the proper discharge of his or her duties or employment in the public interest and of his or her responsibilities as prescribed in the laws of this state, as defined in section 1-85, concerning any matter within the jurisdiction of the authority; provided, no such substantial conflict shall be deemed to exist solely by virtue of the fact that a utility commissioner of the authority or employee of the department assigned to work with the authority, or any business in which such a person has an interest, receives utility service from one or more Connecticut utilities under the normal rates and conditions of service.
(h) No utility commissioner of the Public Utilities Regulatory Authority or employee of the Department of Energy and Environmental Protection assigned to work with the authority, during such assignment, shall accept other employment which will either impair his or her independence of judgment as to his or her official duties or employment or require him or her, or induce him or her, to disclose confidential information acquired by him or her in the course of and by reason of his or her official duties.
(i) No utility commissioner of the Public Utilities Regulatory Authority or employee of the Department of Energy and Environmental Protection assigned to work with the authority, during such assignment, shall wilfully and knowingly disclose, for pecuniary gain, to any other person, confidential information acquired by him or her in the course of and by reason of his or her official duties or employment or use any such information for the purpose of pecuniary gain.
(j) No utility commissioner of the Public Utilities Regulatory Authority or employee of the Department of Energy and Environmental Protection assigned to work with the authority, during such assignment, shall agree to accept, or be in partnership or association with any person, or a member of a professional corporation or in membership with any union or professional association which partnership, association, professional corporation, union or professional association agrees to accept any employment, fee or other thing of value, or portion thereof, in consideration of his or her appearing, agreeing to appear, or taking any other action on behalf of another person before the authority, the Connecticut Siting Council, the Office of Policy and Management or the Commissioner of Energy and Environmental Protection.
(k) No utility commissioner of the Public Utilities Regulatory Authority shall, for a period of one year following the termination of his or her service as a utility commissioner, accept employment: (1) By a public service company or by any person, firm or corporation engaged in lobbying activities with regard to governmental regulation of public service companies; (2) by a certified telecommunications provider or by any person, firm or corporation engaged in lobbying activities with regard to governmental regulation of persons, firms or corporations so certified; or (3) by an electric supplier or by any person, firm or corporation engaged in lobbying activities with regard to governmental regulation of electric suppliers. No such utility commissioner who is also an attorney shall in any capacity, appear or participate in any matter, or accept any compensation regarding a matter, before the authority, for a period of one year following the termination of his or her service as a utility commissioner.
(l) The chairperson of the authority shall assign authority staff to fulfill the duties of procurement manager where required pursuant to this title and title 16a.
(m) Notwithstanding any provision of the general statutes, the decisions of the Public Utilities Regulatory Authority, including, but not limited to, decisions relating to rate amendments arising from the Comprehensive Energy Strategy, the Integrated Resources Plan, the Conservation and Load Management Plan and policies established by the Department of Energy and Environmental Protection, shall be guided by said strategy and plans and such policies.
(n) Two or more utility commissioners serving on a panel established pursuant to subsection (c) of this section may confer or communicate regarding the matter before such panel. Any such conference or communication that does not occur before the public at a hearing or proceeding shall not constitute a meeting as defined in section 1-200.
(1949, Rev., S. 5391; 1959, P.A. 383, S. 1; P.A. 74-216, S. 1, 8; P.A. 75-486, S. 3, 69; P.A. 77-614, S. 19, 67, 162, 589, 610; P.A. 78-303, S. 13, 136; P.A. 80-462, S. 1; P.A. 82-150, S. 1; P.A. 84-342, S. 4, 13; P.A. 85-552, S. 3, 8; P.A. 86-187, S. 4, 10; P.A. 89-291, S. 1, 8; P.A. 94-74, S. 1, 11; 94-77; P.A. 98-28, S. 78, 117; P.A. 99-248, S. 1, 3; 99-286, S. 3, 19; P.A. 00-112, S. 4, 5; P.A. 02-89, S. 22; P.A. 07-242, S. 57; P.A. 11-80, S. 1, 15; P.A. 13-244, S. 25; 13-298, S. 3; June Sp. Sess. P.A. 15-5, S. 466; P.A. 19-117, S. 79, 80.)
History: 1959 act provided appointment of members be subject to the consent of either house of the general assembly rather than both, provided for minority representation and added provision that appointment procedure of Sec. 4-7 is generally applicable; P.A. 74-216 increased membership from three to five members with not more than three of the same political party, rather than two, reduced terms from six to five years, deleted reference to appointment in odd-numbered years, added provision to cover terms during transition period and added Subsecs. (b) and (c); P.A. 75-486 amended section to replace public utilities commission with public utilities control authority, requiring consent of both houses rather than either house for appointments, increasing terms to six years and providing for transition period and added Subsecs. (d) to (k); P.A. 77-614 replaced personnel policy board with commissioner of administrative services in Subsec. (d), replaced “Connecticut energy agency”, i.e. department of planning and energy policy, with office of policy and management and, effective January 1, 1979, replaced public utilities control authority with division of public utility control within the department of business regulation and revised appointment provisions in Subsec. (a) to cover transition period; P.A. 78-303 restored public utilities control authority; P.A. 80-462 replaced former Subsec. (k) re applicability of Secs. 1-69 to 1-78 with new provisions re employment by public service company after serving as commissioner; P.A. 82-150 updated provisions re appointment of members and election of officers transferred the provisions of Sec. 16-50 to Subsec. (f) and made other technical changes; P.A. 84-342 established position of executive director in Subsec. (f) and replaced “staff” of the authority with “employee of the department” in Subsecs. (g), (h), (i) and (j); P.A. 85-552 amended Subsec. (k) to prohibit any commissioner from accepting employment with entity engaged in lobbying with regard to regulation of public service companies; P.A. 86-187 replaced power facility evaluation council with Connecticut siting council in Subsec. (j); P.A. 89-291 updated salary group references for commissioners in Subsec. (d) and for the chairpersons in Subsec. (f); P.A. 94-74 amended Subsec. (k) by adding provision restricting commissioner's employment by persons, firms or corporations certified to provide intrastate telecommunication services, effective July 1, 1994; P.A. 94-77 amended Subsec. (e) by adding “prior to July 1, 1997,” in Subdiv. (1) and adding Subdiv. (2) re standards for commissioners on and after July 1, 1997; P.A. 98-28 amended Subsec. (k) by rearranging language, deleting obsolete provisions and adding electric suppliers, effective July 1, 1998; P.A. 99-248 amended Subsec. (d) to increase the salary of commissioners from group seventy-four to group seventy-five, to increase the salary of the chairman from group seventy-six to group seventy-seven and to make a technical change, effective July 1, 1999; P.A. 99-286 amended Subsec. (k)(2) by changing reference to person, firm or corporation certified by the department to “certified telecommunications provider”, effective July 19, 1999; P.A. 00-112 amended Subsec. (d) to make a technical change, effective May 26, 2000; P.A. 02-89 amended Subsec. (e) to delete as obsolete former Subdiv. (1) re qualifications for commissioners prior to July 1, 1997, and to delete Subdiv. (2) designator; P.A. 07-242 amended Subsec. (e) to change qualifications from applying on and after July 1, 1997, to at least three commissioners, to on and after October 1, 2007, to any newly appointed commissioner and to provide that any time a commissioner is newly appointed, at least one commissioner shall have experience in utility customer advocacy; P.A. 11-80 amended Subsec. (a) to change “Public Utilities Control Authority” to “Public Utilities Regulatory Authority within the Department of Energy and Environmental Protection”, reduce number of electors from 5 to 3 and number of members from same political party from 3 to 2, replace former member appointment criteria with requirements re staggered terms for initial appointments and 4-year terms thereafter and end term for any commissioner serving on June 30, 2011, amended Subsec. (c) to reduce panel size from 3 to “one or more”, delete provisions re appointment of examiner and referral to entire authority and add provisions re request for hearing officer appointment and approval by majority vote, amended Subsec. (f) to delete provisions re executive director appointment and duties and add provisions re chairperson duties re authority staff with approval of Commissioner of Energy and Environmental Protection, amended Subsecs. (g) to (j) to add references to department employees “assigned to work with the authority”, changed “commissioner” and “commissioners” to “director” and “directors” throughout and made technical changes, effective July 1, 2011; P.A. 13-244 amended Subsec. (d) to replace provision re financial disclosure filed with Secretary of the State with provision re statement of financial interests filed with Office of State Ethics; P.A. 13-298 amended Subsec. (c) to replace “request the appointment of” with “may assign” re hearing officer and to replace “majority vote of the panel” with “majority vote of the utility commissioners”, amended Subsec. (f) by dividing existing provisions into new Subdivs. (1) and (2) and making technical changes therein, deleting former Subdiv. (2) re coordinating the activities of the authority and, in new Subdiv. (2), adding provision re chairperson of the authority implementing comprehensive planning and organizational structure and coordinating activities of the authority, amended Subsec. (g) to delete provision re conflict of interest while serving as utility commissioner and add provision re conflict of interest concerning any matter within the authority's jurisdiction, added Subsec. (m) re authority's decision guided by strategy, plans and policies, and replaced “director” with “utility commissioner” and made technical changes throughout, effective July 8, 2013; June Sp. Sess. P.A. 15-5 added Subsec. (n) re conference or communication between utility commissioners serving on a panel, effective June 30, 2015; P.A. 19-117 amended Subsec. (a) by changing number of members from 3 to 5, changing maximum number of members in office from one political party from 2 to 3, deleting provision re appointment on or before July 1, 2011, changing number of members appointed by Governor from 3 to 5, adding provision re procedure in Sec. 4-7, deleting provisions re commissioners appointed on or before July 1, 2011, adding provisions re terms for commissioners appointed and confirmed between February 1, 2019 and June 1, 2019, adding provisions re terms for commissioners appointed and confirmed between February 1, 2018 and June 1, 2018, adding provisions re appointment of commissioners between July 1, 2019 and May 1, 2020, replacing “January 1, 2014” with “May 1, 2020”, deleting provisions re procedures in section 4-7 and deleting provision re term of commissioners serving on June 30, 2011, amended Subsec. (c) by changing number of commissioners that may be assigned to a panel from 1 or more to 3 or more and changing number of panel members that may be designated to conduct a hearing from 1 or 2 to 1 or more, amended Subsec. (l) by deleting provisions re inclusion of a procurement manager and duties of procurement manager and adding provisions re the chairperson of authority assigning staff to fulfill duties of procurement manager where required and made technical changes, effective July 1, 2019.
Cited. 136 C. 314; 171 C. 387; 183 C. 128; 184 C. 1; 210 C. 349; 234 C. 624.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-2a. Office of Consumer Counsel. Office of State Broadband. Consumer Counsel. Staff. (a) There shall be an independent Office of Consumer Counsel, within the Department of Energy and Environmental Protection, for administrative purposes only, to act as the advocate for consumer interests in all matters which may affect Connecticut consumers with respect to public service companies, electric suppliers and certified telecommunications providers, including, but not limited to, rates and related issues, ratepayer-funded programs and matters concerning the reliability, maintenance, operations, infrastructure and quality of service of such companies, suppliers and providers. The Office of Consumer Counsel is authorized to appear in and participate in any regulatory or judicial proceedings, federal or state, in which such interests of Connecticut consumers may be involved, or in which matters affecting utility services rendered or to be rendered in this state may be involved. The Office of Consumer Counsel shall be a party to each contested case before the Public Utilities Regulatory Authority and shall participate in such proceedings to the extent it deems necessary. Said Office of Consumer Counsel may appeal from a decision, order or authorization in any such state regulatory proceeding notwithstanding its failure to appear or participate in said proceeding.
(b) Except as prohibited by the provisions of section 4-181, the Office of Consumer Counsel shall have access to the records of the Public Utilities Regulatory Authority and shall be entitled to call upon the assistance of the authority's and the department's experts, and shall have the benefit of all other facilities or information of the authority or department in carrying out the duties of the Office of Consumer Counsel, except for such internal documents, information or data as are not available to parties to the authority's proceedings. The department shall provide such space as necessary within the department's quarters for the operation of the Office of Consumer Counsel, and the department shall be empowered to set regulations providing for adequate compensation for the provision of such office space.
(c) There shall be established an Office of State Broadband within the Office of Consumer Counsel. The Office of State Broadband shall work to facilitate the availability of broadband access to every state citizen and to increase access to and the adoption of ultra-high-speed gigabit capable broadband networks. The Office of Consumer Counsel may work in collaboration with public and nonprofit entities and state agencies, and may provide advisory assistance to municipalities, local authorities and private corporations for the purpose of maximizing opportunities for the expansion of broadband access in the state and fostering innovative approaches to broadband in the state, including the procurement of grants for such purpose. The Office of State Broadband shall include a Broadband Policy Coordinator and such other staff as the Consumer Counsel deems necessary to perform the duties of the Office of State Broadband.
(d) The Office of Consumer Counsel shall be under the direction of a Consumer Counsel, who shall be appointed by the Governor with the advice and consent of either house of the General Assembly. The Consumer Counsel shall be an elector of this state and shall have demonstrated a strong commitment and involvement in efforts to safeguard the rights of the public. The Consumer Counsel shall serve for a term of five years unless removed pursuant to section 16-5. The salary of the Consumer Counsel shall be equal to that established for management pay plan salary group seventy-one by the Commissioner of Administrative Services. No Consumer Counsel shall, for a period of one year following the termination of service as Consumer Counsel, accept employment by a public service company, a certified telecommunications provider or an electric supplier. No Consumer Counsel who is also an attorney shall in any capacity, appear or participate in any matter, or accept any compensation regarding a matter, before the Public Utilities Regulatory Authority, for a period of one year following the termination of service as Consumer Counsel.
(e) The Consumer Counsel shall hire such staff as necessary to perform the duties of said Office of Consumer Counsel and may employ from time to time outside consultants knowledgeable in the utility regulation field including, but not limited to, economists, capital cost experts and rate design experts. The salaries and qualifications of the individuals so hired shall be determined by the Commissioner of Administrative Services pursuant to section 4-40.
(f) Nothing in this section shall be construed to prevent any party interested in such proceeding or action from appearing in person or from being represented by counsel therein.
(g) As used in this section, “consumer” means any person, city, borough or town that receives service from any public service company, electric supplier or from any certified telecommunications provider in this state whether or not such person, city, borough or town is financially responsible for such service.
(h) The Office of Consumer Counsel shall not be required to post a bond as a condition to presenting an appeal from any state regulatory decision, order or authorization.
(i) The expenses of the Office of Consumer Counsel shall be assessed in accordance with the provisions of section 16-49.
(P.A. 74-216, S. 6, 8; P.A. 75-486, S. 11, 69; P.A. 76-180, S. 1; 76-335, S. 2; P.A. 77-614, S. 67, 162, 164, 587, 610; P.A. 78-303, S. 85, 136; P.A. 80-462, S. 2; 80-482, S. 340, 348; P.A. 84-342, S. 5, 13; P.A. 88-22, S. 2; P.A. 89-291, S. 2, 8; P.A. 94-74, S. 2, 11; P.A. 95-79, S. 48, 189; P.A. 98-28, S. 79, 117; P.A. 99-248, S. 2, 3; 99-286, S. 4, 19; P.A. 00-53, S. 1; P.A. 01-49, S. 2; P.A. 11-80, S. 1, 16; P.A. 12-148, S. 9; June Sp. Sess. P.A. 15-5, S. 420.)
History: P.A. 75-486 greatly expanded provisions re office of consumer counsel and made office an independent agency, previously it had been “within the public utilities commission”; P.A. 76-180 added appeal provision in Subsec. (a) and added Subsec. (g) re exemption from bond requirement; P.A. 76-335 added Subsec. (h) re expenses; P.A. 77-614 and P.A. 78-303 replaced personnel policy board with commissioner of administrative services and, effective January 1, 1979, replaced public utilities control authority with division of public utility control within the department of business regulation and made office of consumer counsel a division within that department; P.A. 80-462 added provisions in Subsec. (c) re employment of consumer counsel by public service company after termination of service; P.A. 80-482 made division of consumer counsel a division within department of public utility control (formerly division of public utility control) rather than within department of business regulation which was abolished; P.A. 84-342 added references to department of public utility control, in the process transferring certain duties formerly held by authority to the department in Subsec. (b); P.A. 88-22 substituted the office of consumer counsel for the division of consumer counsel; P.A. 89-291 added provision in Subsec. (a) providing consumer counsel with automatic party status in each contested case before the department and updated the salary group reference for the consumer counsel in Subsec. (c); P.A. 94-74 amended Subsecs. (a), (c) and (f) by adding provisions re persons, firms or corporations certified to provide intrastate telecommunication services, effective July 1, 1994; P.A. 95-79 amended Subsec. (f) to redefine “consumer” to include a limited liability company, effective May 31, 1995; P.A. 98-28 amended Subsecs. (a), (c) and (f) by adding electric suppliers and made technical changes in Subsec. (c), effective July 1, 1998; P.A. 99-248 amended Subsec. (c) to increase the salary of the Consumer Counsel from group seventy to group seventy-one and to make technical changes, effective July 1, 1999; P.A. 99-286 amended Subsec. (a) by changing reference to persons, firms and corporations certified or seeking to be certified to provide intrastate telecommunications service to “certified telecommunications providers” and amended Subsecs.(c) and (f) by changing references to person, firm or corporation certified to provide intrastate telecommunications service to “certified telecommunications provider” and deleting Subdiv. designators in Subsec. (c), effective July 19, 1999; P.A. 00-53 made technical changes in Subsec. (f); P.A. 01-49 amended Subsec. (f) to make a technical change; P.A. 11-80 amended Subsec. (a) to change “Department of Public Utility Control” to “Department of Energy and Environmental Protection” or “Public Utilities Regulatory Authority”, amended Subsec. (b) to delete reference to Department of Public Utility Control and change “Public Utilities Control Authority” to “Public Utilities Regulatory Authority” and amended Subsec. (d) to delete “he deems” re hiring staff as necessary, effective July 1, 2011; P.A. 12-148 amended Subsec. (a) to add provision re matters for which Office of Consumer Counsel shall act as advocate, effective June 15, 2012; June Sp. Sess. P.A. 15-5 added new Subsec. (c) re Office of State Broadband and redesignated existing Subsecs. (c) to (h) as Subsecs. (d) to (i), effective July 1, 2015.
See Sec. 4-38f for definition of “administrative purposes only”.
Cited. 176 C. 191; 216 C. 627; 219 C. 51; 234 C. 624; 235 C. 334. Provision that otherwise permits Office of Consumer Counsel to obtain judicial review is inconsistent with the scheme specified in the Cable Act and is therefore expressly preempted by 47 USC 556(c). 259 C. 56.
Cited. 3 CA 416.
Cited. 44 CS 21.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-2b. Term “Office of Consumer Counsel” deemed to mean Division of Consumer Counsel within the Department of Business Regulation. Section 16-2b is repealed.
(P.A. 77-614, S. 164, 610; P.A. 80-482, S. 346, 348.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-2c. Division of Adjudication. There is established a Division of Adjudication within the Public Utilities Regulatory Authority. The staff of the division shall include, but not be limited to, hearing officers appointed pursuant to subsection (c) of section 16-2. The responsibilities of the division shall include, but not be limited to, hearing matters assigned under said subsection and advising the Public Utilities Regulatory Authority concerning legal issues. A panel of one or more utility commissioners may assign a hearing officer pursuant to section 16-2, and the chairperson of the Public Utilities Regulatory Authority may assign such other staff as are necessary to advise said chairperson.
(P.A. 84-342, S. 8, 13; P.A. 11-80, S. 17; P.A. 13-298, S. 4.)
History: P.A. 11-80 changed “Department of Public Utility Control” to “Department of Energy and Environmental Protection”, changed “chairperson of the Public Utilities Control Authority” to “commissioner and the Public Utilities Regulatory Authority”, changed “hearing examiners” to “hearing officers”, and required commissioner to appoint hearing officers and assign such other staff as necessary, effective July 1, 2011; P.A. 13-298 replaced “Department of Energy and Environmental Protection” with “Public Utilities Regulatory Authority” and “The commissioner shall appoint such hearing officers” with “A panel of one or more utility commissioners may assign a hearing officer”, added provision re chairperson of authority assigning other staff and made technical changes, effective July 8, 2013.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-2d. Office of energy efficient businesses. There is established within the Department of Energy and Environmental Protection, within available appropriations, an office of energy efficient businesses. The office shall provide in-state businesses (1) a single point of contact for any state business interested in energy efficiency, renewable energy or conservation projects, (2) information on loans and grants for energy efficiency, renewable energy projects and conservation, (3) audit and assessment services, including, but not limited to, on-site outreach to businesses by qualified entities without a commercial interest in the outcome of the audit, and (4) any other service deemed relevant by said office.
(P.A. 11-80, S. 119.)
History: P.A. 11-80 effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-3. Vacancy. If any vacancy of a utility commissioner occurs in the Public Utilities Regulatory Authority at any time when the General Assembly is not in session, the Governor shall appoint a utility commissioner to fill such vacancy until such vacancy is filled at the next session of the General Assembly.
(1949 Rev., S. 5392; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 78-303, S. 79, 136; P.A. 11-80, S. 18; P.A. 13-298, S. 5.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 would have replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979, except for action of P.A. 78-303 which retained reference to authority in this section; P.A. 11-80 changed “Public Utilities Control Authority” to “Public Utilities Regulatory Authority” and “commissioner” to “director”, effective July 1, 2011; P.A. 13-298 added “of a utility commissioner” re vacancy, replaced “director” with “utility commissioner”, deleted provision re filling any other vacancy and made a technical change, effective July 8, 2013.
Read together with Sec. 4-1, this section provides that, on failure of General Assembly to act on nomination submitted by the Governor, the incumbent commissioner holds over as a de jure officer. 136 C. 312.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-3a. Appointment of initial members. Transfer of business between commission and authority. Obsolete.
(P.A. 75-486, S. 21, 69; July Sp. Sess. P.A. 75-1, S. 1, 2; P.A. 77-614, S. 162, 610; P.A. 78-303, S. 79, 136.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-4. Employees of public service companies, certified telecommunications providers and electric suppliers ineligible to serve on authority or in department. No officer, employee, attorney or agent of any public service company, of any certified telecommunications provider or of any electric supplier shall be a member of the Public Utilities Regulatory Authority or an employee of the Department of Energy and Environmental Protection.
(1949 Rev., S. 5393; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 78-303, S. 79, 136; P.A. 84-342, S. 6, 13; P.A. 94-74, S. 3, 11; P.A. 98-28, S. 80, 117; P.A. 99-286, S. 5, 19; P.A. 11-80, S. 19.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 would have replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979, except for action of P.A. 78-303 which retained reference to authority in this section; P.A. 84-342 added reference to the department of public utility control; P.A. 94-74 added provision re persons, firms or corporations certified to provide intrastate telecommunication services, effective July 1, 1994; P.A. 98-28 rearranged language, deleted an obsolete provision and added electric suppliers, effective July 1, 1998; P.A. 99-286 changed reference to person, firm or corporation certified by the department to “certified telecommunications provider”, effective July 19, 1999; P.A. 11-80 changed “Public Utilities Control Authority” to “Public Utilities Regulatory Authority” and “Department of Public Utility Control” to “Department of Energy and Environmental Protection”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-5. Removal. Misconduct, material neglect of duty, incompetence in the conduct of his office or active participation in political management or campaigns by any commissioner shall constitute cause for removal. Such removal shall be made only after judgment of the Superior Court rendered upon written complaint of the Attorney General. The Attorney General may file such complaint in his discretion and shall file such complaint if so directed by the Governor. Upon the filing of such complaint, a rule to show cause shall issue to the accused, who may make any proper answer within such time as the court may limit and shall have the right to be heard in his own defense and by witnesses and counsel. The procedure upon such complaint shall be similar to that in civil actions, but such complaint shall be privileged in order of trial and shall be heard as soon as practicable. If, after hearing, the court finds cause for removal, it shall render judgment to that effect, and thereupon the office of such commissioner shall become vacant.
(1949 Rev., S. 5394.)
Continued violation of statutory duty would constitute material neglect of duty. 111 C. 639. Statute does not violate due process. Id., 647. Former provision required Attorney General to file complaint on petition of one hundred electors alleging facts not manifestly untrue. 112 C. 586.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-6. Office and records. The Public Utilities Regulatory Authority shall keep its office open during the usual business hours and shall keep all of its records in such office. The authority shall keep a record of all communications addressed to it, or to any of its members or employees, officially, of all its and their official acts and proceedings and of all facts learned in relation to any casualty or accident, with the names of the persons from whom such facts were obtained or by whom they may be proved.
(1949 Rev., S. 5395; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 41, 348; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
Cited. 170 C. 9.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-6a. Participation in proceedings before federal agencies and federal courts. Expenses. (a) The Public Utilities Regulatory Authority and the Office of Consumer Counsel are authorized to participate in proceedings before agencies of the federal government and the federal courts on matters affecting utility services rendered or to be rendered in this state.
(b) For any proceeding before the Federal Energy Regulatory Commission, the United States Department of Energy or the United States Nuclear Regulatory Commission, or appeal thereof, the Attorney General, upon request of the authority, may retain outside legal counsel in accordance with section 3-125 to participate in such proceedings on behalf of the authority. All reasonable and proper expenses of such outside legal counsel shall be borne by the public service companies, certified telecommunications providers, electric suppliers or gas registrants that are affected by the decisions of such proceedings and shall be paid at such times and in such manner as the authority directs, provided such expenses shall be apportioned in proportion to the revenues of each affected entity as reported to the authority for purposes of section 16-49 for the most recent period, and provided further such expenses shall not exceed two hundred fifty thousand dollars per proceeding, including any appeals thereof, in any calendar year unless the authority finds good cause for exceeding the limit and the affected entities have an opportunity, after reasonable notice, to comment on the proposed overage. All such legal expenses shall be recognized by the authority as proper business expenses of the affected entities for rate-making purposes, as provided in section 16-19e, if applicable.
(c) For any proceeding before the Federal Energy Regulatory Commission, the United States Department of Energy, the United States Nuclear Regulatory Commission, the Securities and Exchange Commission, the Federal Trade Commission, the United States Department of Justice or the Federal Communications Commission, or appeal thereof, the Attorney General, upon request of the Office of Consumer Counsel, may retain outside legal counsel in accordance with section 3-125 to participate in such proceedings on behalf of the office, provided the work performed on behalf of the office shall not include lobbying activities, as defined in 2 USC 1602. All reasonable and proper expenses of such outside legal counsel shall be borne by the public service companies, certified telecommunications providers, electric suppliers or gas registrants that are affected by the decisions of such proceedings and shall be paid at such times and in such manner as the office directs, provided such expenses shall be apportioned in proportion to the revenues of each affected entity as reported to the authority for purposes of section 16-49 for the most recent period, and provided further such expenses shall not exceed two hundred fifty thousand dollars, including any appeals thereof, in any calendar year. The Public Utilities Regulatory Authority shall recognize all such legal expenses as proper business expenses of the affected entities for rate-making purposes, as provided in section 16-19e, if applicable.
(1963, P.A. 167; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 42, 348; P.A. 97-3, S. 1, 2; P.A. 00-107, S. 1, 3; P.A. 05-264, S. 1; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 97-3 designated existing language as Subsec. (a) and added language re federal courts, and added Subsec. (b) re the retention of outside legal counsel, effective February 14, 1997; P.A. 00-107 amended Subsec. (b) by adding reference to United States Department of Energy, by adding certified telecommunications providers, electric suppliers and gas registrants to the entities required to pay expenses of legal counsel and by making conforming technical changes, effective May 26, 2000; P.A. 05-264 amended Subsec. (a) to add reference to the Office of Consumer Counsel, made a technical change in Subsec. (b) and added Subsec. (c) re retention of outside legal counsel on behalf of the Office of Consumer Counsel; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-6b. Regulations. The Public Utilities Regulatory Authority may, in accordance with chapter 54, adopt such regulations with respect to: (1) Rates and charges, services, accounting practices, safety and the conduct of operations generally of public service companies subject to its jurisdiction as it deems reasonable and necessary; (2) services, accounting practices, safety and the conduct of operations generally of electric suppliers subject to its jurisdiction as it deems reasonable and necessary; and (3) standards for systems utilizing cogeneration technology and renewable fuel resources, in accordance with the Department of Energy and Environmental Protection's policies.
(P.A. 73-342, S. 1, 2; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 43, 348; P.A. 81-439, S. 3, 14; P.A. 98-28, S. 81, 117; P.A. 11-80, S. 1, 20; P.A. 13-298, S. 6.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 81-439 authorized department to adopt regulations establishing standards for systems utilizing cogeneration technology and renewable fuel resources; P.A. 98-28 added provision authorizing the adoption of regulations with respect to electric suppliers, effective July 1, 1998; P.A. 11-80 replaced “Department of Public Utility Control” with “Public Utilities Regulatory Authority, in consultation with the Department of Energy and Environmental Protection”, specified that department may adopt regulations in consultation with the authority and made a technical change, effective July 1, 2011; P.A. 13-298 added Subdiv. (1), (2) and (3) designators and made conforming changes, deleted references to Department of Energy and Environmental Protection and Office of Policy and Management and added provision re systems standards in accordance with department's policies, effective July 8, 2013.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-6c. Power to delay implementation of electric suppliers' generation portfolio standards. Section 16-6c is repealed, effective July 1, 2003.
(P.A. 99-225, S. 19, 33; P.A. 03-135, S. 24.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-7. Right of entry. Penalty. The utility commissioners of the Public Utilities Regulatory Authority, or their designees, while engaged in the performance of their duties may, at all reasonable times, enter any premises, buildings, cars, plants or other places belonging to or controlled by any public service company, electric supplier or person involved in the transportation of gas, as such terms are defined in section 16-280a, and any person obstructing or in any way causing to be obstructed or hindered any utility commissioner of the Public Utilities Regulatory Authority or employee of the Public Utilities Regulatory Authority in the performance of his or her duties shall be fined not more than ten thousand dollars or imprisoned not more than six months, or both.
(1949 Rev., S. 5397; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 587, 610; P.A. 78-303, S. 85, 136; P.A. 80-482, S. 44, 348; P.A. 98-28, S. 82, 117; P.A. 11-80, S. 1, 21; P.A. 13-298, S. 7; P.A. 22-20, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 and P.A. 78-303 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 98-28 added electric suppliers, effective July 1, 1998; P.A. 11-80 replaced “commissioners and any employees of the Department of Public Utility Control” with “directors and any employees of the department assigned to the Public Utilities Regulatory Authority” and made a technical change, effective July 1, 2011; P.A. 13-298 replaced “directors and any employees of the department assigned to” with “utility commissioners of” and added “or their designees” re utility commissioners, replaced “member” with “utility commissioner of the Public Utilities Regulatory Authority” and made technical and conforming changes, effective July 8, 2013; P.A. 22-20 added references to plants and persons involved in the transportation of gas and replaced “two hundred” with “ten thousand”.
Cited. 162 C. 51.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-7a. Power to stop work. The utility commissioners, as defined in section 16-1, or their designees, shall have the authority to cause any work performed by any person involved in the transportation of gas, as such terms are defined in section 16-280a, to cease immediately if said work may endanger any person.
(P.A. 22-20, S. 10.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-8. Examination of witnesses and documents. Hearing officers. Management audits. (a) The Public Utilities Regulatory Authority may, in its discretion, delegate its powers, in specific cases, to one or more of its directors or to a hearing officer to ascertain the facts and report thereon to the authority. The authority, or any director thereof, in the performance of its duties or in connection with any hearing, or at the request of any person, corporation, company, town, borough or association, may summon and examine, under oath, such witnesses, and may direct the production of, and examine or cause to be produced and examined, such books, records, vouchers, memoranda, documents, letters, contracts or other papers in relation to the affairs of any public service company or person involved in the transportation of gas, as such terms are defined in section 16-280a, as it may find advisable, and shall have the same powers in reference thereto as are vested in magistrates taking depositions. If any witness objects to testifying or to producing any book or paper on the ground that such testimony, book or paper may tend to incriminate him, and the authority directs such witness to testify or to produce such book or paper, and he complies, or if he is compelled so to do by order of court, he shall not be prosecuted for any matter concerning which he or she has so testified. The fees of witnesses summoned by the authority to appear before it under the provisions of this section, and the fees for summoning witnesses shall be the same as in the Superior Court. All such fees, together with any other expenses authorized by statute, the method of payment of which is not otherwise provided, shall, when taxed by the authority, be paid by the state, through the business office of the authority, in the same manner as court expenses. The authority may designate in specific cases a hearing officer who may be a member of its technical staff or a member of the Connecticut Bar engaged for that purpose under a contract approved by the Secretary of the Office of Policy and Management to hold a hearing and make report thereon to the authority. A hearing officer so designated shall have the same powers as the authority, or any director thereof, to conduct a hearing, except that only a director of the authority shall have the power to grant immunity from prosecution to any witness who objects to testifying or to producing any book or paper on the ground that such testimony, book or paper may tend to incriminate him or her.
(b) (1) The authority may employ professional personnel to perform management audits. The authority shall promptly establish such procedures as it deems necessary or desirable to provide for management audits to be performed on a regular or irregular schedule on all or any portion of the operating procedures and any other internal workings of any public service company or person involved in the transportation of gas, as such terms are defined in section 16-280a, including the relationship between any public service company or person involved in the transportation of gas, as such terms are defined in section 16-280a, and a related holding company or subsidiary, consistent with the provisions of section 16-8c, provided no such audit shall be performed on a community antenna television company, except with regard to any noncable communications services which the company may provide, or when (A) such an audit is necessary for the authority to perform its regulatory functions under the Communications Act of 1934, 47 USC 151, et seq., as amended from time to time, other federal law or state law, (B) the cost of such an audit is warranted by a reasonably foreseeable financial, safety or service benefit to subscribers of the company which is the subject of such an audit, and (C) such an audit is restricted to examination of the operating procedures that affect operations within the state.
(2) In any case where the authority determines that an audit is necessary or desirable, it may (A) order the audit to be performed by one of the management audit teams, (B) require the affected company or person to perform the audit utilizing the company's own internal management audit staff as supervised by designated members of the authority's staff or the person's own internal management audit staff as supervised by designated members of the authority's staff, or (C) require that the audit be performed under the supervision of designated members of the authority's staff by an independent management consulting firm selected by the authority, in consultation with the affected company or person. If the affected company or person has more than seventy-five thousand customers, such independent management consulting firm shall be of nationally recognized stature. All reasonable and proper expenses of the audits, including, but not limited to, the costs associated with the audit firm's testimony at a public hearing or other proceeding, shall be borne by the affected companies or persons and shall be paid by such companies or persons at such times and in such manner as the authority directs.
(3) For purposes of this section, a complete audit shall consist of (A) a diagnostic review of all functions of the audited company or person, which shall include, but not be limited to, documentation of the operations of the company or person, assessment of the company's system of internal controls or assessment of the person's system of internal controls, and identification of any areas of the company or person which may require subsequent audits, and (B) the performance of subsequent focused audits identified in the diagnostic review and determined necessary by the authority. All audits performed pursuant to this section shall be performed in accordance with generally accepted management audit standards. The authority shall adopt regulations in accordance with the provisions of chapter 54 setting forth such generally accepted management audit standards. Each audit of a community antenna television company shall be consistent with the provisions of the Communications Act of 1934, 47 USC 151, et seq., as amended from time to time, and of any other applicable federal law. The authority shall certify whether a portion of an audit conforms to the provisions of this section and constitutes a portion of a complete audit.
(4) A complete audit of each portion of each gas company or electric distribution company having more than seventy-five thousand customers shall begin no less frequently than every six years, so that a complete audit of such a company's operations shall be performed every six years. Such an audit of each such company having more than seventy-five thousand customers shall be updated as required by the authority.
(5) The results of an audit performed pursuant to this section shall be filed with the authority and shall be open to public inspection. Upon completion and review of the audit, if the person or firm performing or supervising the audit determines that any of the operating procedures or any other internal workings of the affected public service company or person involved in the transportation of gas, as such terms are defined in section 16-280a, are inefficient, improvident, unreasonable, negligent or in abuse of discretion, the authority may, after notice and opportunity for a hearing, order the affected public service company or person involved in the transportation of gas, as such terms are defined in section 16-280a, to adopt such new or altered practices and procedures as the authority shall find necessary to promote efficient and adequate service to meet the public convenience and necessity. The authority shall annually submit a report of audits performed pursuant to this section to the joint standing committee of the General Assembly having cognizance of matters relating to public utilities which report shall include the status of audits begun but not yet completed and a summary of the results of audits completed. Any such report may be submitted electronically.
(6) All reasonable and proper costs and expenses, as determined by the authority, of complying with any order of the authority pursuant to this subsection shall be recognized by the authority for all purposes as proper business expenses of the affected company or person.
(7) After notice and hearing, the authority may modify the scope and schedule of a management audit of a telephone company which is subject to an alternative form of regulation so that such audit is consistent with that alternative form of regulation.
(c) Nothing in this section shall be deemed to interfere or conflict with any powers of the authority or its staff provided elsewhere in the general statutes, including, but not limited to, the provisions of this section and sections 16-7, 16-28 and 16-32, to conduct an audit, investigation or review of the books, records, plants and equipment of any regulated public service company or person involved in the transportation of gas, as such terms are defined in section 16-280a.
(1949 Rev., S. 5398; P.A. 73-355, S. 2; P.A. 75-486, S. 6, 69; P.A. 77-614, S. 19, 162, 587, 610; P.A. 78-303, S. 85, 136; P.A. 80-168; 80-482, S. 4, 40, 45, 345, 348; P.A. 81-348, S. 1; P.A. 82-472, S. 50, 183; P.A. 85-509, S. 2, 11; 85-552, S. 4, 8; P.A. 90-221, S. 2, 15; P.A. 94-229, S. 1; P.A. 97-23; P.A. 98-28, S. 83, 117; June Sp. Sess. P.A. 98-1, S. 5, 121; P.A. 11-80, S. 1, 23; P.A. 13-5, S. 2; P.A. 13-119, S. 1, 2; P.A. 14-134, S. 48; P.A. 22-20, S. 2.)
History: P.A. 73-355 specified that hearing examiners may be staff member or member of Connecticut bar; P.A. 75-486 replaced public utilities commission with public utilities control authority, allowed authority to act at request of person, corporation, company, town, borough or association and added Subsec. (b) re audits; P.A. 77-614 and P.A. 78-303 replaced commissioner of finance and control with secretary of the office of policy and management and, effective January 1, 1979, replaced public utilities control authority with division of public utility control within the department of business regulation; P.A. 80-168 replaced “member(s)” with “commissioner(s)”, and “secretary” with “business office”, allowed delegation of powers to hearing examiners and replaced provision whereby hearing examiner had power only to administer oaths with provision granting examiners same powers as division except power to grant immunity from prosecution; P.A. 80-482 made division an independent department with public utilities control authority as its head; P.A. 81-348 reduced number of consulting firms required to be included in list provided to company by department in Subsec. (b), from five to three; P.A. 82-472 made technical corrections; P.A. 85-509 divided Subsec. (b) into Subsecs. (b) and (c) and, in Subsec. (b), prohibited management audits of community antenna television companies except with regard to noncable communications services; P.A. 85-552 amended Subsec. (b) to require department, instead of affected company, to select consulting firm for management audit, to require consulting firm to be of nationally-recognized stature if affected company has more than 75,000 customers and to require periodic audits only of gas, electric and telephone companies having more than 75,000 customers; P.A. 90-221 in Subsec. (b) added provision that the affected companies shall pay all reasonable and proper costs of an audit, including the costs of the audit firm's testimony at a public hearing and a provision that such costs shall be paid as directed by the department; P.A. 94-229 amended Subsec. (b) by adding Subdiv. designations, adding provision re relationship between public service company and related holding company or subsidiary in Subdiv. (1), adding Subparas. (A) to (C) re audits of community antenna television companies in Subdiv. (1), changing subdivision designations to subparagraph designations in Subdiv. (2), deleting provision re audits of gas, electric or telephone companies having more than 75,000 customers from Subdiv. (2), adding Subdiv. (3) re complete audits, adding Subdiv. (4) re audits of gas, electric and telephone companies having more than 75,000 customers, changing “any such audits” to “an audit performed pursuant to this section” in Subdiv. (5), adding provision re report of audits in Subdiv. (5), and adding Subdiv. (7) re audits of telephone companies subject to an alternative form of regulation; P.A. 97-23 amended Subsec. (b)(4) to delete references to telephone companies and delete provision requiring department to schedule complete audits; P.A. 98-28 amended Subsec. (b)(4) by adding electric distribution companies, effective July 1, 1998; June Sp. Sess. P.A. 98-1 made a technical change to Subsec. (b)(5), effective June 24, 1998; P.A. 11-80 amended Subsecs. (a) and (b) to replace “Department of Public Utility Control” with “Public Utilities Regulatory Authority”, “department” with “authority” and “hearing examiner” with “hearing officer” and amended Subsec. (b)(1) to replace provision allowing Department of Public Utility Control to establish management audit teams with provision allowing authority, within available appropriations, to employ personnel to perform management audits, effective July 1, 2011; pursuant to P.A. 11-80, “department” was changed editorially by the Revisors to “authority” in Subsec. (c), effective July 1, 2011; P.A. 13-5 amended Subsecs. (a) and (b)(3) to replace “department” with “authority”, effective May 8, 2013; P.A. 13-119 amended Subsec. (b) to delete “within available appropriations,” re employment of professional personnel to perform management audits in Subdiv. (1) and to add provision re electronic submission of report in Subdiv. (5), effective June 18, 2013; P.A. 14-134 amended Subsec. (b)(4) by deleting reference to electric company and making a technical change, effective June 6, 2014; P.A. 22-20 amended Subsecs. (a), (b) and (c) by adding references to person involved in the transportation of gas as defined in Sec. 16-280a, amended Subsec. (b) by adding “or person” and “or persons” after instances of “company” or “companies”, adding reference to the person's own internal management audit staff in Subdiv. (2), adding reference to assessment of the person's system of internal controls in Subdiv. (3), and making a technical change in Subsec. (c).
See Sec. 52-260 re witness fees.
Cited. 162 C. 51; 210 C. 349.
Cited. 44 CS 21.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-8a. Protection of employee of public service company, person involved in the transportation of gas, contractor or Nuclear Regulatory Commission from retaliation. Procedures. Regulations. (a) No public service company, as defined in section 16-1, holding company, as defined in section 16-47, person involved in the transportation of gas, as such terms are defined in section 16-280a, or Nuclear Regulatory Commission licensee operating a nuclear power generating facility in this state, or person, firm, corporation, contractor or subcontractor directly or indirectly providing goods or services to such public service company, holding company, person involved in the transportation of gas or licensee, may take or threaten to take any retaliatory action against an employee for the employee's disclosure of (1) any matter involving the substantial misfeasance, malfeasance or nonfeasance in the management of such public service company, holding company, person involved in the transportation of gas or licensee, or (2) information pursuant to section 31-51m. Any employee found to have knowingly made a false disclosure shall be subject to disciplinary action by the employee's employer, up to and including dismissal.
(b) Any employee of such a public service company, holding company, person involved in the transportation of gas or licensee, or of any person, firm, corporation, contractor or subcontractor directly or indirectly providing goods or services to such a public service company, holding company, person involved in the transportation of gas or licensee, having knowledge of any of the following may transmit all facts and information in the employee's possession to the Public Utilities Regulatory Authority: (1) Any matter involving substantial misfeasance, malfeasance or nonfeasance in the management of such public service company, holding company, person involved in the transportation of gas or licensee; or (2) any matter involving retaliatory action or the threat of retaliatory action taken against an employee who has reported the misfeasance, malfeasance or nonfeasance, in the management of such public service company, holding company, person involved in the transportation of gas or licensee. With regard to any matter described in subdivision (1) of this subsection, the authority shall investigate such matter in accordance with the provisions of section 16-8 and shall not disclose the identity of such employee without the employee's consent unless it determines that such disclosure is unavoidable during the course of the investigation. With regard to any matter described in subdivision (2) of this subsection, the matter shall be handled in accordance with the procedures set forth in subsections (c) and (d) of this section.
(c) (1) Not more than ninety business days after receipt of a written complaint, in a form prescribed by the authority, by an employee alleging the employee's employer has retaliated against an employee in violation of subsection (a) of this section, the authority shall make a preliminary finding in accordance with this subsection.
(2) Not more than five business days after receiving a written complaint, in a form prescribed by the authority, the authority shall notify the employer by certified mail. Such notification shall include a description of the nature of the charges and the substance of any relevant supporting evidence. The employer may submit a written response and both the employer and the employee may present rebuttal statements in the form of affidavits from witnesses and supporting documents and may meet with the authority informally to respond verbally about the nature of the employee's charges. The authority shall consider in making its preliminary finding as provided in subdivision (3) of this subsection any such written and verbal responses, including affidavits and supporting documents, received by the authority not more than twenty business days after the employer receives such notice. Any such response received after twenty business days shall be considered by the authority only upon a showing of good cause and at the discretion of the authority. The authority shall make its preliminary finding as provided in subdivision (3) of this subsection based on information described in this subdivision, without a public hearing.
(3) Unless the authority finds by clear and convincing evidence that the adverse employment action was taken for a reason unconnected with the employee's report of substantial misfeasance, malfeasance or nonfeasance, there shall be a rebuttable presumption that an employee was retaliated against in violation of subsection (a) of this section if the authority finds that: (A) The employee had reported substantial misfeasance, malfeasance or nonfeasance in the management of the public service company, holding company, person involved in the transportation of gas or licensee; (B) the employee was subsequently discharged, suspended, demoted or otherwise penalized by having the employee's status of employment changed by the employee's employer; and (C) the subsequent discharge, suspension, demotion or other penalty followed the employee's report closely in time.
(4) If such findings are made, the authority shall issue an order requiring the employer to immediately return the employee to the employee's previous position of employment or an equivalent position pending the completion of the authority's full investigatory proceeding pursuant to subsection (d) of this section.
(d) Not later than thirty days after making a preliminary finding in accordance with the provisions of subsection (c) of this section, the authority shall initiate a full investigatory proceeding in accordance with the provisions of section 16-8, at which time the employer shall have the opportunity to rebut the presumption. The authority may issue orders, impose civil penalties, order payment of back pay or award attorneys' fees in a manner that conforms with the notice and hearing provisions in section 16-41 against a public service company, holding company, person involved in the transportation of gas or licensee or a person, firm, corporation, contractor or subcontractor directly or indirectly providing goods or services to such public service company, holding company, person involved in the transportation of gas or licensee, in order to enforce the provisions of this section.
(e) If an employee or former employee of such a public service company, holding company, person involved in the transportation of gas or licensee, or of a person, firm, corporation, contractor or subcontractor directly or indirectly providing goods or services to such a public service company, holding company, person involved in the transportation of gas or licensee, having knowledge of any matter involving the substantial misfeasance, malfeasance or nonfeasance in the management of such public service company, holding company, person involved in the transportation of gas or licensee, enters into an agreement with the employee's employer that contains a provision directly or indirectly discouraging the employee from presenting a written complaint or testimony concerning such misfeasance, malfeasance or nonfeasance in any legislative, administrative or judicial proceeding, such provision shall be void as against public policy.
(f) The Public Utilities Regulatory Authority shall adopt regulations, in accordance with chapter 54, to carry out the provisions of this section. Such regulations shall include the following: (1) The procedures by which a complaint may be brought pursuant to subsection (a) of this section; (2) the time period in which such a complaint may be brought; (3) the time period by which the authority shall render a decision pursuant to subsection (d) of this section; (4) the form on which written complaints shall be submitted to the authority by an employee pursuant to subsection (c) of this section; and (5) the requirement that a notice be posted in the workplace informing all employees of any public service company, holding company, person involved in the transportation of gas and licensee and of any person, firm, corporation, contractor or subcontractor directly or indirectly providing goods or services to a company or licensee, as defined in subsection (b) of this section, of their rights under this section, including the right to be reinstated in accordance with subsection (c) of this section.
(P.A. 85-245, S. 1; P.A. 89-88; P.A. 91-247, S. 1; P.A. 96-22, S. 1, 2; P.A. 97-60, S. 1, 2; P.A. 99-46, S. 1, 2; P.A. 11-80, S. 24; P.A. 13-119, S. 3; P.A. 22-20, S. 3.)
History: P.A. 89-88 included provisions re employees of a holding company, a Nuclear Regulatory Commission licensee, a contractor or a subcontractor and added new Subsec. (c) re department orders to enforce provisions of section; P.A. 91-247 added provision in Subsec. (a) authorizing persons having knowledge of “the discharge, discipline or penalizing of a person reporting the misfeasance, or nonfeasance of the company” to report the same to the department, in Subsec. (c) authorized the department to issue cease and desist orders and added a new Subsec. (d) requiring the department to adopt regulations to provide employees with information re rights relating to complaints against a company; P.A. 96-22 imposed January 1, 1997, deadline for the department to adopt regulations as provided for in Subsec. (d), effective April 29, 1996; P.A. 97-60 inserted new Subsec. (a) prohibiting retaliation against employees, relettered former Subsec. (a) as Subsec. (b) and restructured the language, deleted former Subsecs. (b) and (c), inserted new Subsec. (c) creating procedures for preliminary findings of retaliation and establishing presumptions, inserted new Subsec. (d) describing procedures for full investigatory proceedings, inserted new Subsec. (e) rendering certain agreements as void, and relettered former Subsec. (d) as Subsec. (f) and restructured language, effective May 27, 1997; P.A. 99-46 amended Subsec. (c) by deleting provisions re complaints pending on May 27, 1997, and requiring department to make finding based on sworn affidavits and verified documents without a public hearing in Subdiv. (1), by rewording language re notice to employer and preliminary findings in Subdiv. (2), authorizing employee to present rebuttal statements and respond verbally and changing to 20 the number of days a party can respond to department, by adding provision re adverse employment action taken for reason unconnected to misfeasance and changing Subpara. (c) criteria in Subdiv. (3), and by adding provision re pending completion of department's full investigatory proceeding in Subdiv. (4), amended Subsec. (d) by adding “Not later than thirty days”, and making technical changes, effective May 27, 1999; P.A. 11-80 replaced “Department of Public Utility Control” with “Public Utilities Regulatory Authority” and replaced “department” with “authority”, effective July 1, 2011; P.A. 13-119 amended Subsec. (c)(1) by changing from 30 to 90 the number of days before the authority must issue a preliminary finding and amended Subsec. (d) by adding provision re ordering of payment of back pay or awarding attorneys' fees, effective July 1, 2013; P.A. 22-20 amended Subsec. (a) by adding reference to person involved in the transportation of gas as defined in Sec. 16-280a, and added throughout references to person involved in the transportation of gas in provisions re employees of public service companies, holding companies, or Nuclear Regulatory Commission licensees.
See Sec. 16-8d re recovery of costs or expenses associated with any action brought under section 16-8a.
To the extent that section creates some right of action by a whistle-blower, it is a right against a power company and not against department or the state; section does not require a hearing when department investigates an employee's whistle-blower complaint against a nuclear power company and finds no merit to the complaint. 48 CS 188.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-8b. Labor disputes at public service companies. Determination of unreasonable profits during dispute. Refunds. Whenever a labor dispute at a public service company, as defined in section 16-1, results in a work stoppage for a period of more than seven days, the Public Utilities Regulatory Authority shall initiate a proceeding not later than thirty days after the termination of the labor dispute to determine whether the public service company, as a result of such work stoppage, earned unreasonable profits and whether the quality of service to the customers of such public service company was impaired. The authority may issue such remedial orders as may be necessary to protect ratepayers including, but not limited to, refunds or other adjustments.
(P.A. 87-82; P.A. 11-80, S. 1.)
History: Pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
Unreasonable profits, as determined by text and legislative history, are not measured by authorized rate of return pursuant to Sec. 16-247k, but by an incremental analysis that considers whether public utility earned profits as result of not paying labor costs at a time when service to customers was impaired. 274 C. 119.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-8c. Examination of witnesses and documents. Audits. Relationship between public service companies and subsidiaries. (a) The Public Utilities Regulatory Authority or any director or any hearing officer thereof may exercise the powers provided under subsection (a) of section 16-8, in relation to summoning and examining under oath, such witness and the production and examination of such books, records, vouchers, memoranda, documents, letters, contracts or other papers as it deems advisable of any holding company or subsidiary that is related to a public service company, provided such powers may be exercised in regard to (1) a holding company, only with respect to transactions between the holding company and a related public service company or transactions between the holding company and a subsidiary of such holding company which is not itself a public service company, which transactions are of the same type as transactions between such holding company and a related public service company, or (2) a subsidiary, only with respect to transactions between such subsidiary and a related public service company, and in either case only after having first determined that the exercise of such powers may be necessary to protect customers of the related public service company from any adverse impact on the costs, revenues, rates, charges or quality of service of such public service company.
(b) The authority may require the audit of (1) transactions between a public service company and a related holding company or subsidiary which is not itself a public service company, and (2) transactions between a related holding company and a subsidiary of such holding company which is not itself a public service company, which transactions are of the same type as transactions between such holding company and a related public service company, to the extent necessary to ensure that such transactions do not have an adverse impact on the costs or revenues of the public service company, the rates and charges paid by the customers of the public service company or upon the quality of service of such public service company. Upon completion of any audit conducted pursuant to this section, if the authority determines that any transactions which were the subject of such audit have had an adverse impact on the costs, revenues, rates, charges or quality of service of the public service company, the authority may exercise its powers under this title with respect to the public service company to ensure that the rates, charges and quality of service of the public service company conform to the principles and guidelines set forth in section 16-19e. The authority may disallow, for rate-making purposes, the costs of the audit, after first considering the reasons for the audit and any adverse impact on the customers of the public service company.
(c) Proprietary commercial and proprietary financial information of a holding company or subsidiary provided pursuant to this section shall be confidential and protected by the authority, subject to the provisions of section 4-177.
(d) For the purposes of this section, a subsidiary and a public service company are related if the subsidiary is owned or controlled by the public service company, a holding company thereof, a subsidiary of the public service company or holding company, or a subsidiary of such subsidiary. A holding company and a public service company are related if the public service company is owned or controlled by the holding company, a subsidiary of such holding company or a subsidiary of such subsidiary.
(e) As used in this section, (1) “holding company” means a company as defined in section 16-47, (2) “controlled” or “control” means the possession of the power to direct or cause the direction of the management and policies of a public service company, a holding company, or a subsidiary whether through the ownership of its voting securities, the ability to effect a change in the composition of its board of directors or otherwise, (3) “subsidiary” means any corporation, limited liability company, company, association, joint stock association, partnership, person or other entity which is owned or controlled, directly or indirectly, by a public service company, a holding company or a subsidiary of a public service company or holding company, and (4) “transactions” means cost allocations, capital structure, provision of goods and services, transfers of assets and liabilities, loans, financings, leases and other financial obligations.
(f) Nothing in this section shall be deemed to limit any existing statutory powers of the authority with respect to public service companies, holding companies or subsidiaries.
(g) The authority may conduct joint hearings with another agency including, but not limited to, the utility regulatory agency of another state on matters of mutual cognizance and interest.
(P.A. 88-198; P.A. 95-79, S. 49, 189; P.A. 11-80, S. 1.)
History: P.A. 95-79 amended Subsec. (h) to redefine “subsidiary” to include a limited liability company, effective May 31, 1995 (Revisor's note: A reference in Subsec. (b) to “title 16” was changed editorially by the Revisors to “this title” for consistency with customary statutory usage); pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-8d. Recovery of costs, expenses, judgments or attorney's fees for an action brought under section 16-8a. (a) No costs, expenses or judgments associated with any action brought under the provisions of section 16-8a may be included in the rates or charge of any public service company, as defined in section 16-1, until such time as the Public Utilities Regulatory Authority or the Labor Department, in a final decision, finds in favor of the company or if such action is appealed, until such time as the court finds, in a final decision, in favor of the company.
(b) In any action brought under the provisions of section 16-8a, which results in a judgment in favor of the plaintiff, the court shall award to the plaintiff, in addition to any other relief, costs and a reasonable attorney's fee based on the work reasonably performed by an attorney and not on the amount of recovery, and may award punitive damages.
(c) The provisions of subsections (a) and (b) of this section shall only apply to an action brought pursuant to section 16-8a by an employee of a Nuclear Regulatory Commission licensee operating a nuclear power generating facility in this state or by any person, firm, corporation, contractor or subcontractor directly or indirectly providing goods or services to such licensee.
(P.A. 91-247, S. 2; P.A. 92-194; P.A. 11-80, S. 1.)
History: P.A. 92-194 amended Subsec. (a) prohibiting the inclusion of judgments in the rates or charges of a public service company unless the public utility control department or labor department in a final decision finds in favor of the company and added Subsecs. (b) and (c) authorizing the awarding of attorney's fees and limiting the application of the section to actions brought against nuclear regulatory licensees; (Revisor's note: In 1997 a reference in Subsec. (a) to “Department of Labor” was changed editorially by the Revisors to “Labor Department” for consistency with statutory usage); pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority” in Subsec. (a), effective July 1, 2011.
Section provides a whole set of remedies for a cause of action that General Assembly failed to formulate; to the extent that Sec. 16-8a creates some right of action by a whistle-blower, it is a right against a power company and not against department or the state. 48 CS 188.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-9. Orders. All decisions, orders and authorizations of the Public Utilities Regulatory Authority shall be in writing and shall specify the reasons therefor, shall be filed and kept in the office of the authority and recorded in a book kept by it for that purpose and shall be public records. Said authority may, at any time, for cause shown, upon hearing had after notice to all parties in interest, rescind, reverse or alter any decision, order or authorization by it made. Written notice of all orders, decisions or authorizations issued by the authority shall be given to the company or person affected thereby, by personal service upon such company or person or by registered or certified mail, as the authority determines. Any final decision, order or authorization of the Public Utilities Regulatory Authority in a contested case shall constitute a final decision for the purposes of chapter 54.
(1949 Rev., S. 5399; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 587, 610; P.A. 78-303, S. 85, 136; P.A. 80-482, S. 46, 348; P.A. 88-297, S. 14; P.A. 11-80, S. 1, 22.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 and P.A. 78-303 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 88-297 substituted “records” for “documents”; P.A. 11-80 replaced “Department of Public Utility Control” with “Public Utilities Regulatory Authority” and added provision re final decision of authority in a contested case to constitute a final decision for purposes of chapter 54, effective July 1, 2011; pursuant to P.A. 11-80, “department” was changed editorially by the Revisors to “authority”, effective July 1, 2011.
Right to render conditional judgment. 41 C. 355. Provision as to notice held to be merely directory. 78 C. 301. Trial before commission on appeal to it from local authorities is de novo; dismissal of appeal because of finding in another, distinct appeal improper. 84 C. 24. Appearance before commission waives want of notice of proceeding. Id.; Id., 40. No formal pleadings necessary before commission. 86 C. 36. All orders must find their justification in public convenience, necessity or safety. 89 C. 528. Court may take judicial notice of regulations of commission. 113 C. 416. Section confers right to reopen and rehear. Id., 503. Cited. 132 C. 514. When commission must make findings of facts. 145 C. 243. If commission can reverse its decision for due cause, then, on a new application for the same privilege, it can reach a different result. Id., 617. Cited. 162 C. 51; 165 C. 114; 166 C. 328. Legislative selection of the words “the company or person” instead of “the companies or persons” suggests that it intended that the written notice requirement be limited to giving such notice to the applicant if the order were issued in response to an application, or, in other cases, to the party to whom the order was directed. 168 C. 478. Cited. 169 C. 344; 170 C. 3; 219 C. 51; Id., 121; Id., 168. Authority lacked jurisdiction to resolve capacity clearing price dispute pursuant to section; interpretation that section was intended to confer jurisdiction on authority to unilaterally alter a decision approving the form of a contract after private parties have agreed to its terms rejected as constitutionally suspect; nothing in section confers jurisdiction on authority to exercise equitable power to reform contract to conform to true intent of the parties. 319 C. 367.
Cited. 40 CS 520.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-9a. Party status in proceedings before authority. In a proceeding before the Public Utilities Regulatory Authority, the authority shall give special consideration to a request for party status from a person whose interests are not otherwise adequately represented by another party to the proceeding and shall not unreasonably deny such request.
(P.A. 96-247, S. 2; P.A. 11-80, S. 1.)
History: Pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-9b. Commissioner of Energy and Environmental Protection to be party to proceedings before authority. The Commissioner of Energy and Environmental Protection shall be a party to each proceeding before the Public Utilities Regulatory Authority and may participate in any such proceeding at said commissioner's discretion.
(P.A. 13-298, S. 9.)
History: P.A. 13-298 effective July 8, 2013.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-10. Enforcement of statutes and orders. The Superior Court, on application of the Public Utilities Regulatory Authority or of the Attorney General, may enforce, by appropriate decree or process, any provision of this chapter or any order of the authority rendered in pursuance of any statutory provision.
(1949 Rev., S. 5400; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 47, 348; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
Cited. 145 C. 526; 162 C. 51.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-10a. Revocation of franchises. Procedure. Reassignment. (a) Whenever any person, firm or corporation, incorporated under the general statutes or any special act, is granted a franchise to operate as a public service company, as defined in section 16-1, and fails to provide service which is adequate to serve the public convenience and necessity of any town, city, borough, district or other political subdivision of the state, or any portion thereof, for a period of five years from the date of such franchise or from January 1, 1961, whichever is later, the Public Utilities Regulatory Authority, on its own initiative, or upon complaint of any such town, city, borough, district or other political subdivision, or on petition of not less than five per cent of the affected persons, but in no event more than one thousand persons, in any such town, city, borough, district or other political subdivision, shall fix a time and place for a hearing to be held thereon. The authority shall give notice thereof to all parties in interest and shall make such further investigation into the alleged failure to provide such service as it deems necessary. If upon such hearing, said authority finds that the holder of such franchise has failed to provide such service and that there is an immediate need for such service, it may revoke such franchise as to any such town, city, borough, district or political subdivision, or any portion thereof, or make such other order as may be necessary to provide such service. Whenever any person, firm or corporation, incorporated under the general statutes or any special act, is granted a franchise to operate as a railroad company, as defined in section 13b-199, and fails to provide adequate service, or has discontinued the service, on any segment of its lines for which such franchise is granted for a period of five years or more, the franchise for such segment of line shall cease to exist and shall be revoked by the authority for such failure to operate such service or discontinuance of service for a period of five years or more.
(b) The Public Utilities Regulatory Authority, on its own initiative or upon complaint of any town, city, borough, district or other political subdivision of the state, in which a public service company, other than a community antenna television company, having five thousand or fewer customers, or a water company provides service, or on petition of either fifty per cent of the residents of such a town, city, borough, district or other political subdivision, or of five hundred customers of such company in any such town, city, borough, district or other political subdivision, may conduct a hearing, after giving notice thereof to all interested parties, to determine whether the rates that have been charged by such company for a period of five consecutive years immediately preceding the date of such hearing are so excessive in comparison to the rates charged by other public service companies providing the same or similar service as to inhibit the economic development of the area in which such company is authorized to furnish service or impose an unreasonable cost on the customers of such company. In making such determination, the authority may conduct such further investigation as it deems necessary and may consider whether such rates, if excessive, are the result of such factors as the overall size, stability and financial condition of such company, the organization, including technical and managerial expertise and efficiency, of such company and the physical condition and capacity of such company's plant. If the authority finds that such company is unable or unwilling to provide service at a reasonable cost to its customers, as determined by the authority, it may (1) make such order as may be necessary to provide such service, or (2) revoke the franchise held by such company. The authority shall adopt regulations, in accordance with the provisions of chapter 54, to implement the provisions of this subsection.
(c) If any such franchise is revoked, the Public Utilities Regulatory Authority, when the General Assembly is not in session, may grant a franchise to any person, firm or corporation, incorporated under the general statutes or any special act, qualified and prepared to provide such services within a reasonable time, as determined by said authority provided the authority first finds there is an immediate need for such a franchise after a public hearing in the area to be served thereunder. Such hearing shall be advertised at least twice prior thereto in a newspaper having a general circulation in each town of the area to be serviced by such franchise, once at least three days before said hearing, once at least fifteen days before said hearing, both advertisements to be at least ten days apart. Such franchise shall carry the same authority and powers and shall be subject to the same conditions and restrictions, if any, as the original franchise.
(1969, P.A. 789, S. 1; P.A. 73-353; P.A. 75-486, S. 7, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 48, 348; P.A. 81-472, S. 24, 159; P.A. 85-246, S. 9; P.A. 87-96; P.A. 89-261, S. 1; P.A. 94-219, S. 2; P.A. 11-80, S. 1; P.A. 14-134, S. 3.)
History: P.A. 73-353 added provisions re revocation of franchise upon failure to provide or discontinuance of service in Subsec. (a); P.A. 75-486 replaced public utilities commission with public utilities control authority and amended Subsec. (a) to allow hearings if service not adequate to serve public convenience and necessity and to add provision re petition for hearing; P.A. 77-614 replaced the authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 81-472 made technical changes; P.A. 85-246 amended Subsec. (a) to delete reference to street railway companies; P.A. 87-96 relettered existing Subsec. (b) as Subsec. (c) and added new Subsec. (b) re franchise revocation procedures applicable to small public service companies unable or unwilling to provide service at a reasonable cost; P.A. 89-261 deleted provision in Subsec. (b) preventing the department from revoking a water company franchise; P.A. 94-219 in Subsec. (b) changed requirements for a petition to determine if rates charged by a public service water company are excessive from 5% of the affected persons to either 50% of the residents of such town, city or borough, district or other political subdivision or 500 customers of such company; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 14-134 amended Subsec. (a) by replacing reference to Sec. 16-1 with reference to Sec. 13b-199 re railroad company, effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-11. Safety of public and employees. Powers. The Public Utilities Regulatory Authority shall, so far as is practicable, keep fully informed as to the condition of the plant, equipment and manner of operation of all public service companies and persons involved in the transportation of gas, as such terms are defined in section 16-280a, in respect to their adequacy and suitability to accomplish the duties imposed upon such companies by law and in respect to their relation to the safety of the public and of the employees of such companies or persons. The authority may order such reasonable improvements, repairs or alterations in such plant or equipment, or such changes in the manner of operation, as may be reasonably necessary in the public interest. The general purposes of this section and sections 16-19, 16-25, 16-43 and 16-47 are to assure to the state of Connecticut its full powers to regulate its public service companies, to increase the powers of the Public Utilities Regulatory Authority and to promote local control of the public service companies of this state, and said sections shall be so construed as to effectuate these purposes.
(1949 Rev., S. 5401; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 4, 40, 345, 348; P.A. 82-150, S. 2; P.A. 11-80, S. 1; P.A. 22-20, S. 4.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 82-150 deleted an obsolete reference to Sec. 16-37 and substituted “companies” for “corporations”; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 22-20 added reference to persons involved in the transportation of gas as defined in Sec. 16-280a and added “or persons” after “such companies”.
In case of conflict of powers between commission and local authorities, latter yield. 66 C. 211; 103 C. 212. Duties are administrative rather than judicial. 43 C. 382; 75 C. 471; 78 C. 306; 80 C. 640; 86 C. 36; 88 C. 471; 89 C. 537; 97 C. 458; Id., 733. Have no powers of arbitration; conditional decrees. 41 C. 355; 104 U.S. 1. Except for local regulations, such as traffic rules, municipalities have no power to regulate street railways. 103 C. 212. Cited. 140 C. 650; 144 C. 516. Contract of public utility company affecting its service and the public interest is subject to scrutiny of commission. 145 C. 526. Does not provide that a transfer of control under Sec. 16-47 can be made only to inhabitants of franchise area. 146 C. 1. Dispute concerning private property rights of various riparian owners, including defendant water company, does not fall within administrative process of commission and was properly brought before Superior Court. 155 C. 477. Within their scope, the regulations of commission have the force of statutes and a violation of a valid regulation is negligence per se; defendant electric utility exercised every reasonable precaution to safeguard the public against live wires in a severe storm and could plead and prove contributory negligence by plaintiff. 158 C. 600. Cited. 162 C. 93; 219 C. 121.
Cited. 43 CA 196.
Cited. 30 CS 36; 40 CS 520.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-11a. Nuclear Energy Advisory Council; composition; duties. (a) There is established a Nuclear Energy Advisory Council which shall (1) hold regular public meetings for the purpose of discussing issues relating to the safety and operation of the nuclear power generating facilities located in this state and to advise the Governor, the General Assembly and municipalities within a five-mile radius of any nuclear power generating facility in this state of such issues, (2) work in conjunction with agencies of the federal, state and local governments to ensure the public health and safety, (3) discuss proposed changes in or problems arising from the operation of a nuclear power generating facility, (4) communicate with any company operating a nuclear power generating facility about safety or operational concerns at the facility, which communications may include, but not be limited to, receipt of written reports and presentations to the council, and (5) review the current status of facilities with the Nuclear Regulatory Commission.
(b) The advisory council shall consist of: (1) Two members appointed by the president pro tempore of the Senate and two members appointed by the speaker of the House of Representatives; (2) the Commissioner of Energy and Environmental Protection, or said commissioner's designee; (3) one representative of an operator of a nuclear power generating facility located in the state, appointed by the Governor; (4) two electors from each municipality in which a nuclear power generating facility is located, appointed by the chief executive officers of said municipalities; and (5) four electors each of whom is from a municipality which is adjacent to a municipality in which a nuclear power generating facility is located, one appointed by the majority leader of the House of Representatives, one appointed by the majority leader of the Senate, one appointed by the minority leader of the House of Representatives, and one appointed by the minority leader of the Senate.
(c) All appointments to the advisory council shall be made not more than thirty days after June 6, 1996. Any vacancy shall be filled by the appointing authority.
(d) The council shall elect a chairperson from among its members, except that the speaker of the House of Representatives and the president pro tempore of the Senate shall select the chairpersons for the first meeting of the council. Such chairpersons shall schedule the first meeting of the council, which shall be held within sixty days after June 6, 1996.
(e) The membership of the council shall serve without compensation. The Commissioner of Energy and Environmental Protection shall provide clerical support to the council.
(f) On or before January 1, 1997, and annually thereafter, the advisory council shall report to the General Assembly concerning its activities for the preceding year.
(P.A. 96-245, S. 17, 44; P.A. 00-155; P.A. 01-49, S. 3; P.A. 11-80, S. 1; P.A. 14-134, S. 49.)
History: P.A. 96-245 effective June 6, 1996 (Revisor's note: In codifying this section the Revisors editorially substituted “council” for “task force” in the phrase “Such chairpersons shall schedule the first meeting of the council, which shall ...”); P.A. 00-155 deleted “within available resources” in Subsec. (e); P.A. 01-49 amended Subsecs. (a) and (b) to make technical changes, including a change for purposes of gender neutrality; pursuant to P.A. 11-80, “Commissioner of Environmental Protection” was changed editorially by the Revisors to “Commissioner of Energy and Environmental Protection” in Subsecs. (b) and (e), effective July 1, 2011; P.A. 14-134 amended Subsec. (a) by deleting references to any electric company operating a nuclear power generating facility, effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-12. Complaints as to dangerous conditions. Any person or any town, city or borough may make complaint, in writing, to the Public Utilities Regulatory Authority, of any defects in any portion of the plant or equipment of any public service company or electric supplier, or of the manner of operating such plant, by reason of which the public safety or the health or safety of employees is endangered; and, if he or it so requests, the name of the complainant shall not be divulged unless in the opinion of the authority the complaint is such that publicity is demanded.
(1949 Rev., S. 5402; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 49, 348; P.A. 98-28, S. 84, 117; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 98-28 added electric suppliers, effective July 1, 1998; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-13. Procedure upon complaint. Upon receipt of such complaint, the Public Utilities Regulatory Authority shall fix a time and place for hearing thereon and shall give notice thereof to all parties in interest, and shall make such further investigation into the alleged conditions as it deems necessary. If, upon such hearing, the authority finds the conditions to be dangerous to public safety or to the safety of employees, it shall make such order as may be necessary to remedy the same and shall furnish a copy of such order to the complainant, upon request. If the authority finds that the complaint is not justified, it shall so notify the complainant in writing, by registered or certified letter, specifying the reasons for such finding, and shall file a copy of such notification in the office of the authority.
(1949 Rev., S. 5403; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 4, 40, 345, 348; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
Cited. 169 C. 344.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-14. Powers concerning electrolysis or escape of electricity. Any town, city or borough, or any person or corporation maintaining pipes, conductors or other structures under or above ground in the streets or highways, or owning cattle, as defined in section 22-381, may make complaint in writing to the Public Utilities Regulatory Authority of conditions resulting in injury to or destruction of such pipes, conductors, structures or cattle by electrolysis or by reason of the escape of electricity of any public service company or electric supplier. Proceedings shall be had upon such complaint as provided in sections 16-12 and 16-13. After hearing, as therein provided, said authority may make such order as may be necessary to prevent such injury or destruction, and said authority may, at any time thereafter, for cause shown, upon hearing, after notice to all parties in interest, alter any such decision or order. Neither the provisions of this section nor compliance with any order passed pursuant to the provisions hereof shall constitute a defense in an action for damages resulting from electrolysis.
(1949 Rev., S. 5404; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 50, 348; P.A. 94-242, S. 8; P.A. 98-28, S. 85, 117; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 94-242 expanded applicability to owners of cattle; P.A. 98-28 added electric suppliers, effective July 1, 1998; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-15. Compliance with orders. Penalty. Each public service company and electric supplier shall comply immediately with any order of the Public Utilities Regulatory Authority made in accordance with the provisions of sections 16-13 and 16-14, and any company failing to comply with any such order shall be fined not more than one thousand dollars for each offense and shall be liable in double damages for any injury or damage resulting to any person from such failure.
(1949 Rev., S. 5405; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 51, 348; P.A. 98-28, S. 86, 117; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 98-28 added electric suppliers, effective July 1, 1998; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-16. Report of accidents. Each public service company, person involved in the transportation of gas, as such terms are defined in section 16-280a, and electric supplier subject to regulation by the Public Utilities Regulatory Authority shall, in the event of any accident attended with personal injury or involving public safety, which was or may have been connected with or due to the operation of its property, or caused by contact with the wires of any public service company or electric supplier, notify the authority thereof, by telephone or otherwise, as soon as may be reasonably possible after the occurrence of such accident, unless such accident is a minor accident, as defined by regulations of the authority. Each such person, company or electric supplier shall report such minor accidents to the authority in writing, in summary form, once each month. If notice of such accident, other than a minor accident, is given otherwise than in writing, it shall be confirmed in writing within five days after the occurrence of such accident. Any person, company or electric supplier failing to comply with the provisions of this section shall be fined not more than five hundred dollars for each offense.
(1949 Rev., S. 5406; P.A. 75-486, S. 1, 69; P.A. 77-254; 77-614, S. 162, 610; P.A. 79-610, S. 42; P.A. 80-482, S. 52, 348; P.A. 94-242, S. 1, 9; P.A. 98-28, S. 87, 117; P.A. 11-80, S. 1; P.A. 22-20, S. 5.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-254 added special provisions for reporting minor accidents; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 79-610 deleted reference to companies operating motor buses or taxicabs; P.A. 80-482 made division of public utility control an independent department and deleted reference to abolished department of business regulation; P.A. 94-242 deleted references to persons or companies operating motor vehicles in livery service and motor common or contract carriers of property for hire, effective June 2, 1994; P.A. 98-28 added electric suppliers, effective July 1, 1998; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 22-20 added reference to person involved in the transportation of gas as defined in Sec. 16-280a and made a technical change.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-17. Duties as to accidents. The Public Utilities Regulatory Authority shall examine the causes of, and the circumstances connected with, all fatal accidents occurring in the operation of the plant or equipment of any public service company or electric supplier, and such other accidents, whether resulting in personal injury or not, as, in its judgment, require investigation. The authority shall make a record of the causes, facts and circumstances of each accident, within three months thereafter, and as a part of such record shall suggest means, if possible, whereby similar accidents may be avoided in the future. Such record shall be open to public inspection at the office of the authority and a copy thereof shall be mailed to the public service company or electric supplier affected thereby. The authority may by written order extend the deadline for completion of its record in cases where it is not possible to conclude an investigation within the three-month period because of circumstances beyond its control.
(1949 Rev., S. 5407; 1971, P.A. 221; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 53, 348; P.A. 82-150, S. 3; P.A. 90-51, S. 1; P.A. 98-28, S. 88, 117; P.A. 11-80, S. 1.)
History: 1971 act required that record of accident be made within three months rather than one month; P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced the authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division of public utility control an independent department and deleted reference to abolished department of business regulation; P.A. 82-150 made technical grammatical change; P.A. 90-51 added provision allowing department to extend deadline for completion of its record; P.A. 98-28 added electric suppliers and made a technical change, effective July 1, 1998; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
Cited. 162 C. 53.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-18. Powers concerning poles and wires. The Public Utilities Regulatory Authority shall have power, after notice to the companies interested and public hearing, to require any public service company or certified telecommunications provider maintaining a line or lines of poles and wires in this state to change the location of such poles and wires in the public highways whenever public convenience or necessity requires such change and, if two or more companies, persons, firms or corporations are using or maintaining lines of poles or wires in the same street, to require the wires of such companies, persons, firms and corporations to be strung upon one or more lines of poles to be owned and maintained by the companies, persons, firms or corporations using the same as said authority determines.
(1949 Rev., S. 5408; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 54, 348; P.A. 94-74, S. 4, 11; P.A. 99-286, S. 6, 19; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 94-74 added provisions re persons, firms or corporations certified to provide intrastate telecommunication services, effective July 1, 1994; P.A. 99-286 changed reference to person, firm or corporation certified to provide telecommunications service to “certified telecommunications provider”, effective July 19, 1999; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
Cited. 103 C. 205; 162 C. 93.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-18a. Consultants: Retention, expenses, findings and recommendations. (a) In the performance of their duties the Public Utilities Regulatory Authority, the Department of Energy and Environmental Protection and the Office of Consumer Counsel may retain consultants to assist their staffs in proceedings before the authority by providing expertise in areas in which staff expertise does not currently exist or when necessary to supplement existing staff expertise. In any case where the authority, the Department of Energy and Environmental Protection or the Office of Consumer Counsel determines that the services of a consultant are necessary or desirable, the authority shall (1) allow opportunity for the parties and participants to the proceeding for which the services of a consultant are being considered to comment regarding the necessity or desirability of such services, (2) upon the request of a party or participant to the proceeding for which the services of a consultant are being considered, hold a hearing, and (3) limit the reasonable and proper expenses for such services to not more than two hundred thousand dollars for each agency per proceeding involving a public service company, telecommunications company, electric supplier or person seeking certification to provide telecommunications services pursuant to chapter 283, with more than fifteen thousand customers, and to not more than fifty thousand dollars for each agency per proceeding involving such a company, electric supplier or person with less than fifteen thousand customers, provided the authority, the Department of Energy and Environmental Protection or the Office of Consumer Counsel may exceed such limits for good cause. In the case of multiple proceedings conducted to implement the provisions of this section and sections 16-1, 16-19, 16-19e, 16-22, 16-247a to 16-247c, inclusive, 16-247e to 16-247h, inclusive, and 16-247k and subsection (e) of section 16-331, the authority, the Department of Energy and Environmental Protection or the Office of Consumer Counsel may exceed such limits, but the total amount for all such proceedings shall not exceed the aggregate amount which would be available pursuant to this section. All reasonable and proper expenses, as defined in subdivision (3) of this section, shall be borne by the affected company, electric supplier or person and shall be paid by such company, electric supplier or person at such times and in such manner as the authority, the Department of Energy and Environmental Protection or the Office of Consumer Counsel directs. All reasonable and proper costs and expenses, as defined in subdivision (3) of this section, shall be recognized by the authority for all purposes as proper business expenses of the affected company, electric supplier or person. The providers of consultant services shall be selected by the authority, the Department of Energy and Environmental Protection or the Office of Consumer Counsel and shall submit written findings and recommendations to the authority, the Department of Energy and Environmental Protection or the Office of Consumer Counsel, as the case may be, which shall be made part of the public record.
(b) Notwithstanding any provision of the general statutes, the authority, the Department of Energy and Environmental Protection and the Office of Consumer Counsel shall not retain any consultant under subsection (a) of this section in connection with any proceeding involving telecommunications if such consultant, at the time the consultant would be retained, is serving as a consultant to a certified telecommunications provider or a telephone company that would be affected by such proceeding, unless each party and intervenor to such proceeding agrees in writing to waive the provisions of this subsection.
(c) The Department of Energy and Environmental Protection, in consultation with the Public Utilities Regulatory Authority and the Office of Consumer Counsel, may retain consultants to assist its staff by providing expertise in areas in which staff expertise does not currently exist or to supplement staff expertise for any proceeding before or in any negotiation with the Federal Energy Regulatory Commission, the United States Department of Energy, the United States Nuclear Regulatory Commission, the United States Securities and Exchange Commission, the Federal Trade Commission, the Federal Communications Commission or the United States Department of Justice. The Public Utilities Regulatory Authority, in consultation with the Office of Consumer Counsel, may retain consultants to assist its staff by providing expertise in areas in which staff expertise does not currently exist or to supplement staff expertise for any proceeding before or in any negotiation with the Federal Communications Commission. All reasonable and proper expenses of any such consultants shall be borne by the public service companies, certified telecommunications providers, holders of a certificate of video franchise authority, electric suppliers or gas registrants affected by the decisions of such proceeding and shall be paid at such times and in such manner as the authority directs, provided such expenses (1) shall be apportioned in proportion to the revenues of each affected entity as reported to the authority pursuant to section 16-49 for the most recent fiscal year, and (2) shall not exceed two and one-half million dollars per calendar year, including any appeals thereof, unless the authority finds good cause for exceeding the limit. The authority shall recognize all such expenses as proper business expenses of the affected entities for ratemaking purposes pursuant to section 16-19e, if applicable.
(P.A. 92-25, S. 1; P.A. 94-83, S. 11, 16; P.A. 98-28, S. 34, 117; P.A. 99-286, S. 7, 19; P.A. 00-53, S. 2; P.A. 00-107, S. 2, 3; June Sp. Sess. P.A. 01-9, S. 17, 131; P.A. 11-80, S. 25; P.A. 13-298, S. 8; P.A. 16-101, S. 2; P.A. 19-35, S. 12.)
History: P.A. 94-83 added “or when necessary to supplement existing staff expertise”, made technical changes, amended Subdiv. (1) by replacing hearing with opportunity for comment, added new Subdiv. (2) re hearing, renumbered Subdiv. (2) as (3) and changed references to Subdiv. (2) to Subdiv. (3), added provisions re telecommunications companies and persons, firms or corporations seeking certification, added provision re multiple proceedings and deleted “The provisions of this section shall terminate on January 1, 1997”, effective July 1, 1994; P.A. 98-28 designated existing provisions as Subsec. (a), making technical changes and adding references to electric suppliers, and added new Subsec. (b) authorizing the department to retain consultants for implementing the public education outreach program, effective July 1, 1998; P.A. 99-286 amended Subsec. (a) by making technical changes, effective July 19, 1999; P.A. 00-53 made a technical change in Subsec. (a); P.A. 00-107 added new Subsec. (c) prohibiting the use of certain consultants, effective May 26, 2000; June Sp. Sess. P.A. 01-9 extended the authority of the department to retain consultants for implementing the public education outreach program from December 31, 2000, to December 31, 2005, effective July 1, 2001; P.A. 11-80 replaced “Department of Public Utility Control” with “Public Utilities Regulatory Authority”, replaced “department” with “authority”, deleted former Subsec. (b) re retaining consultants to assist in developing and implementing public education outreach program, and redesignated existing Subsec. (c) as Subsec. (b), effective July 1, 2011; P.A. 13-298 added Subsec. (c) re retaining consultants to assist in federal proceedings, effective July 1, 2013; P.A. 16-101 amended Subsec. (a) by replacing “16-247i” with “16-247h”, effective June 2, 2016; P.A. 19-35 amended Subsecs. (a) and (b) by adding references to Department of Energy and Environmental Protection, amended Subsec. (c) by adding reference to the Federal Communications Commission and made technical changes.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19. Amendment of rate schedule; investigations and findings by authority; hearings; deferral of municipal rate increases; refunds; notice of application for rate amendment, interim rate amendment and reopening of rate proceeding. (a) No public service company may charge rates in excess of those previously approved by the Public Utilities Control Authority or the Public Utilities Regulatory Authority, except that any rate approved by the Public Utilities Commission, the Public Utilities Control Authority or the Public Utilities Regulatory Authority shall be permitted until amended by the Public Utilities Regulatory Authority, that rates not approved by the Public Utilities Regulatory Authority may be charged pursuant to subsection (b) of this section, and that the hearing requirements with respect to adjustment clauses are as set forth in section 16-19b. For water companies, existing rates shall include the amount of any adjustments approved pursuant to section 16-262w since the company's most recent general rate case, provided any adjustment amount shall be separately identified in any customer bill. Each public service company shall file any proposed amendment of its existing rates with the authority in such form and in accordance with such reasonable regulations as the authority may prescribe. Each electric distribution, gas or telephone company filing a proposed amendment shall also file with the authority an estimate of the effects of the amendment, for various levels of consumption, on the household budgets of high and moderate income customers and customers having household incomes not more than one hundred fifty per cent of the federal poverty level. Each electric distribution company shall also file such an estimate for space heating customers. Each water company, except a water company that provides water to its customers less than six consecutive months in a calendar year, filing a proposed amendment, shall also file with the authority a plan for promoting water conservation by customers in such form and in accordance with a memorandum of understanding entered into by the authority pursuant to section 4-67e. Each public service company shall notify each customer who would be affected by the proposed amendment, by mail, at least one week prior to the first public hearing thereon, but not earlier than six weeks prior to such first public hearing, that an amendment has been or will be requested. Such notice shall also indicate (1) the date, time and location of any scheduled public hearing, (2) a statement that customers may provide written comments regarding the proposed amendment to the Public Utilities Regulatory Authority or appear in person at any scheduled public hearing, (3) the Public Utilities Regulatory Authority telephone number for obtaining information concerning the schedule for public hearings on the proposed amendment, and (4) whether the proposed amendment would, in the company's best estimate, increase any rate or charge by twenty per cent or more, and, if so, describe in general terms any such rate or charge and the amount of the proposed increase, provided no such company shall be required to provide more than one form of the notice to each class of its customers. In the case of a proposed amendment to the rates of any public service company, the authority shall hold one or more public hearings thereon, except as permitted with respect to interim rate amendments by subsections (d) and (g) of this section, and shall make such investigation of such proposed amendment of rates as is necessary to determine whether such rates conform to the principles and guidelines set forth in section 16-19e, or are unreasonably discriminatory or more or less than just, reasonable and adequate, or that the service furnished by such company is inadequate to or in excess of public necessity and convenience, provided the authority may (A) evaluate the reasonableness and adequacy of the performance or service of the public service company using any applicable metrics or standards adopted by the authority pursuant to section 16-244aa, and (B) determine the reasonableness of the allowed rate of return of the public service company based on such performance evaluation. The authority, if in its opinion such action appears necessary or suitable in the public interest may, and, upon written petition or complaint of the state, under direction of the Governor, shall, make the aforesaid investigation of any such proposed amendment which does not involve an alteration in rates. If the authority finds any proposed amendment of rates to not conform to the principles and guidelines set forth in section 16-19e, or to be unreasonably discriminatory or more or less than just, reasonable and adequate to enable such company to provide properly for the public convenience, necessity and welfare, or the service to be inadequate or excessive, it shall determine and prescribe, as appropriate, an adequate service to be furnished or just and reasonable maximum rates and charges to be made by such company. In the case of a proposed amendment filed by an electric distribution, gas or telephone company, the authority shall also adjust the estimate filed under this subsection of the effects of the amendment on the household budgets of the company's customers, in accordance with the rates and charges approved by the authority. The authority shall issue a final decision on each electric distribution or gas company rate filing within three hundred fifty days from the proposed effective date thereof. The authority shall issue a final decision on all public service company rate filings, except electric distribution or gas company rate filings, within two hundred days from the proposed effective date thereof.
(b) If the authority has not made its finding respecting an amendment of any electric distribution or gas company rate within three hundred fifty days from the proposed effective date of such amendment thereof, or if the authority has not made its finding respecting an amendment of any public service company rate, except an electric distribution or a gas company rate, within two hundred days from the proposed effective date of such amendment thereof, such amendment may become effective pending the authority's finding with respect to such amendment upon the filing by the company with the authority of assurance satisfactory to the authority, which may include a bond with surety, of the company's ability and willingness to refund to its customers with interest such amounts as the company may collect from them in excess of the rates fixed by the authority in its finding or fixed at the conclusion of any appeal taken as a result of a finding by the authority.
(c) Upon conclusion of its investigation of the reasonableness of any proposed increase of rates, the authority shall order the company to refund to its customers with interest any amounts the company may have collected from them during the period that any amendment permitted by subsection (b) of this section was in force, which amounts the authority may find to have been in excess of the rates fixed by the authority in its finding or fixed at the conclusion of any appeal taken as a result of a finding by the authority. Any such refund ordered by the authority shall be paid by the company, under direction of the authority, to its customers in such amounts as are determined by the authority.
(d) Nothing in this section shall be construed to prevent the authority from approving an interim rate increase, if the authority finds that such an interim rate increase is necessary to prevent substantial and material deterioration of the financial condition of a public service company, to prevent substantial deterioration of the adequacy and reliability of service to its customers or to conform to the applicable principles and guidelines set forth in section 16-19e, provided the authority shall first hold a special public hearing on the need for such interim rate increase and the company, at least one week prior to such hearing, notifies each customer who would be affected by the interim rate increase that such an increase is being requested. The company shall include the notice in a mailing of customer bills, unless such a mailing would not provide timely notice, in which case the authority shall authorize an alternative manner of providing such notice. Any such interim rate increase shall only be permitted if the public service company submits an assurance satisfactory to the authority, which may include a bond with surety, of the company's ability and willingness to refund to its customers with interest such amounts as the company may collect from such interim rates in excess of the rates approved by the authority in accordance with subsection (a) of this section. The authority shall order a refund in an amount equal to the excess, if any, of the amount collected pursuant to the interim rates over the amount which would have been collected pursuant to the rates finally approved by the authority in accordance with subsection (a) of this section or fixed at the conclusion of any appeal taken as a result of any finding by the authority. Such refund ordered by the authority shall be paid by the company to its customers in such amounts and by such procedure as ordered by the authority.
(e) If the authority finds that the imposition of any increase in rates would create a hardship for a municipality, because such increase is not reflected in its then current budget, or cannot be included in the budget of its fiscal year which begins less than five months after the effective date of such increase, the authority may defer the applicability of such increase with respect to services furnished to such municipality until the fiscal year of such municipality beginning not less than five months following the effective date of such increase; provided the revenues lost to the public service company through such deferral shall be paid to the public service company by the municipality in its first fiscal year following the period of such deferral.
(f) Any public service company, as defined in section 16-1, filing an application with the Public Utilities Regulatory Authority to reopen a rate proceeding under this section, which application proposes to increase the company's revenues or any rate or charge of the company by five per cent or more, shall, not later than one week prior to the hearing under the reopened proceeding, notify each customer who would be affected thereby that such an application is being filed. Such notice shall indicate the rate increases proposed in the application. The company shall include the notice in a mailing of customer bills, unless such a mailing would not provide timely notice to customers of the reopening of the proceeding, in which case the authority shall authorize an alternative manner of providing such notice.
(g) The authority shall hold either a special public hearing or combine an investigation with an ongoing four-year review conducted in accordance with section 16-19a or with a general rate hearing conducted in accordance with subsection (a) of this section on the need for an interim rate decrease (1) when a public service company has, for the rolling twelve-month period ending with the two most recent consecutive financial quarters, earned a return on equity which exceeds the return authorized by the authority by at least one percentage point, (2) if it finds that any change in municipal, state or federal tax law creates a significant increase in a company's rate of return, or (3) if it finds that a public service company may be collecting rates which are more than just, reasonable and adequate, as determined by the authority, provided the authority shall require appropriate notice of hearing to the company and its customers who would be affected by an interim rate decrease in such form as the authority deems reasonable. The company shall be required to demonstrate to the satisfaction of the authority that earning such a return on equity or collecting rates which are more than just, reasonable and adequate is directly beneficial to its customers. At the completion of the proceeding, the authority may order an interim rate decrease if it finds that such return on equity or rates exceeds a reasonable rate of return or is more than just, reasonable and adequate as determined by the authority. Any such interim rate decrease shall be subject to a customer surcharge if the interim rates collected by the company are less than the rates finally approved by the authority or fixed at the conclusion of any appeal taken as a result of any finding by the authority. Such surcharge shall be assessed against customers in such amounts and by such procedure as ordered by the authority.
(h) The provisions of this section shall not apply to the regulation of a telecommunications service which is a competitive service, as defined in section 16-247a, or to a telecommunications service to which an approved plan for an alternative form of regulation applies, pursuant to section 16-247k.
(1949 Rev., S. 5409; 1969, P.A. 217; 1972, P.A. 192, S. 1; P.A. 74-216, S. 2, 8; P.A. 75-486, S. 8, 69; P.A. 77-121; 77-614, S. 162, 587, 610; P.A. 78-303, S. 85, 136; P.A. 80-482, S. 55, 348; P.A. 83-190, S. 1–3; P.A. 84-113, S. 1, 2, 4; 84-342, S. 9, 13; 84-546, S. 49, 173; P.A. 85-33, S. 1; P.A. 87-202, S. 1; 87-331, S. 1, 4; P.A. 89-327, S. 5, 7; P.A. 94-83, S. 12, 16; 94-242, S. 2, 9; P.A. 98-28, S. 89, 117; P.A. 00-17, S. 1; P.A. 01-49, S. 4; P.A. 11-61, S. 6; 11-80, S. 1; P.A. 13-119, S. 4; P.A. 14-134, S. 50; P.A. 17-138, S. 1; Sept. Sp. Sess. P.A. 20-5, S. 2; P.A. 21-40, S. 17.)
History: 1969 act allowed suspension of effective date of increase for 150 days rather than 120 days; 1972 act added provisions re deferment of increase to municipalities if increase would cause budget difficulties; P.A. 74-216 added special provisions re rate increases for gas and electric companies; P.A. 75-486 replaced public utilities commission with public utilities control authority, clarified and rearranged provisions, allowed company to charge rates higher than those previously approved under certain circumstances and made interim rate provisions applicable to all public service companies rather than to gas and electric companies only; P.A. 77-121 required that companies notify customers of rate amendment request by mail before public hearing in Subsec. (a); P.A. 77-614 and P.A. 78-303 replaced authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 83-190 amended Subsec. (a) to require notice of proposed amendment one week prior to hearing and indication whether amendment would increase any rate or charge by at least 20%, amended Subsec. (d) to establish notice requirement for proposed interim rate amendments and added Subsec. (f) to establish notice requirement for any application to reopen a rate proceeding, which application proposes to increase company's revenues or any rate or charge by at least 5%; P.A. 84-113 amended Subsecs. (a) and (b) to authorize department to extend deadline for issuing a final decision on a rate filing by 30 days, to 180 days; P.A. 84-342 amended Subsec. (a) to require filing of estimate of effects of amendment and adjustment of estimate by department; P.A. 84-546 confirmed action of the Revisors in adding P.A. 83-190, S. 1 as Subsec. (f); P.A. 85-33 amended Subsec. (a) to require each public service company to include, in notice of proposed amendment, department telephone number for information on hearing schedule; P.A. 87-202 amended Subsec. (a) to require water companies filing proposed rate amendments to submit water conservation plans; P.A. 87-331 added Subsec. (g) re interim rate decrease and Subsec. (h) re effects of Tax Reform Act of 1986; P.A. 89-327 amended Subsec. (a) requiring that water conservation plan be in accordance with the memorandum of understanding; P.A. 94-83 added new Subsec. (i) re applicability to telecommunications service which is competitive or to which an approved plan for an alternative form of regulation applies, effective July 1, 1994; P.A. 94-242 deleted former Subsec. (h) re review of the effects of the federal Tax Reform Act of 1986, necessitating relettering of new Subsec. (i) added by P.A. 94-83 as (h), effective June 2, 1994; P.A. 98-28 amended Subsec. (a) by adding electric distribution companies, effective July 1, 1998; P.A. 00-17 amended Subsec. (g) by authorizing the department to combine investigation with ongoing four-year review or with general rate hearing as an alternative to a special public hearing and by making conforming technical changes; P.A. 01-49 amended Subsec. (g) to make technical changes; P.A. 11-61 amended Subsec. (a) to specify that adjustments approved under Sec. 16-262w are included in water companies' existing rates, effective June 21, 2011; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 13-119 amended Subsec. (a) to specify when notice must be mailed to customers, to redesignate existing Subdivs. (1) and (2) as Subdivs. (3) and (4), to add new Subdivs. (1) and (2) re notice requirements and to make technical changes; P.A. 14-134 amended Subsec. (a) by deleting references to electric company, effective June 6, 2014; P.A. 17-138 amended Subsec. (g)(1) to replace “six consecutive months” with “the rolling twelve-month period ending with the two most recent consecutive financial quarters”; Sept. Sp. Sess. P.A. 20-5 amended Subsec. (a) to permit evaluation and rate determination based upon performance-based metrics or standards, and amended Subsecs. (a) and (b) to extend deadline for issuing a final decision on a rate filing to 350 days for electric distribution or gas companies and 200 days for all other public service companies, effective October 2, 2020; P.A. 21-40 made technical changes in Subsec. (b).
See Sec. 16-11 re condition of plant, equipment and manner of operation of public service companies.
See Sec. 16-19h re reopening of water company rate proceedings.
See Sec. 16a-49 re conservation and load management program.
This section and Sec. 16-20 compared. 91 C. 138. Nature of power to regulate rates; what considered in determining their reasonableness; discrimination. Id., 692. Power of commission to change rate fixed by contract between a utility and a municipality. 101 C. 158. Cited. 103 C. 206. Establishment of changed rate schedule is not conditioned upon prior approval by commission. 132 C. 497, 509. Power to direct suspension of rate schedule. Id., 510. Cited. 158 C. 626; 159 C. 327; 166 C. 328; 169 C. 344; 174 C. 258; 176 C. 191; 183 C. 128; 188 C. 90; 196 C. 451; 216 C. 627; 219 C. 121; 234 C. 624.
Cited. 19 CS 359. Scope of commission's power in determining rate schedules; fact that commission did not take into consideration tax-free nature of dividends paid to corporation owner of a public utility in setting rate schedule of such utility, held not to invalidate action of commission. 21 CS 69. Rates could not be so low as to be confiscatory or so high as to exceed value of service to the consumer; what constitutes reasonable rate is primarily question of fact, depending largely on circumstances of particular case. 24 CS 441. Proposal filed must be amendment of existing rate schedule. 29 CS 379. Cited. 30 CS 149; 31 CS 65; 34 CS 172; 40 CS 520.
Subsec. (g):
Department's authority to order interim rate reduction is discretionary and statute does not require an interim rate reduction hearing to result in direct cash benefit to taxpayers; department decision to allow power company to apply part of its projected over-earnings toward accelerated amortization of certain regulatory assets as part of interim rate decrease found to be within department's authority. 252 C. 115.
Legislature deliberately created distinct procedure to examine need for temporary rate decrease between full rate cases, and department did not violate public service company's federal or state due process rights by holding an expedited hearing. 51 CS 307.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19a. Periodic review re gas and electric distribution companies' rates, services and performance. Approval of performance-based incentives and penalties. (a)(1) The Public Utilities Regulatory Authority shall, at intervals of not more than four years from the last previous general rate hearing of each gas and electric distribution company having more than seventy-five thousand customers, conduct a complete review and investigation of the financial and operating records of each such company and hold a public hearing to determine whether the rates of each such company are unreasonably discriminatory or more or less than just, reasonable and adequate, or that the service furnished by such company is inadequate to or in excess of public necessity and convenience or that the rates do not conform to the principles and guidelines set forth in section 16-19e. In making such determination, the authority shall consider the gross and net earnings of such company since its last previous general rate hearing, its retained earnings, its actual and proposed capital expenditures, its advertising expenses, the dividends paid to its stockholders, the rate of return paid on its preferred stock, bonds, debentures and other obligations, its credit rating, and such other financial and operating information as the authority may deem pertinent.
(2) The authority may conduct a general rate hearing in accordance with subsection (a) of section 16-19, in lieu of the periodic review and investigation proceedings required under subdivision (1) of this subsection.
(b) In any proceeding required under subdivision (1) of subsection (a) of this section, or in any rate hearing pursuant to section 16-19, the authority shall consider the implementation of financial performance-based incentives and penalties and performance-based metrics. Notwithstanding subsection (a) of this section, if the authority approves such performance-based incentives and penalties for a particular company, the authority shall include in such approval a framework for periodic monitoring and review of the company's performance pursuant to metrics developed by the authority.
(P.A. 74-216, S. 3, 8; P.A. 75-486, S. 9, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 56, 348; P.A. 85-30, S. 1, 2; P.A. 96-42, S. 1, 2; P.A. 98-28, S. 90, 117; P.A. 00-17, S. 2; P.A. 11-80, S. 1, 26; P.A. 14-134, S. 51; Sept. Sp. Sess. P.A. 20-5, S. 3.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority, required review not more than two years after last rate hearing, rather than not less than two years after hearing, included operating records in review and required review to see whether rates conform to guidelines in Sec. 16-19e; P.A. 77-614 replaced authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 85-30 required department to conduct reviews and investigations at intervals of not more than four years, instead of not more than two years, from last rate hearing and limited applicability of provisions of section to companies having more than 75,000 customers; P.A. 96-42 lettered existing section as Subsec. (a) and added Subsec. (b) re performance-based incentives and periodic monitoring and review by the Department of Public Utility Control in lieu of a rate proceeding described in Subsec. (a), effective May 2, 1996; P.A. 98-28 amended Subsec. (a) by adding electric distribution companies, effective July 1, 1998; P.A. 00-17 amended Subsec. (a) by designating existing language as Subdiv. (1) and inserting new Subdiv. (2) authorizing department to conduct general rate hearing in lieu of periodic review and investigation proceedings, and amended Subsec. (b) by making conforming technical changes; P.A. 11-80 replaced “Department of Public Utility Control” with “Public Utilities Regulatory Authority” and replaced “department” with “authority”, effective July 1, 2011; P.A. 14-134 amended Subsec. (a)(1) to delete reference to electric company and amended Subsec. (b) to replace “electric company” with “electric distribution company”, effective June 6, 2014; Sept. Sp. Sess. P.A. 20-5 amended Subsec. (b) by adding “, or in any rate hearing pursuant to section 16-19”, replacing “may approve performance-based incentives to encourage a gas or electric distribution company to operate efficiently and provide high quality service at fair and reasonable prices” with “shall consider the implementation of financial performance-based incentives and penalties and performance-based metrics”, adding reference to penalties, deleting provisions re performance criteria specified by authority and periodic review and investigation, adding reference to metrics developed by the authority and by making a technical change, effective November 1, 2020.
See Sec. 16-243a(d) re cogeneration generating capacity.
See Sec. 16a-49 re conservation and load management.
Cited. 219 C. 121.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19b. Purchased gas adjustment clauses, energy adjustment clauses and transmission rate adjustment clauses. (a) No adjustment clause of any kind whatsoever shall be authorized by the Public Utilities Regulatory Authority if such a clause operates automatically to permit charges, assessments or amendments to existing rate schedules to be made which have not been first approved by the authority.
(b) If the authority finds that the changed price of purchased gas required for distribution by a gas company substantially threatens the ability of the company to earn a reasonable rate of return, or will cause the company to have an excessive rate of return, the authority shall, after investigation and public hearing, approve a suitable purchased gas adjustment clause to be superimposed upon the existing rate schedule of the company. The authority shall design any such purchased gas adjustment clause to allow the gas company to charge or to reimburse the consumer only for the changes in the cost of purchased gas which occur when the actual price of purchased gas differs from the price reflected in the base rates of the company. The authority may establish an efficiency factor in the purchased gas adjustment clause of each gas company, which may provide for less than one hundred per cent recovery of the gross earnings tax imposed by section 12-264 on the revenues from such purchased gas. A purchased gas adjustment clause approved pursuant to this section shall apply to all gas companies similarly affected by the costs which form the basis for the adjustment clause.
(c) If the authority, after notice and hearing, determines that the adoption of an energy adjustment clause would protect the interests of ratepayers of an electric distribution company, ensure economy and efficiency in energy production and purchase by the electric distribution company and achieve the objectives set forth in subsection (a) of section 16-19 and in section 16-19e better than would the continued operation of a fuel adjustment clause and a generation utilization adjustment clause, the authority shall approve an energy adjustment clause to be superimposed upon the existing rate schedule of the electric distribution company. The authority shall design any such energy adjustment clause to reflect cost-efficient energy resource procurement and to recover the costs of energy that are proper for rate-making purposes and for which the authority has not authorized recovery through base rates. These costs, reflecting prudent and efficient management and operations, may include, but are not limited to, the costs of oil, gas, coal, nuclear fuel, wood or other fuels, and energy transactions with other utilities, nonutility generators or power pools, all or part of the cost of conservation and load management, and the gross earnings tax imposed by section 12-264 on the revenues from the energy sources subject to the energy adjustment clause. The authority shall design the energy adjustment clause to provide for recovery of energy costs prudently incurred by an electric distribution company in accordance with section 16-19e. Notwithstanding the provisions of section 16-19, the authority shall change an energy adjustment clause in accordance with the provisions of subsections (e) and (h) of this section. An energy adjustment clause approved pursuant to this section shall apply to all electric distribution companies similarly affected by the costs which form the basis for the adjustment clause.
(d) The Public Utilities Regulatory Authority shall adjust the retail rate charged by each electric distribution company for electric transmission services periodically to recover all transmission costs prudently incurred by each electric distribution company. The Public Utilities Regulatory Authority, after notice and hearing, shall design the retail transmission rate to provide for recovery of all Federal Energy Regulatory Commission approved transmission costs, rates, tariffs and charges and of other transmission costs prudently incurred by an electric distribution company in accordance with section 16-19e. Notwithstanding the provisions of section 16-19, the authority shall adjust the retail transmission rate in accordance with the provisions of subsections (e) and (h) of this section. A transmission rate adjustment clause approved pursuant to this section shall apply to all electric distribution companies similarly affected by transmission costs. The Public Utilities Regulatory Authority's authority to review the prudence of costs shall not apply to any matter over which any agency, department or instrumentality of the federal government has exclusive jurisdiction, or has jurisdiction concurrent with that of the state and has exercised such jurisdiction to the exclusion of regulation of such matter by the state.
(e) No proposed purchased gas adjustment, energy adjustment charge or credit or transmission rate shall become effective until the Public Utilities Regulatory Authority has approved such charges or credits. The authority may hold a hearing on such charges, provided the authority shall hold a hearing on such charges at the request of the electric distribution or gas company, interested persons or members of the public. Any such hearing shall be open to the public and, if held, shall be convened within ten days of the filing of an application by an electric distribution or gas company. Notice of such application and any hearing shall be published at least five days prior to such hearing, which may include publication in a newspaper of general circulation in the area served by such company. The authority shall receive and consider comments of interested persons and members of the public at such a hearing, which shall not be considered a contested case for purposes of title 4, this title or any regulation adopted thereunder. Any approval or denial of the authority pursuant to this subsection shall not be deemed an order, authorization or decision of the authority for purposes of section 16-35. After notice and hearing, the authority shall adopt regulations, in accordance with chapter 54, which shall include the requirements of the filing to support the requested charge or credit. Notwithstanding the provisions of this section, in the event that the authority has not rendered an approval or denial concerning any such application within fifteen days of the day the authority received the application, the proposed charges or credits (1) shall become effective at the option of the company pending the authority's finding with respect to such charges, or (2) in the discretion of the authority, may become effective upon the filing by the company with the authority of an assurance. Such assurance may include a bond with surety, and shall satisfy the authority of the company's ability and willingness to refund to its customers any such amounts as the company may collect from them in excess of the charges approved by the authority in its finding.
(f) Each company subject to a purchased gas adjustment clause or an energy adjustment clause shall disclose in its customer bills the per unit rate of the charges or credits made under the clause and the actual amount thereof in dollars and cents.
(g) The authority shall not suspend or discontinue a purchased gas adjustment clause or an energy adjustment clause which it has approved except (1) after general rate hearings for the companies affected by the clause, and (2) upon a finding by the Public Utilities Regulatory Authority that the market prices of purchased gas or the costs of energy have stabilized and are likely to remain stable.
(h) The Public Utilities Regulatory Authority shall continually monitor and oversee the application of the purchased gas adjustment clause, the energy adjustment clause, and the transmission rate adjustment clause. The authority shall hold a public hearing thereon whenever the authority deems it necessary or upon application of the Office of Consumer Counsel, but no less frequently than annually, and undertake such other proceeding thereon to determine whether charges or credits made under such clauses reflect the actual prices paid for purchased gas or energy and the actual transmission costs and are computed in accordance with the applicable clause. If the authority finds that such charges or credits do not reflect the actual prices paid for purchased gas or energy, and the actual transmission costs or are not computed in accordance with the applicable clause, it shall recompute such charges or credits and shall direct the company to take such action as may be required to insure that such charges or credits properly reflect the actual prices paid for purchased gas or energy and the actual transmission costs and are computed in accordance with the applicable clause for the applicable period.
(i) The authority shall establish procedures conforming to the requirements of this section after notice and opportunity for a public hearing.
(j) Any purchased gas adjustment clause or energy adjustment clause approved by the authority may include a provision designed to allow the electric distribution or gas company to charge or reimburse the customer for any under-recovery or over-recovery of overhead and fixed costs due solely to the deviation of actual retail sales of electricity or gas from projected retail sales of electricity or gas. The authority shall include such provision in any energy adjustment clause approved for an electric distribution company if it determines (1) that a significant cause of excess earnings by the electric distribution company is an increase in actual retail sales of electricity over projected retail sales of electricity as determined at the time of the electric distribution company's most recent rate amendment, and (2) that such provision is likely to benefit the customers of the electric distribution company.
(k) Notwithstanding the provisions of this section, upon the application of any gas company, the authority may modify, suspend or discontinue a purchased gas adjustment clause for one or more gas companies if the authority determines that as part of an overall performance-based rate plan, such modification, suspension or discontinuance will ensure safety and reliability, will provide substantial financial benefits to ratepayers at least equal to those provided to the gas company and will lower the rates below what they would be without such modification, suspension or discontinuance, as determined by the authority.
(P.A. 74-216, S. 4, 8; P.A. 75-486, S. 10, 69; P.A. 77-614, S. 162, 610; P.A. 78-370; P.A. 80-482, S. 57, 348; P.A. 82-150, S. 4; P.A. 83-97; P.A. 84-105; P.A. 85-233, S. 1, 2; P.A. 87-331, S. 2, 4; P.A. 90-221, S. 3, 15; P.A. 95-43, S. 1, 2; P.A. 00-221, S. 2; P.A. 05-210, S. 30; P.A. 06-196, S. 229; P.A. 11-80, S. 1; P.A. 13-119, S. 5; P.A. 14-134, S. 52–54; P.A. 17-35, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority and essentially rewrote provisions, expanding and clarifying them greatly; P.A. 77-614 replaced authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 78-370 amended Subsec. (a) to exclude gross earnings tax from consideration as part of cost of fossil fuel or purchased gas; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 82-150 deleted obsolete provisions in Subsec. (h) continuing adjustment clauses in effect prior to December 1, 1975, until superseded and repealed Subsec. (i) prohibiting adjustments from August 1, 1975, to December 1, 1975, unless approved after administrative proceeding, the procedure for which was set out in detail; P.A. 83-97 added Subsec. (i), authorizing provision re under-recovery or over- recovery of overhead and fixed costs; P.A. 84-105 amended Subsec. (a) to delete provision prohibiting gross earnings tax from being included in cost of purchased gas and added Subdiv. (2), authorizing establishment of efficiency factor in purchased gas adjustment clause; P.A. 85-233 added Subsec. (j) re inclusion of a provision on fossil fuel adjustment clause re cogeneration technology, renewable fuel resources or solid waste; P.A. 87-331 amended Subsec. (i) by adding requirements for annual public hearing and mandatory inclusion of provision re over-recovery of overhead and fixed costs in fossil fuel adjustment clause approved for electric companies; P.A. 90-221 deleted provision in Subsec. (i) requiring the department to hold an annual public hearing as to whether the department should include in the fossil fuel adjustment clause a provision concerning the deviation of actual retail sales to electricity or gas from the actual retail sales; P.A. 95-43 divided Subsec. (a) into Subsecs. (a) and (b), deleted provisions re fossil fuel adjustment clause, added new Subsec. (c) and references re energy adjustment clause, relettered Subsecs. (c) to (f) as (d) to (g), amended new Subsec. (d) by adding references to credits and changing the required content of regulations from monthly filings with the department and the office of the Governor to “the requirements of the filing to support the requested charge or credit” and deleted provision re explanation if no decision in five-day period, amended Subsec. (g) by extending frequency of hearings from every three to every six months, deleted former Subsec. (g) re rate of return and former Subsec. (j) re recovery of costs from customers and added new Subsec. (j) re clauses in effect July 1, 1995, effective July 1, 1995; P.A. 00-221 added Subsec. (k) re modification, suspension or discontinuance of purchased gas adjustment clause; P.A. 05-210 made technical changes in Subsec. (c), added new Subsec. (d) re adjustment of retail rate to recover prudently incurred transmission costs, redesignated existing Subsecs. (d) to (k), inclusive, as Subsecs. (e) to (l), inclusive, amended Subsec. (e) to add “or transmission rate”, and amended Subsec. (h) to allow the department to monitor and oversee the transmission rate adjustment clause and to add “and the actual transmission costs”, effective July 6, 2005; P.A. 06-196 made a technical change in Subsec. (d), effective June 7, 2006; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 13-119 amended Subsec. (h) to add requirement that the authority hold a public hearing upon application of Office of Consumer Counsel and to change frequency of a public hearing from every 6 months to annually; P.A. 14-134 amended Subsecs. (c), (e) and (j) by replacing references to electric company with references to electric distribution company, deleted former Subsec. (k) re approved fossil fuel or generation utilization clause for an electric company and redesignated existing Subsec. (l) as Subsec. (k), effective June 6, 2014; P.A. 17-35 amended Subsec. (e) by replacing provision re administrative proceeding with provision re hearing on charges, replacing “within five days of the day the administrative proceeding shall have been convened” with “within fifteen days of the day the authority received the application” and made technical and conforming changes.
Cited. 183 C. 128; 216 C. 627.
Cited. 40 CS 520.
Subsec. (c):
Statute creates a relative rather than an intrinsic standard and legislature intended that the phrase “better than would the continued operation of a fuel adjustment clause and a generation utilization adjustment clause” modify each of the three preceding clauses, including the first clause relating to protecting ratepayer interests; prudently incurred costs attributable to management decisions may be recovered through interim rate adjustments. 246 C. 18.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19c. Investigation of fuel cost adjustment and purchased gas adjustment charges. Section 16-19c is repealed.
(P.A. 74-216, S. 5, 8; P.A. 75-486, S. 68, 69.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19d. Advertising not to be deemed an operating expense for purposes of rate-making. Disclosure of source of payment for advertising. (a) As used in this section:
(1) “Advertising” means the commercial use of any media including, but not limited to, newspaper and all other forms of print, radio and television, in order to transmit a message to a substantial number of members of the public or customers of a public service company;
(2) “Political advertising” means any advertising for the purpose of influencing public opinion with respect to any legislative, administrative or electoral decision or with respect to any controversial issue of public importance;
(3) “Institutional advertising” means any advertising which is designed to create, enhance or sustain a public service company's image or good will with regard to the general public or its customers;
(4) “Promotional advertising” means any advertising that has the purpose of inducing the public to select or use the service or additional service of a public service company or select or install any appliance or equipment designed to use such service, provided such advertising shall not include advertising authorized by order or regulation of the Public Utilities Regulatory Authority.
(b) The cost of political, institutional or promotional advertising of any gas company or electric distribution company and the cost of political or institutional advertising of any telephone company shall not be deemed to be an operating expense in any rate schedule proceedings held pursuant to section 16-19. For the purposes of this section, political, institutional or promotional advertising shall not be deemed to include reasonable expenditures for (1) the publication or distribution of existing or proposed tariffs or rate schedules; (2) notices required by law or regulation; (3) public information regarding service interruptions, safety measures, emergency conditions, employment opportunities or the means by which customers can conserve energy or make efficient and economical use of service; (4) the promotion or marketing of efficient gas and electric equipment which the Public Utilities Regulatory Authority determines: (A) Is consistent with the state's energy policy; (B) is consistent with integrated resource planning principles; (C) provides net economic benefit to such company's customers; and (D) shall not have the primary purpose of promoting one fuel over another; or (5) advertising by a gas company that is necessary as a result of competition created by actions and decisions of the Federal Energy Regulatory Commission and the Public Utilities Regulatory Authority. Such advertising shall be limited to the express purpose of promoting gas companies in competition with other providers and marketers of natural gas. Such advertising shall not include any promotions, cash, equipment, installation or service subsidies for the conversion to natural gas from any other energy source.
(c) A public service company shall make application to the authority for determination that equipment meets the requirements of subdivision (4) of subsection (b) of this section. The authority shall, to the extent practicable, make such determination within one hundred twenty days of such filing. All reasonable and proper expenses, required by the authority and the Office of Consumer Counsel, including, but not limited to, the costs associated with analysis, testing, evaluation and testimony at a public hearing or other proceeding, shall be borne by the company and shall be paid by the company at such times and in such manner as the authority directs.
(d) The authority shall not allocate any expenditures made by a gas company pursuant to subdivision (5) of subsection (b) of this section to residential customers in any rate schedule proceedings held pursuant to section 16-19 unless the authority finds that effective competition in the residential gas market already exists.
(e) The authority shall adopt regulations to carry out the purposes of subsections (a) and (b) of this section.
(f) Each gas or electric distribution company shall conspicuously indicate in all of its advertising whether the costs of the advertising are being paid for by the company's shareholders, its customers or both.
(P.A. 75-588; P.A. 77-614, S. 162, 610; P.A. 79-142; P.A. 80-482, S. 58, 348; P.A. 82-150, S. 5; P.A. 83-101; P.A. 91-248, S. 8, 13; P.A. 96-13; P.A. 98-28, S. 91, 117; P.A. 11-80, S. 1; P.A. 14-134, S. 55, 56.)
History: P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979 (original act referred to public utilities commission which was supplanted by the authority via P.A. 75-486); P.A. 79-142 substituted advertising by order of public utility control division for “advertising directed at the replacement appliance market” in Subsec. (a)(4); P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 82-150 deleted superfluous references to definitions in Sec. 16-1; P.A. 83-101 added Subsec. (d), requiring gas and electric companies to indicate source of payment of advertising costs; P.A. 91-248 added Subsec. (b)(4) re marketing of efficient gas and electric equipment and inserted a new Subsec. (c) re approval of efficient gas and electric equipment and payment of the department and office of consumer counsel re applications, relettering former Subsecs. (c) and (d) accordingly; P.A. 96-13 added Subsec. (b)(5) re advertising by a gas company and inserted new Subsec. (d) re allocation of expenditures made by a gas company, relettering former Subsecs. (d) and (e) accordingly; P.A. 98-28 changed “utility” to “public service company” throughout and amended Subsecs. (b) and (f) by adding electric distribution companies, effective July 1, 1998; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 14-134 amended Subsecs. (b) and (f) by deleting references to electric company and making a technical change, effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19e. Guidelines for transfer of assets and franchises, plant expansion, internal utility management and rate structures. Public hearing. Policy coordination among state agencies. Parties to rate proceeding. (a) In the exercise of its powers under the provisions of this title, the Public Utilities Regulatory Authority shall examine and regulate the transfer of existing assets and franchises, the expansion of the plant and equipment of existing public service companies, the operations and internal workings of public service companies and the establishment of the level and structure of rates in accordance with the following principles: (1) That there is a clear public need for the service being proposed or provided; (2) that the public service company shall be fully competent to provide efficient and adequate service to the public in that such company is technically, financially and managerially expert and efficient; (3) that the authority and all public service companies shall perform all of their respective public responsibilities with economy, efficiency and care for public safety and energy security, and so as to promote economic development within the state with consideration for energy and water conservation, energy efficiency and the development and utilization of renewable sources of energy and for the prudent management of the natural environment; (4) that the level and structure of rates be sufficient, but no more than sufficient, to allow public service companies to cover their operating costs including, but not limited to, appropriate staffing levels, and capital costs, to attract needed capital and to maintain their financial integrity, and yet provide appropriate protection to the relevant public interests, both existing and foreseeable which shall include, but not be limited to, reasonable costs of security of assets, facilities and equipment that are incurred solely for the purpose of responding to security needs associated with the terrorist attacks of September 11, 2001, and the continuing war on terrorism; (5) that the level and structure of rates charged customers shall reflect prudent and efficient management of the franchise operation; and (6) that the rates, charges, conditions of service and categories of service of the companies not discriminate against customers which utilize renewable energy sources or cogeneration technology to meet a portion of their energy requirements.
(b) The Public Utilities Regulatory Authority shall promptly undertake a separate, general investigation of, and shall hold at least one public hearing on new pricing principles and rate structures for electric distribution companies and for gas companies to consider, without limitation, long run incremental cost of marginal cost pricing, peak load or time of day pricing and proposals for optimizing the utilization of energy and restraining its wasteful use and encouraging energy conservation, and any other matter with respect to pricing principles and rate structures as the authority shall deem appropriate. The authority shall determine whether existing or future rate structures place an undue burden upon those persons of poverty status and shall make such adjustment in the rate structure as is necessary or desirable to take account of their indigency. The authority shall require the utilization of such new principles and structures to the extent that the authority determines that their implementation is in the public interest, as identified by the Department of Energy and Environmental Protection in the Integrated Resources Plan and the Comprehensive Energy Strategy, and necessary or desirable to accomplish the purposes of this provision without being unfair or discriminatory or unduly burdensome or disruptive to any group or class of customers, and determines that such principles and structures are capable of yielding required revenues. In reviewing the rates and rate structures of electric and gas companies, the authority shall be guided by the goals of the Department of Energy and Environmental Protection, as described in section 22a-2d, the Comprehensive Energy Strategy, the Integrated Resources Plan and the Conservation and Load Management Plan. The authority shall issue its initial findings on such investigation by December 1, 1976, and its final findings and order by June 1, 1977; provided that after such final findings and order are issued, the authority shall at least once every two years undertake such further investigations as it deems appropriate with respect to new developments or desirable modifications in pricing principles and rate structures and, after holding at least one public hearing thereon, shall issue its findings and order thereon.
(c) The Department of Energy and Environmental Protection shall coordinate and integrate its actions, decisions and policies pertaining to gas and electric distribution companies, so far as possible, with the actions, decisions and policies of other agencies and instrumentalities in order to further the development and optimum use of the state's energy resources and conform to the greatest practicable extent with the state energy policy as stated in section 16a-35k, the Comprehensive Energy Strategy and the Integrated Resources Plan taking into account prudent management of the natural environment and continued promotion of economic development within the state. The department shall defer, as appropriate, to any actions taken by other agencies and instrumentalities on matters within their respective jurisdictions.
(d) The Commissioner of Energy and Environmental Protection, the Commissioner of Economic and Community Development, and the Connecticut Siting Council may be made parties to each proceeding on a rate amendment proposed by a gas or electric distribution company and shall participate in such proceedings to the extent necessary.
(e) The Public Utilities Regulatory Authority, in a proceeding on a rate amendment proposed by an electric distribution company based upon an alleged need for increased revenues to finance an expansion of the capacity of its electric distribution system, shall determine whether demand-side management would be more cost-effective in meeting any demand for electricity for which the increase in capacity is proposed.
(f) The provisions of this section shall not apply to the regulation of a telecommunications service which is a competitive service, as defined in section 16-247a, or to a telecommunications service to which an approved plan for an alternative form of regulation applies, pursuant to section 16-247k.
(g) The authority may, upon application of any gas or electric public service company, which has, as part of its existing rate plan, an earnings sharing mechanism, modify such rate plan to allow the gas or electric public service company, after a hearing that is conducted as a contested case, in accordance with chapter 54, to include in its rates the reasonable costs of security of assets, facilities, and equipment, both existing and foreseeable, that are incurred solely for the purpose of responding to security needs associated with the terrorist attacks of September 11, 2001, and the continuing war on terrorism.
(P.A. 75-486, S. 5, 69; P.A. 77-614, S. 19, 162, 284, 587, 610; P.A. 78-303, S. 85, 136; P.A. 79-449, S. 4, 7; P.A. 80-482, S. 59, 348; P.A. 81-439, S. 7, 14; P.A. 86-187, S. 5, 10; P.A. 87-202, S. 2; P.A. 94-83, S. 13, 16; P.A. 95-250, S. 1; P.A. 96-211, S. 1, 5, 6; P.A. 98-28, S. 52, 117; P.A. 02-94, S. 1, 2; P.A. 07-242, S. 7; P.A. 11-80, S. 1, 27; P.A. 13-298, S. 10; P.A. 14-134, S. 57.)
History: P.A. 77-614 and P.A. 78-303 replaced “Connecticut energy agency”, i.e. department of planning and energy policy, with office of policy and management and, effective January 1, 1979, replaced public utilities control authority with division of public utility control within the department of business regulation and commissioner of commerce with commissioner of economic development; P.A. 79-449 required conformity “to the greatest practicable extent with the state energy policy” in Subsec. (c); P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 81-439 amended principles to include energy efficiency and development and utilization of renewable energy and to prohibit discrimination against users of renewable energy sources or cogeneration technology; P.A. 86-187 replaced power facility evaluation council with Connecticut siting council in Subsecs. (c) and (d); P.A. 87-202 amended Subsec. (a) principles to include water conservation; P.A. 94-83 added new Subsec. (e) re applicability to telecommunications service which is competitive or to which an approved plan for an alternative form of regulation applies, effective July 1, 1994; P.A. 95-250 and P.A. 96-211 replaced Commissioner and Department of Economic Development with Commissioner and Department of Economic and Community Development; P.A. 98-28 amended Subsec. (d) by adding electric distribution companies, added new Subsec. (e) requiring consideration of demand-side management for electric distribution companies and redesignated former Subsec. (e) as Subsec. (f), effective July 1, 1998; P.A. 02-94 amended Subsec. (a)(4) by adding provisions to include reasonable costs of security associated with the terrorist attacks of September 11, 2001, and the continuing war on terrorism, made a technical change in Subsec. (a)(5) and added Subsec. (g) to allow the department to modify a rate plan with an earnings sharing mechanism to include such security costs; P.A. 07-242 amended Subsec. (a)(3) to add care for energy security and Subsec. (a)(4) to include appropriate staffing levels as part of operating costs; P.A. 11-80 amended Subsecs. (a), (b), (e) and (g) by replacing “Department of Public Utility Control” with “Public Utilities Regulatory Authority” and replacing “department” with “authority”, amended Subsec. (c) by replacing “Department of Public Utility Control” with “Department of Energy and Environmental Protection”, deleting requirement for department to consult with Commissioner of Environmental Protection, Connecticut Siting Council and Office of Policy and Management to coordinate and integrate its actions and deleting requirement that department consider the energy policies of the state, and amended Subsec. (d) by replacing “Commissioner of Environmental Protection” with “Commissioner of Energy and Environmental Protection”, changing “shall” to “may” re commissioner and Connecticut Siting Council being parties to each proceeding and removing Office of Policy and Management from list of parties, effective July 1, 2011; P.A. 13-298 amended Subsecs. (b) and (c) to add provisions re principles, goals or policies in the Integrated Resources Plan, Comprehensive Energy Strategy or Conservation and Load Management Plan, made a conforming change in Subsec. (b) and amended Subsec. (d) to delete provision re alleged need for increased revenues to finance expansion of capital equipment and facilities, effective July 8, 2013; P.A. 14-134 amended Subsecs. (b) and (c) by replacing references to electric companies with references to electric distribution companies and amended Subsec. (d) by deleting reference to electric company, effective June 6, 2014.
Cited. 174 C. 258; 176 C. 191; 216 C. 627; 219 C. 51; Id., 121; 234 C. 624.
Cited. 40 CS 520.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19f. Rate design standards for electric public service companies and municipal electric companies. Determination of appropriateness. Implementation. Electric vehicle charging stations. (a) As used in this section:
(1) “Cost of service” means an electric utility rate for a class of consumer which is designed, to the maximum extent practicable, to reflect the cost to the utility in providing electric service to such class;
(2) “Declining block rate” means an electric utility rate for a class of consumer which prices successive blocks of electricity consumed by such consumer at lower per-unit prices;
(3) “Time of day rate” means an electric utility rate for a class of consumer which is designed to reflect the cost to the utility of providing electricity to such consumer at different times of the day;
(4) “Seasonal rate” means an electric utility rate for a class of consumer designed to reflect the cost to the utility in providing electricity to such consumer during different seasons of the year;
(5) “Electric vehicle time of day rate” means an electric utility rate for a class of consumer designed to reflect the cost to the utility of providing electricity to such consumer charging an electric vehicle at an electric vehicle charging station at different times of the day, but shall not include demand charges;
(6) “Electric vehicle charging station” means an electric component assembly or cluster of component assemblies designed specifically to charge batteries within electric vehicles by permitting the transfer of electric energy to a battery or other storage device in an electric vehicle;
(7) “Public electric vehicle charging station” means an electric vehicle charging station located at a publicly available parking space;
(8) “Publicly available parking space” means a parking space that has been designated by a property owner or lessee to be available to, and accessible by, the public and may include on-street parking spaces and parking spaces in surface lots or parking garages, but shall not include: (A) A parking space that is part of, or associated with, a private residence; (B) a parking space that is reserved for the exclusive use of an individual driver or vehicle or for a group of drivers or vehicles, such as employees, tenants, visitors, residents of a common interest development, or residents of an adjacent building; or (C) a parking space reserved for persons who are blind and persons with disabilities as described in section 14-253a;
(9) “Interruptible rate” means an electric utility rate designed to reflect the cost to the utility in providing service to a consumer where such consumer permits his service to be interrupted during periods of peak electrical demand; and
(10) “Load management techniques” means cost-effective techniques used by an electric utility to reduce the maximum kilowatt demand on the utility.
(b) The Public Utilities Regulatory Authority, with respect to each electric public service company, shall (1) within two years, consider and determine whether it is appropriate to implement any of the following rate design standards: (A) Cost of service; (B) prohibition of declining block rates; (C) time of day rates; (D) seasonal rates; (E) interruptible rates; and (F) load management techniques, and (2) not later than June 1, 2017, consider and determine whether it is appropriate to implement electric vehicle time of day rates for residential and commercial customers. The consideration of said standards by the authority shall be made after public notice and hearing. Such hearing may be held concurrently with a hearing required pursuant to subsection (b) of section 16-19e. The authority shall make a determination on whether it is appropriate to implement any of said standards. Said determination shall be in writing, shall take into consideration the evidence presented at the hearing and shall be available to the public. A standard shall be deemed to be appropriate for implementation if such implementation would encourage energy conservation, optimal and efficient use of facilities and resources by an electric public service company and equitable rates for electric consumers.
(c) Each municipal electric company shall (1) not later than July 1, 2018, consider and determine whether it is appropriate to implement any of the following rate design standards: (A) Cost of service; (B) prohibition of declining block rates; (C) time of day rates; (D) seasonal rates; (E) interruptible rates; and (F) load management techniques, and (2) not later than June 1, 2017, consider and determine whether it is appropriate to implement electric vehicle time of day rates for residential and commercial customers. The consideration of said standards by each municipal electric company shall be made after public notice and hearing. Each municipal electric company shall make a determination on whether it is appropriate to implement any of said standards. Said determination shall be in writing, shall take into consideration the evidence presented at the hearing and shall be available to the public. A standard shall be deemed to be appropriate for implementation if such implementation would encourage energy conservation, optimal and efficient use of facilities and resources by a municipal electric company and equitable rates for electric consumers. No municipal electric company that completed such consideration and determination regarding any rate design standard or electric vehicle time of day rate before July 1, 2017, shall be required to conduct another consideration and determination regarding the same such rate design standard or electric vehicle time of day rate.
(d) The Public Utilities Regulatory Authority, with respect to each electric public service company, and each municipal electric company may implement any standard determined under subsection (b) of this section to be appropriate or decline to implement any such standard. If the authority or a municipal electric company declines to implement any standard determined to be appropriate, it shall state in writing its reasons for doing so and make such statement available to the public.
(e) The provisions of this section shall not apply to any municipal electric company which has total annual sales of electricity for purposes other than resale of five hundred million kilowatt-hours or less.
(P.A. 79-554, S. 1–5; P.A. 80-482, S. 4, 40, 345, 348; P.A. 88-220, S. 1, 11; P.A. 05-288, S. 65; P.A. 11-80, S. 1, 28; P.A. 13-298, S. 64; P.A. 16-135, S. 4; P.A. 18-18, S. 1; 18-50, S. 30.)
History: P.A. 80-482 made division of public utility control an independent department and abolished department of business regulation; P.A. 88-220 deleted Subsec. (e) containing obsolete 1980 reporting requirement; P.A. 05-288 made a technical change in Subsec. (c), effective July 13, 2005; P.A. 11-80 replaced “Department of Public Utility Control” with “Public Utilities Regulatory Authority” and replaced “department” with “authority”, effective July 1, 2011; P.A. 13-298 amended Subsec. (a) to add new Subdivs. (5) and (6) defining “electric vehicle time of day rate” and “public electric vehicle charging station” and to redesignate existing Subdivs. (5) and (6) as Subdivs. (7) and (8), and amended Subsec. (b) to designate existing provision re implementation of rate design standards as new Subdiv. (1), to redesignate existing Subdivs. (1) to (6) as Subparas. (A) to (F) and to add new Subdiv. (2) re implementation of electric vehicle time of day rates, effective July 8, 2013; P.A. 16-135 amended Subsec. (a) by adding new Subdiv. (6) defining “electric vehicle charging station”, redesignating existing Subdiv. (6) as Subdiv. (7) and amending same to redefine “public electric vehicle charging station”, adding new Subdiv. (8) defining “publicly available parking space” and redesignating existing Subdivs. (7) and (8) re interruptible rate and load management techniques, respectively, as Subdivs. (9) and (10), amended Subsec. (b) by deleting references to municipal electric company and, in Subdiv. (2), by replacing “within one year” with “not later than June 1, 2017” and adding “for residential and commercial customers”, added new Subsec. (c) re municipal electric company rate design standards, and redesignated existing Subsecs. (c) and (d) as Subsecs. (d) and (e), effective July 1, 2016; P.A. 18-18 amended Subsec. (c) by replacing “within two years” with “not later than July 1, 2018” and adding provision re municipal electric companies that completed consideration and determination before July 1, 2017, effective May 24, 2018; P.A. 18-50 made identical changes as P.A. 18-18, effective May 24, 2018.
See chapter 101 re municipal electric companies.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19g. Penalty for failure to report nuclear incident not an operating expense. Section 16-19g is repealed, effective May 8, 2013.
(P.A. 80-351, S. 4, 5; P.A. 82-150, S. 6; P.A. 11-80, S. 1; P.A. 13-5, S. 52.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19h. Reopening of water company rate proceedings. The Public Utilities Regulatory Authority may reopen proceedings on a proposed rate amendment filed under section 16-19 and amend its final decision on such filing to adjust the rates of a water company, as defined in section 16-1, to include in the rate base the construction costs associated with additions to a plant that are required by order of the authority, the Department of Public Health or the Department of Energy and Environmental Protection. The adjustment and approval of any rate under this section shall be based on the criteria set forth in section 16-19e.
(P.A. 82-252, S. 5, 6; P.A. 85-259, S. 2; P.A. 96-153, S. 1; P.A. 11-80, S. 1, 29.)
History: P.A. 85-259 authorized rate adjustments to reflect increased costs of purchased electricity and taxes assessed under Sec. 12-75 or 12-76, applied provisions of section to municipal utilities and established a maximum size for water companies subject to section's provisions; P.A. 96-153 deleted the requirement that a water company supply water to “not more than two hundred fifty service connections or one thousand persons on a regular basis” to reopen a rate proceeding, and redefined the circumstances under which a rate proceeding may be reopened; P.A. 11-80 replaced “Department of Public Utility Control” with “Public Utilities Regulatory Authority” or “authority” and replaced “Department of Environmental Protection” with “Department of Energy and Environmental Protection”, effective July 1, 2011.
Cited. 219 C. 121.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19i. Electric company residential customer service charge indicated on bill. Section 16-19i is repealed, effective July 11, 2001.
(P.A. 82-211, S. 2; P.A. 94-242, S. 3, 9; P.A. 98-28, S. 92, 117; P.A. 01-195, S. 180, 181.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19j. Portion of authority staff to be made party to certain rate proceedings. (a) The Public Utilities Regulatory Authority may require a portion of the staff of the authority to be made a party to any proceeding.
(b) Notwithstanding subsection (a) of this section, the authority shall require a portion of the staff to be made a party to proceedings relating to (1) a rate amendment proposed pursuant to section 16-19 by a public service company having more than seventy-five thousand customers, (2) the approval of performance-based incentives pursuant to subsection (b) of section 16-19a, or (3) the approval of any alternative form of regulation pursuant to section 16-247k, provided the authority shall not require a portion of the staff to be made a party to any proceeding described in this subsection if the authority issues a notice of its intent not to do so in writing. The notice shall include the reasons for not requiring a portion of the staff to be made a party. Upon petition of any party so noticed, the authority shall require a portion of the staff to be made a party.
(c) The provisions of section 4-181 shall apply to any proceeding in which a portion of authority staff is made a party.
(d) The authority staff assigned to participate as a party to any rate proceedings described in subdivision (1) of subsection (b) of this section shall review the proposed rate amendment filed by the company and shall file with the directors of the authority proposed modifications of the rate amendment. Such modifications shall carry out the purposes of subsection (a) of section 16-19e and section 16a-35k. Such staff shall appear and participate in the proceedings in support of its proposed modifications and may employ outside consultants knowledgeable in the utility regulation field.
(P.A. 84-342, S. 1, 13; P.A. 95-217, S. 1; P.A. 99-15; P.A. 11-80, S. 31.)
History: P.A. 95-217 amended Subsec. (a) by deleting obsolete references to 1984 and 1985 and made a technical change; P.A. 99-15 amended Subsec. (a) by allowing the assignment of staff as party to any department proceeding, moved language re mandatory assignment of staff in Subsec. (a) to Subsec. (b), designated a portion of existing Subsec. (a) as Subsec. (b) and amended same by designating existing provisions re a rate amendment proposed by a public service company having more than 75,000 customers as Subdiv. (1), making technical changes thereto, by adding new Subdivs. (2) and (3) and by adding language re proviso of when assignment of staff is not mandatory, added new Subsec. (c) re applicability of Sec. 4-181, relettered former Subsec. (b) as (d), and deleted former Subsecs. (c) and (d); P.A. 11-80 amended Subsec. (a) by replacing “Public Utilities Control Authority” with “Public Utilities Regulatory Authority”, replaced “department” with “authority” throughout, and amended Subsec. (d) by replacing “commissioners of the department” with “directors of the authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19k. Costs of educational materials or information on water conservation included as operating costs. The Public Utilities Regulatory Authority may include the costs of educational materials or information on water conservation required pursuant to section 25-32k as operating costs for rate-making purposes upon determination by the authority that such costs are reasonable. The provisions of this section shall apply to any water company required to provide or that voluntarily makes available the educational materials or information on water conservation.
(P.A. 89-266, S. 2; P.A. 94-144, S. 4, 6; P.A. 02-89, S. 23; P.A. 11-80, S. 1.)
History: P.A. 94-144 added requirement to provide educational materials on water conservation to customers, effective July 1, 1994; P.A. 02-89 deleted reference to Sec. 25-32h and references to water company's residential retrofit program, reflecting the repeal by the same public act of said section and the requirement to establish such program; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19l. Authorization of rates that promote water conservation. The Public Utilities Regulatory Authority shall authorize rates for each water company, as defined in section 16-1, that promote comprehensive supply-side and demand-side water conservation. In establishing such rates, the authority shall take into consideration consumers who are low water users, including those consumers who have previously implemented conservation measures, state energy policies, the capital intensive nature of sustaining water systems that minimize water losses and the competition for capital for continued investments in such systems. Such rates shall (1) prioritize demand projections that recognize the effects of conservation and account for declining rates of water consumption in order to minimize the use of a revenue adjustment mechanism, as defined in section 16-262y, following a general rate case, and (2) consider (A) implementation of metering and measures to provide timely price signals to consumers, (B) multiyear rate plans, (C) measures to reduce system water losses, and (D) alternative rate designs that promote conservation.
(P.A. 13-78, S. 1; 13-298, S. 49.)
History: P.A. 13-78 effective June 5, 2013; P.A. 13-298 added provision re authority to take into consideration consumers who are low water users in establishing rates, deleted former Subdiv. (1) re consideration of demand projects that recognize effects of conservation, added new Subdiv. (1) re prioritization of demand projections that recognize effects of conservation and account for declining rates of water consumption, added new Subdiv. (2) designator and redesignated existing Subdivs. (2) to (5) as Subparas. (A) to (D), effective July 8, 2013.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Secs. 16-19m to 16-19q. Decommissioning of nuclear power generating facilities; definitions. Decommissioning financing plan; contents. Decommissioning finance plans; updates; hearing approval. Review of plan; changes. Decommissioning costs; liability. Sections 16-19m to 16-19q, inclusive, are repealed, effective May 8, 2013.
(P.A. 83-343, S. 1–5; P.A. 92-21, S. 1–3; P.A. 98-28, S. 56, 117; P.A. 01-195, S. 122, 181; P.A. 11-80, S. 1; P.A. 13-5, S. 52.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Secs. 16-19r to 16-19t. Three Mile Island nuclear power generating facility damage costs prohibited from being placed in rate base or included as operating expenses. Revenues associated with construction of electric company facilities and Millstone 3 and Seabrook 1 nuclear power generating facilities; rate treatment; proceedings on economic viability of Seabrook 1; low power startup decontamination costs of Seabrook 1 not included in rates. Excess construction costs of Millstone 3 nuclear power generating facility not included in rates. Sections 16-19r to 16-19t, inclusive, are repealed, effective July 11, 2001.
(P.A. 83-99, S. 1, 3; 83-239, S. 1, 2; 83-343, S. 6; P.A. 84-201, S. 1, 4; P.A. 85-519, S. 2, 4; P.A. 87-92, S. 1, 2; 87-589, S. 24, 87; P.A. 01-195, S. 180, 181.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Secs. 16-19u to 16-19w. Monthly reports from nuclear power generating facility licensees re construction costs and progress. Excess construction costs of Seabrook 1 nuclear power generating facility not included in rates. Prohibition on inclusion of certain costs associated with construction of Seabrook 2 nuclear power generating facility in rates. Sections 16-19u to 16-19w, inclusive, are repealed, effective May 8, 2013.
(P.A. 83-99, S. 2, 3; P.A. 84-201, S. 2–4; P.A. 85-519, S. 3, 4; P.A. 11-80, S. 1; P.A. 13-5, S. 52.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19x. Phase-in of costs of certain large electric generating facilities. If the Public Utilities Regulatory Authority finds that a public service company, as defined in section 16-1, plans to begin operation of a new electric generating facility having a capacity of one hundred megawatts or more and operation of the facility would increase the company's revenue requirements by ten per cent or more if all costs associated with construction of the facility were to be included in determining the rates to be charged by the company when the facility becomes commercially operational, the authority shall include such costs as it deems appropriate in accordance with the provisions of this chapter, over a period (A) beginning on the date the facility begins commercial operation, and (B) having a duration of not less than three nor more than ten years, in approximately equal installments, in a manner which will provide optimal short-term and long-term benefits to customers of the company.
(P.A. 84-343, S. 1; P.A. 85-519, S. 1; P.A. 11-80, S. 1.)
History: P.A. 85-519 required department to phase-in construction costs if conditions met instead of considering phase-in of such costs, changed conditions for phase-in, required such costs as department deems appropriate in accordance with chapter 277 to be included in rates and required phase-in to begin on date facility begins commercial operation, to be in approximately equal installments and to be in a manner providing optimal short-term and long-term benefits to customers; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19y. Rate treatment of enhanced 9-1-1 service costs. Section 16-19y is repealed, effective May 31, 1996.
(P.A. 84-416, S. 9, 15; P.A. 96-150, S. 4, 5.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19z. Rate treatment of land purchased, owned or retained by water companies for water supply protection or future water supply use. In any proceeding pursuant to section 16-19 on a rate amendment proposed by a water company, as defined in section 16-1, the Public Utilities Regulatory Authority shall consider including the cost to the company of purchasing, owning or retaining land for water supply protection or future water supply use in the current rate base of the company, subject to the following conditions: (1) The land shall be included in a water supply plan filed and approved pursuant to section 25-32d or shall otherwise be approved by the Commissioner of Public Health pursuant to the general statutes or regulations adopted under the general statutes; (2) the land shall include (A) an area necessary for surface and groundwater supply protection, (B) the impoundment area, (C) a well site, or (D) other appropriate appurtenances such as a tank site or filtration plant site or other necessary facilities; and (3) the purchase, ownership or retention of the land is found by the authority to be prudent considering cost, availability and need. The authority may not require any such company to sell any such land owned by such company as of October 1, 1997, except as provided in section 16-262n.
(P.A. 85-315; P.A. 88-354, S. 9; P.A. 93-381, S. 9, 39; P.A. 95-257, S. 12, 21, 58; P.A. 97-314, S. 1; P.A. 11-80, S. 1.)
History: P.A. 88-354 deleted provision requiring that sale of land “be used for the net economic benefit of consumers of the water company”; P.A. 93-381 replaced commissioner of health services with commissioner of public health and addiction services, effective July 1, 1993; P.A. 95-257 replaced Commissioner and Department of Public Health and Addiction Services with Commissioner and Department of Public Health, effective July 1, 1995; P.A. 97-314 added water supply protection as a reason why a company may retain land under this section and prohibited the department from requiring companies from selling land owned as of October 1, 1997, except as provided in Sec. 16-262n; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19aa. Excess generating capacity. Exclusion of costs associated with. Return on and depreciation of unrecovered investment in generating facilities. Section 16-19aa is repealed, effective May 8, 2013.
(P.A. 88-220, S. 10, 11; P.A. 91-248, S. 7, 13; P.A. 11-80, S. 1; P.A. 13-5, S. 52.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19bb. Application or refund of electric distribution company rate moderation funds. The Public Utilities Regulatory Authority shall require that any funds held by an electric distribution company in excess of the company's authorized return on equity, which funds are intended by the authority to offset future rate increases in lieu of a present rate decrease, shall be applied to such rate increases or shall be refunded to the company's customers within one year of receipt.
(P.A. 87-331, S. 3, 4; P.A. 98-28, S. 93, 117; P.A. 11-80, S. 1; P.A. 14-134, S. 58.)
History: P.A. 98-28 added electric distribution companies and made a technical change, effective July 1, 1998; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011; P.A. 14-134 deleted reference to electric company, deleted “not later than July 1, 1988” and deleted provision re funds collected after July 1, 1988, effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19cc. Semiannual reports from nuclear generating facility licensees re maintenance, refueling and shutdown schedules. Penalty for shutdown for a significant period of time. Section 16-19cc is repealed, effective May 8, 2013.
(P.A. 88-220, S. 9, 11; P.A. 96-180, S. 44, 166; P.A. 11-80, S. 1; P.A. 13-5, S. 52.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19dd. Conservation and load management programs for agricultural customers. All electric public service companies shall implement conservation and load management programs for agricultural customers.
(P.A. 88-93, S. 1, 2; P.A. 94-242, S. 4, 9; P.A. 11-80, S. 1; P.A. 14-134, S. 7.)
History: P.A. 94-242 deleted former Subsec. (b) re study of the impact on agriculture of the change in electric utility rates from residential to demand rate billing and relettered Subsec. (c) as (b), effective June 2, 1994; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, in Subsec. (a), effective July 1, 2011; P.A. 14-134 deleted former Subsec. (a) re moratorium on changing agricultural rates and deleted Subsec. (b) designator, effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19ee. Reports from electric distribution companies concerning electrical outages from power surges. Each electric distribution company shall, in its periodic report to the Public Utilities Regulatory Authority, concerning electrical outages, indicate which outages resulted from a power surge.
(P.A. 90-39, S. 1; P.A. 98-28, S. 94, 117; P.A. 11-80, S. 1; P.A. 14-134, S. 59.)
History: P.A. 98-28 added electric distribution companies and made a technical change, effective July 1, 1998; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011; P.A. 14-134 deleted reference to electric company and deleted “with more than seventy-five thousand customers”, effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19ff. Submetering. Regulations. Application process. (a) Notwithstanding any provisions of the general statutes to the contrary, each electric distribution company shall allow the installation of submeters at (1) a recreational campground, (2) individual slips at marinas for metering the electric use by individual boat owners, (3) commercial, industrial, multifamily residential or multiuse buildings where the electric power or thermal energy is provided by a Class I renewable energy source, as defined in section 16-1, or a combined heat and power system, as defined in section 16-1, or (4) in any other location as approved by the authority where submetering promotes the state's energy goals, as described in the Comprehensive Energy Strategy, while protecting consumers against termination of residential utility service or other related issues. Each entity approved to submeter by the Public Utilities Regulatory Authority, pursuant to subsection (c) of this section, shall provide electricity to any allowed facility, as described in this subsection, at a rate no greater than the rate charged to that customer class for the service territory in which such allowed facility is located, provided nothing in this section shall permit such entity to charge a submetered account for (A) usage for any common areas of a commercial, industrial or multifamily residential building, or (B) other usage not solely for use by such account.
(b) The Public Utilities Regulatory Authority shall adopt regulations, in accordance with the provisions of chapter 54, to carry out the purposes of this section. Such regulations shall: (1) Require a submetered customer to pay only his portion of the energy consumed, which cost shall not exceed the amount paid by the owner of the main meter for such energy; (2) establish standards for the safe and proper installation of submeters; (3) require that the ultimate services delivered to a submetered customer are consistent with any service requirements imposed upon the company; (4) establish standards that protect a submetered customer against termination of service or other related issues; and (5) establish standards for the locations of submeters. The authority may adopt any other provisions it deems necessary to carry out the purposes of this section and section 16-19ee.
(c) The authority shall develop an application and approval process that allows for the reasonable implementation of submetering provisions at allowed facilities, as described in subsection (a) of this section, while protecting consumers against termination of residential utility service or other related issues.
(P.A. 90-39, S. 2; P.A. 98-28, S. 95, 117; 98-149, S. 1, 3; P.A. 02-17, S. 1; P.A. 11-80, S. 1; P.A. 13-298, S. 36; P.A. 14-134, S. 60.)
History: P.A. 98-28 amended Subsec. (a) by adding electric distribution companies, effective July 1, 1998; P.A. 98-149 amended Subsec. (a) to apply provisions to electric distribution companies and to require electric companies and electric distribution companies to provide electricity to recreational campgrounds at a rate no greater than the residential rate, effective June 4, 1998; P.A. 02-17 amended Subsec. (a) by allowing submeters for individual slips at marinas and requiring separate metering and billing at appropriate rates for nonresidential facilities; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 13-298 amended Subsec. (a) to add Subdiv. (1), (2) and (4) designators in existing provisions re recreational campgrounds, individual slips at marinas and other locations approved by the authority, to add Subdiv. (3) re commercial, industrial, multifamily residential or multiuse buildings, to add provision in Subdiv. (4) re promoting state's energy goals while protecting consumers against termination of residential utility service and to add Subparas. (A) and (B) re usage in a common area and other usage not solely for use by submetered account, amended Subsec. (b) to add new Subdiv. (4) re standards that protect against termination of service and to renumber part of existing Subdiv. (4) re locations of submeters as Subdiv. (5), added Subsec. (c) re application and approval process, and made conforming changes, effective July 1, 2013; P.A. 14-134 amended Subsec. (a) by deleting reference to electric company, effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19gg. Factors to be considered during a rate proceeding. (a) During each proceeding on a rate amendment under section 16-19 proposed by an electric or gas public service company, as defined in section 16-1, the Public Utilities Regulatory Authority, when determining rates for individual rate classes, shall give consideration to the energy cost of manufacturers by analyzing the following: (1) The effect of different rates of return among rate classes upon manufacturers; (2) the use of different cost allocation methodologies; (3) the use of flexible pricing; and (4) any other issue deemed relevant by the authority.
(b) In any rate amendment proposed on and after May 19, 1992, by a public service company, as defined by section 16-1, the Public Utilities Regulatory Authority shall analyze the effect on ratepayers of a public service company's provision of reduced or free utility service to its employees.
(P.A. 90-65, S. 1, 5; P.A. 92-99, S. 1, 3; P.A. 11-80, S. 1.)
History: P.A. 92-99 added a new Subsec. (b) re effect on ratepayers of reduced or free utility service for company employees; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19hh. Implementation of flexible pricing and rates. Special contracts for electric service. Exemption from competitive transition assessment. Regulations. Gas rates for certain manufacturers. (a) In order to encourage economic development and maintain the state's manufacturing base, the authority shall: (1) Continue to implement flexible pricing when it determines that such pricing is appropriate; (2) require each water and gas company, as defined in section 16-1, which serves manufacturing customers and has not yet done so, to propose, in its first application for an amendment of rates filed pursuant to section 16-19 on or after October 1, 1993, flexible and innovative rates which promote manufacturing, which rates may include, but not be limited to, economic development, business retention, competitive energy, interruptible, conservation and time of use rates; and (3) require each water and gas company, as defined in said section 16-1, to support and promote the Connecticut manufacturing program for energy technology.
(b) Notwithstanding the provisions of subsection (a) of this section, an electric distribution company that (1) renegotiates, extends or renews any special contract for electric service that is in effect on July 1, 2000, and has a term that expires prior to July 1, 2000, for a term that extends beyond June 30, 2000, or (2) enters into any new special contracts for electric service, shall provide in any such renegotiated, extended, renewed or new contract for the collection of the assessment required under section 16-245g, as provided in said section 16-245g, and for the collection of the charge required in section 16-245l, as provided in said section 16-245l, provided no such contract shall shift costs to other ratepayers.
(c) Notwithstanding the provisions of subsections (a) and (b) of this section, a customer that is (1) an existing or proposed manufacturing plant that will add or create one hundred or more jobs and that will demand at least fifty kilowatts of additional load through the construction or expansion of manufacturing facilities, or (2) an existing manufacturing plant located in a distressed municipality, as defined in section 32-9p, that is located in an enterprise corridor and employing not less than two hundred persons may be exempted from payment of the competitive transition assessment required under section 16-245g. A customer meeting the requirements of subdivision (1) of this subsection may apply to the authority for an exemption from the payment of the competitive transition assessment that relate to the new or incremental load created by such construction or expansion. A customer meeting the requirements of subdivision (2) of this subsection may apply to the authority for an exemption from the payment of the competitive transition assessment. The authority shall hold a hearing on any such application, and if approved, direct the electric distribution company to refrain from collecting a specific portion of the competitive transition assessment from such customer. The authority may adopt regulations pursuant to chapter 54 to implement the provisions of this section.
(d) (1) As used in this subsection, “qualified manufacturer” means a manufacturer described in the North American Industry Classification System Codes 324000 to 325999, inclusive, and “qualified manufacturing facility” means a manufacturing facility owned by a qualified manufacturer that, during any calendar year beginning on or after January 1, 2016, used more than two million five hundred thousand centum cubic feet of natural gas.
(2) Each gas company shall propose, in its first application for an amendment of rates filed pursuant to section 16-19 on or after October 1, 2017, a rate for certain qualified manufacturers that are firm service gas customers of such gas company on October 1, 2017, and that do not qualify for interruptible gas sales or transportation service under such gas company's applicable interruptible service tariffs. No qualified manufacturing facility of a qualified manufacturer shall utilize such rate, as described in this subsection, unless (A) such qualified manufacturer petitions the authority for approval, and (B) the authority grants approval after determining that: (i) Participation of such qualified manufacturer in such rate is in the public interest; (ii) participation of such qualified manufacturer in such rate will provide economic benefits to the state; and (iii) utilization of such rate will not endanger the integrity of the gas distribution system of the gas company.
(3) The rate proposed and approved pursuant to subdivision (2) of this subsection shall allow for a rate equal to not less than seventy per cent of the delivery component in the gas company's firm gas service rate that it charges to large commercial or industrial customers.
(4) A gas company shall recover its revenues lost resulting from the provisions of this subsection through such gas company's decoupling mechanism pursuant to section 16-19tt or a monthly surcharge assessed to all of such gas company's gas firm customers.
(5) Each gas company shall file with the authority, as part of such gas company's annual decoupling filing pursuant to 16-19tt or in a separate proceeding, an annual revenue reconciliation of actual revenues to allowed revenues associated with the implementation of the rate in this subsection.
(P.A. 90-65, S. 2, 5; P.A. 91-61, S. 1; P.A. 93-72; P.A. 98-28, S. 57, 58, 117; P.A. 00-192, S. 81, 102; P.A. 02-141, S. 1; May 9 Sp. Sess. P.A. 02-7, S. 71; P.A. 13-5, S. 3; P.A. 14-134, S. 61; June Sp. Sess. P.A. 17-2, S. 554.)
History: P.A. 91-61 added new Subdivs. (2) and (3) re flexible rates and the manufacturing program for energy technology; P.A. 93-72 applied provisions to water companies and required that companies serving manufacturing companies include with rate amendment application, rates which would encourage and promote manufacturing; P.A. 98-28 designated existing provisions as Subsec. (a) and added new Subsec. (b) re collection of the competitive transition assessment and systems benefits charge, effective April 29, 1998, and amended Subsec. (a) by deleting references to electric companies and making technical changes, effective July 1, 2000; P.A. 00-192 added Subsec. (c) re exemption from portion of payment of competitive transition assessment and re adoption of regulations, effective July 1, 2000; P.A. 02-141 amended Subsec. (c) by designating existing exemption requirements as Subdiv. (1) and adding Subdiv. (2) re exemption for existing manufacturing plant in a distressed municipality that is located in an enterprise corridor and that employs not less than two hundred persons, effective July 1, 2002; May 9 Sp. Sess. P.A. 02-7 amended Subsec. (c) by deleting “a portion of the”, changing “these requirements” to “the requirements of subdivision (1) of this subsection” and adding provisions re total exemption for customers meeting requirements of Subdiv. (2), effective August 15, 2002; P.A. 13-5 amended Subsecs. (a) and (c) to replace “department” with “authority”, effective May 8, 2013; P.A. 14-134 amended Subsec. (b) by deleting reference to electric company, effective June 6, 2014; June Sp. Sess. P.A. 17-2 added Subsec. (d) re gas rates for certain manufacturers, effective October 31, 2017.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19ii. Use of electric resistance space heating. Differential rates. Section 16-19ii is repealed.
(P.A. 90-219, S. 8; P.A. 96-23.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19jj. Alternative dispute resolution mechanisms. The Public Utilities Regulatory Authority shall, whenever it deems appropriate, encourage the use of proposed settlements produced by alternative dispute resolution mechanisms to resolve contested cases and proceedings.
(P.A. 91-61, S. 2; P.A. 11-80, S. 1.)
History: Pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19kk. Finding re conservation and load management programs. Rates of return for conservation and load management programs and programs promoting the state's economic development. Considerations in establishing company's authorized return. Performance-based incentives. Consumer Counsel authorized to retain experts. Regulations. (a) The General Assembly finds that if the earnings of electric, gas, telephone and water public service companies, as defined in section 16-1, are adversely affected by such companies' conservation and load management programs or other programs promoting the state's economic development, energy and other policy, those companies will have a disincentive to implement such programs. The General Assembly further finds that in order to further the implementation of such programs the earnings of electric, gas, telephone and water public service companies should be consistent with the principles and guidelines set forth in this section and sections 16-19e and 16-19ll to 16-19oo, inclusive, and 16a-49 notwithstanding participation in conservation and load management programs and other programs authorized by the Public Utilities Regulatory Authority, promoting the state's economic development, energy and other policy.
(b) The authority shall, on or before July 1, 1993, implement rate-making and other procedures and practices in order to encourage the implementation of conservation and load management programs and other programs authorized by the authority promoting the state's economic development, energy and other policy. Such procedures to implement a modification or elimination of any direct relationship between the volume of sales and the earnings of electric, gas, telephone and water public service companies may include the adoption of a sales adjustment clause pursuant to subsection (j) of section 16-19b, or other adjustment clause similar thereto.
(c) Notwithstanding the provisions of subdivision (4) of subsection (a) of section 16-19e, in a proceeding under subsection (a) of section 16-19 the authority shall consider for an electric, gas, telephone or water public service company, as defined in section 16-1, in establishing the company's authorized return within the range of reasonable rates of return: Quality, reliability and cost of service provided by the company, the reduced or shifted demand for electricity, gas or water resulting from the company's conservation and load management programs approved by the authority, the company's successful implementation of programs supporting economic development of the state and the company's success in decreasing or constraining dependence on the use of petroleum or any other criteria consistent with the state energy or other policy. The authority may also establish other performance-based incentives both related and unrelated to the company's rate of return designed to implement the purposes of said sections 16-19e, 16-19kk to 16-19oo, inclusive, and 16a-49.
(d) In any proceeding before the authority in which a company seeks beneficial rate treatment pursuant to this section, the Office of Consumer Counsel may retain independent experts to provide analysis, evaluation and testimony to address the issue of the appropriateness of such beneficial treatment under consideration in the proceeding, and all reasonable and proper expenses, to provide such analysis, evaluation and testimony, to a maximum of fifty thousand dollars per proceeding, shall be paid by the company and shall be proper rate-making expenses.
(e) The Public Utilities Regulatory Authority may adopt regulations, in accordance with the provisions of chapter 54, to carry out the purposes of this section.
(P.A. 91-248, S. 1, 13; P.A. 92-122, S. 1; P.A. 11-80, S. 1; P.A. 13-5, S. 32; 13-298, S. 54; P.A. 14-134, S. 62.)
History: P.A. 92-122 amended Subsec. (b) to impose a deadline of July 1, 1993, for implementation of rate-making procedures; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 13-5 amended Subsecs. (a) and (c) to make technical changes, effective May 8, 2013; P.A. 13-298 amended Subsec. (b) to make a technical change, effective July 8, 2013; P.A. 14-134 amended Subsec. (a) by making technical changes and amended Subsec. (b) by deleting provisions re authority investigating the relationship between a company's volume of sales and its earnings and re review of regulations and policies to identify disincentives, and by making a technical change, effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19ll. Submittal of legislation re encouraging conservation and load management programs, etc. Section 16-19llis repealed, effective October 1, 2002.
(P.A. 91-248, S. 2, 13; S.A. 02-12, S. 1.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19mm. Consideration of external costs and benefits. In its review of an electric, gas and water public service company's resource planning, the Public Utilities Regulatory Authority shall consider the external costs and benefits of all proposed resources, consistent with the state's energy and other policy, and integrated resource planning principles.
(P.A. 91-248, S. 3, 13; P.A. 11-80, S. 1.)
History: Pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19nn. Encouragement of specific end uses of electricity and gas. The Public Utilities Regulatory Authority may permit electric and gas public service companies, as defined in section 16-1, to encourage specific end uses of electricity and gas to further the state's energy and other policy consistent with integrated resource planning principles and with the provisions of section 16-19d.
(P.A. 91-248, S. 4, 13; P.A. 11-80, S. 1.)
History: Pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19oo. Approval of rate amendments for conservation and load management programs or programs promoting the state's economic development in proceedings other than rate proceedings. Approval of rate mechanisms to recover costs of natural gas infrastructure expansion plan in contested proceedings. In order to promote an electric distribution, gas, telephone and water company's conservation and load management programs or other programs promoting the state's economic development, energy and other policy, the Public Utilities Regulatory Authority may approve rate amendments for any such company, pursuant to subsection (a) of section 16-19 or, upon the request of a company in a proceeding, other than a rate proceeding pursuant to said subsection. Upon filing by a gas company of a natural gas infrastructure expansion plan in accordance with section 16-19ww, the authority may approve in a contested proceeding new rate mechanisms to recover the costs of such plan.
(P.A. 91-248, S. 5, 13; P.A. 11-80, S. 1; P.A. 13-298, S. 50; P.A. 14-134, S. 63.)
History: Pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011; P.A. 13-298 added provision re authority approval in contested proceeding of new rate mechanisms to recover costs of natural gas infrastructure expansion plan, effective July 8, 2013; P.A. 14-134 replaced reference to electric company with reference to electric distribution company, effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19pp. Uncontested proceedings before the authority. Participating parties. The Public Utilities Regulatory Authority shall not hold an uncontested proceeding on any issue affecting ratepayers of the state unless such proceeding provides ratepayers with equal status and the same rights of participation as that of a public service company, as defined in section 16-1. Such ratepayers shall include: Any domestic or qualified nonprofit corporation or association formed in whole or in part to promote conservation or natural beauty, to protect the environment, personal health or biological values, to preserve historical sites, to promote consumer interests, to represent commercial and industrial groups or to promote the orderly development of the areas in which the facility is to be located, if it has filed with the authority a notice of intent to be a party, and such other persons as the authority may at any time deem appropriate.
(P.A. 92-25, S. 3; P.A. 11-80, S. 1.)
History: Pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19qq. Outages of nuclear power generating facilities; rate proceedings; rebuttable presumption of imprudent management. Section 16-19qq is repealed, effective May 8, 2013.
(P.A. 97-21, S. 1, 2; P.A. 11-80, S. 1; P.A. 13-5, S. 52.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19rr. Rates charged by electric distribution companies and electric utilities to veterans' organizations. Each municipal electric utility established under chapter 101 and each electric utility owned, leased, maintained, operated, managed or controlled by any unit of local government under any general statute or special act shall, upon request, provide electricity and each electric distribution company shall, upon request, provide electric distribution services to military veterans' posts and organizations that are exempt from federal taxation under Section 501(c) of the Internal Revenue Code of 1986, or any subsequent corresponding internal revenue code of the United States, as from time to time amended, at the lesser of the residential or commercial rate for the service territory in which the facility is located, provided such rates are not inconsistent with said chapter 101 or any municipal charter or ordinance adopted pursuant thereto, or with any such special act.
(P.A. 99-29; P.A. 00-53, S. 10; P.A. 14-134, S. 64.)
History: P.A. 00-53 changed “501(c)(19)” to “501(c)” and deleted references to definitions in Sec. 16-1; P.A. 14-134 deleted reference to electric company, effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19ss. Solicitations for the provision of temporary electric generation facilities. Section 16-19ss is repealed, effective May 8, 2013.
(P.A. 03-135, S. 17; June Sp. Sess. P.A. 05-1, S. 3; P.A. 07-242, S. 64; P.A. 11-80, S. 38; P.A. 13-5, S. 52.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19tt. Gas and electric distribution companies' distribution revenue decoupling. (a) In any rate case initiated on or after June 4, 2007, and for which a final decision has not been issued prior to July 8, 2013, the Public Utilities Regulatory Authority shall order the state's gas and electric distribution companies to decouple distribution revenues from the volume of natural gas or electricity sales through any of the following strategies, singly or in combination: (1) A mechanism that adjusts actual distribution revenues to allowed distribution revenues, (2) rate design changes that increase the amount of revenue recovered through fixed distribution charges, or (3) a sales adjustment clause, rate design changes that increase the amount of revenue recovered through fixed distribution charges, or both. In making its determination on this matter, the authority shall consider the impact of decoupling on the gas or electric distribution company's return on equity and make necessary adjustments thereto.
(b) In any rate case initiated on or after July 8, 2013, or in a pending rate case for which a final decision has not been issued prior to July 8, 2013, the Public Utilities Regulatory Authority shall order the state's gas and electric distribution companies to decouple distribution revenues from the volume of natural gas and electricity sales. For electric distribution companies, the decoupling mechanism shall be the adjustment of actual distribution revenues to allowed distribution revenues. For gas distribution companies, the decoupling mechanism shall be a mechanism that does not remove the incentive to support the expansion of natural gas use pursuant to the 2013 Comprehensive Energy Strategy, such as a mechanism that decouples distribution revenue based on a use-per-customer basis. In making its determination on this matter, the authority shall consider the impact of decoupling on the gas or electric distribution company's return on equity and make any necessary adjustments thereto.
(P.A. 07-242, S. 107; P.A. 11-80, S. 1; P.A. 13-298, S. 11.)
History: P.A. 07-242 effective June 4, 2007; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011; P.A. 13-298 designated existing provisions as Subsec. (a) and amended same by making a technical change and adding “and for which a final decision has not been issued prior to July 8, 2013,” and added Subsec. (b) re decoupling mechanisms for any rate case initiated on or after July 8, 2013, or in a pending rate case for which a final decision has not been issued prior to July 8, 2013, effective July 8, 2013.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19uu. Adjustments to competitive transition assessment with respect to economic recovery revenue bonds. (a) At such time as economic recovery revenue bonds are issued to fund the economic recovery transfer, the Public Utilities Regulatory Authority shall ensure that the competitive transition assessment charged to customers of each electric distribution company is adjusted to reflect the lower charge to be paid by customers. No electric distribution company may bill any customer an amount for the competitive transition assessment that is in excess of the amount necessary to fund the economic recovery transfer.
(b) At such time as the competitive transition assessment charged to customers has allowed full or partial recovery by the financing entity of any economic recovery revenue bonds and full or partial recovery by the electric distribution company of stranded costs not funded with the proceeds of economic recovery revenue bonds, the authority shall ensure that the competitive transition assessment charged to customers of each electric distribution company is adjusted to reflect, in the case of a partial recovery, the lower charge to be paid by customers, and, in the case of a full recovery, the absence of such assessment. No electric distribution company may bill any customer an amount for the competitive transition assessment that is in excess of the amount necessary to fund economic recovery revenue bonds or stranded costs.
(P.A. 10-179, S. 138; P.A. 11-80, S. 1; P.A. 14-134, S. 65.)
History: P.A. 10-179 effective May 7, 2010; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011; P.A. 14-134 deleted references to electric company, effective June 6, 2014.
See Secs. 16-245e to 16-245k re economic recovery revenue bonds.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19vv. Public service companies' customer deposits. (a) No public service company, other than a telephone company, shall require a deposit from any customer or prospective customer, other than a residential customer or prospective residential customer, in excess of an amount equal to such company's charges for one and one-half months.
(b) The Public Utilities Regulatory Authority shall initiate a proceeding to examine the collection of deposits by public service companies, other than telephone companies, from any customer or prospective customer, other than a residential customer or prospective residential customer. Such examination shall include, but not be limited to, consideration of (1) criteria used to determine creditworthiness of such customers, (2) criteria for when the public service company shall return the deposit plus interest, and (3) provisions for collecting deposits from such customers moving from one location to another within the same service area of the same company. On or before January 1, 2011, the authority shall report, in accordance with section 11-4a, the results of such proceeding to the joint standing committee of the General Assembly having cognizance of matters relating to energy.
(P.A. 10-190, S. 2; P.A. 11-80, S. 1.)
History: P.A. 10-190 effective June 9, 2010; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19ww. Natural gas infrastructure expansion plan. Hurdle rate; rate for new customers added pursuant to the plan; rate mechanism for gas companies to recover prudent investments made pursuant to the plan outside a rate proceeding; assignment of nonfirm margin credit. (a) On or before June 15, 2013, the gas companies, as defined in section 16-1, shall jointly submit to the Commissioner of Energy and Environmental Protection and the Public Utilities Regulatory Authority a natural gas infrastructure expansion plan to provide natural gas service to on and off-main gas customers consistent with the goals of the 2013 Comprehensive Energy Strategy approved by the Commissioner of Energy and Environmental Protection in accordance with section 16a-3d. Such plan shall include steps to expand the natural gas distribution network, increase the rate of cost-effective customer conversions, provide natural gas access for industrial facilities in the state to the greatest extent feasible, lower the costs of adding new customers, ensure the reliability and timely addition of natural gas supply and limit the risk to existing gas customers by incorporating mechanisms to increase or decrease the rate of conversions over time in response to changes in energy prices. Such plan shall include, but not be limited to, the following components: (1) A customer conversion plan and schedule for a ten-year period, (2) an analysis demonstrating the feasibility of reaching the new customer conversion goals as directed by the Comprehensive Energy Strategy for on and off-main customers, (3) a plan for outreach and marketing tailored to each customer segment, (4) a description of steps the gas companies will take to reduce the costs of conversion, (5) a strategy for capacity procurement, (6) a strategy for leveraging third-party investment to finance equipment replacement and main extensions for new customers, (7) a plan to harmonize natural gas infrastructure expansion with steps to reduce methane leakage from existing gas infrastructure, (8) a description of steps the gas companies will take to ensure that potential customers targeted for conversion to natural gas are incented to install efficient equipment and improve the efficiency of the building envelope at the time of conversion, provided such steps include, but are not limited to, providing such customers with information regarding the Home Energy Solutions audit, and to the extent feasible, an application form of said audit, and (9) a proposal for rate changes consistent with the recommendations of the Comprehensive Energy Strategy, including specific cost recovery mechanisms for each customer segment and a description of the rate impact of any proposed rate changes.
(b) Not later than thirty days after the natural gas infrastructure expansion plan is submitted to the commissioner pursuant to subsection (a) of this section, the commissioner shall review the plan and issue a preliminary determination as to whether the plan is consistent with the goals of the Comprehensive Energy Strategy.
(c) In the event that the commissioner determines that the plan is consistent with the Comprehensive Energy Strategy pursuant to subsection (b) of this section, the Public Utilities Regulatory Authority shall, in a contested proceeding during which the authority shall hold a public hearing, approve or modify the plan not later than one hundred twenty days after such plan is submitted to the authority.
(d) In reviewing the natural gas infrastructure expansion plan pursuant to subsection (c) of this section, in order to protect the interests of ratepayers and ensure revenue recovery for gas companies, and consistent with the recommendations of the Comprehensive Energy Strategy, the authority shall, in accordance with section 16-19oo, (1) establish a hurdle rate utilizing a twenty-five-year payback period to compare the revenue requirement of connecting new customers to the gas distribution system to determine the level of new business capital expenditures that will be recoverable through rates, taking into consideration any nonfirm margin credits pursuant to subparagraph (B) of subdivision (4) of this subsection that will offset the expansion costs of the gas companies, provided the authority shall develop a methodology that reasonably accounts for revenues that would be collected from new customers who signaled an intention to switch to natural gas over a period of at least three years within a common geographic location, (2) establish a new rate for new customers added pursuant to the natural gas infrastructure expansion plan to offset incremental costs of expanding natural gas infrastructure pursuant to such plan, (3) establish a rate mechanism for the gas companies to recover prudent investments made pursuant to the approved natural gas infrastructure expansion plan in a timely manner outside of a rate proceeding, provided such mechanism shall take into consideration the additional revenues that the gas companies will generate through implementation of such plan, and (4) notwithstanding the provisions of section 16-19b, effective for the period of the natural gas expansion plan, (A) assign at least half of the nonfirm margin credit to be credited to ratepayers of the gas companies through a purchased gas adjustment clause established pursuant to section 16-19b, and (B) assign the lesser of (i) an amount equal to half of the nonfirm margin credit, or (ii) an amount equal to fifteen million dollars from the nonfirm margin credit annually for all gas companies in the aggregate, apportioned to each gas company in proportion to revenues of the existing and new capacity contracted for by each gas company, to offset expansion costs, including, but not limited to, the costs of adding new state, municipal, residential, commercial and industrial customers.
(e) On or before June 15, 2014, and annually thereafter for a period of nine years, the gas companies shall jointly report to the commissioner and the authority the status and progress of such implementation. Such report shall include, but not be limited to (1) the number of customers added over the previous year, (2) a comparison of actual expenditures to estimated expenditures for the previous year, (3) a forecast of new customers and expenditures for the upcoming year, and (4) any additional information that either the authority or the commissioner deems appropriate.
(P.A. 13-298, S. 51; P.A. 14-94, S. 51.)
History: P.A. 13-298 effective July 8, 2013; P.A. 14-94 amended Subsec. (d) by requiring authority to take into consideration any nonfirm margin credits pursuant to Subdiv. (4)(B) in Subdiv. (1), and by requiring authority to assign a portion of the nonfirm margin credit to credit ratepayers through a purchased gas adjustment clause, adding residential customers to list of expansion customers, and deleting provision re societal benefits in Subdiv. (4), effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19xx. Deferral of public service company tax expense increase. Any public service company, as defined in section 16-1, shall be permitted to defer for recovery in its next general rate case any increase in tax expense, pursuant to public act 15-244*, which is not currently authorized in such company's rates.
(June Sp. Sess. P.A. 15-5, S. 468.)
*Note: Public act 15-244 is entitled “An Act Concerning the State Budget for the Biennium Ending June 30, 2017, and Making Appropriations Therefor, and Other Provisions Related to Revenue, Deficiency Appropriations and Tax Fairness and Economic Development”. (See Reference Table captioned “Public Acts of 2015” in Volume 16 which lists the sections amended, created or repealed by the act.)
History: June Sp. Sess. P.A. 15-5 effective July 1, 2015.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19yy. Compensation rate recovery for electric distribution companies, gas companies or water companies. Notwithstanding any provision of the general statutes, in exercising its discretion regarding whether to allow the recovery through rates of any portion of the compensation package for executives or officers or of any portion of any incentive compensation for employees of any electric distribution company, gas company or water company, as defined in section 16-1, the Public Utilities Regulatory Authority shall consider whether to require that any such compensation that is recoverable through rates be dependent upon the achievement of performance targets established pursuant to section 16-244aa.
(Sept. Sp. Sess. P.A. 20-5, S. 4.)
History: Sept. Sp. Sess. P.A. 20-5 effective October 2, 2020.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19zz. Interim rate decreases, low-income rates and economic development rates for customers of electric distribution companies. Not later than November 1, 2020, the Public Utilities Regulatory Authority may initiate a proceeding or proceedings to consider the implementation of an interim rate decrease, low-income rates and economic development rates for customers of electric distribution companies, pursuant to its authority in subsection (g) of section 16-19 and sections 16-19e and 16-19oo.
(Sept. Sp. Sess. P.A. 20-5, S. 5.)
History: Sept. Sp. Sess. P.A. 20-5 effective October 2, 2020.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Secs. 16-19aaa to 16-19ddd. Reserved for future use.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19eee. Definitions. As used in this section and sections 14-12, 16-19fff, 16-19ggg, 16a-3e and 43-3a:
(1) “Battery electric vehicle” means any vehicle that operates solely by use of a battery or battery pack, or that is powered primarily through the use of an electric battery or battery pack and uses a flywheel or capacitor that stores energy produced by an electric motor or through regenerative braking to assist in vehicle operation;
(2) “Electric vehicle” means any battery electric vehicle, fuel cell electric vehicle, plug-in hybrid electric vehicle or range-extended battery electric vehicle;
(3) “Fuel cell electric vehicle” means any vehicle that operates solely by use of a fuel cell, as defined in subparagraph (B)(i) of subdivision (113) of section 12-412;
(4) “Hybrid electric vehicle” means a motor vehicle that allows power to be delivered to the driver wheels solely by a battery-powered electric motor that also incorporates the use of a combustion engine to provide power to the battery, or any vehicle that allows power to be delivered to the driver wheels by either a combustion engine or by a battery-powered electric motor, or both;
(5) “Plug-in hybrid electric vehicle” means a hybrid electric vehicle that has the capability to charge the battery or batteries used for vehicle propulsion from an off-vehicle electric source, such that the off-vehicle source cannot be connected to the vehicle while the vehicle is in motion; and
(6) “Range-extended battery electric vehicle” means a vehicle (A) powered predominantly by a zero-emission energy storage device, (B) with a manufacturer rating of more than seventy-five all-electric miles, and (C) equipped with a backup auxiliary power unit that does not operate until the energy storage device is fully depleted.
(P.A. 16-135, S. 1.)
History: P.A. 16-135 effective July 1, 2016.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19fff. Electric vehicle charging load projections. (a) The Public Utilities Regulatory Authority shall require each electric distribution company, as defined in section 16-1, to integrate electric vehicle charging load projections into such company's distribution planning. Such projections shall be based on the number of electric vehicles, as defined in section 16-19eee, registered in the state and projected increases or decreases in sales of such vehicles.
(b) Not later than January 1, 2017, and annually thereafter, each electric distribution company shall publish on such company's Internet web site a report explaining the incorporation of such company's electric vehicle charging load projections for the company's distribution planning.
(P.A. 16-135, S. 5.)
History: P.A. 16-135 effective July 1, 2016.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-19ggg. Public electric vehicle charging stations. Parking restrictions. (a) The owner or operator of a public electric vehicle charging station, as defined in section 16-19f, that requires payment of a fee shall provide multiple payment options that allow access by the public.
(b) The owner or operator of a public electric vehicle charging station shall disclose the location and characteristics of each such public electric vehicle charging station, including, but not limited to, the address, voltage and timing restrictions, to the federal database operated by the United States Department of Energy Alternative Fuels Data Center.
(c) No person shall park in a space equipped with a public electric vehicle charging station, unless such person is operating a plug-in hybrid electric vehicle or battery electric vehicle, as defined in section 16-19eee. Violation of this subsection shall be an infraction.
(d) The owner or operator of a public electric vehicle charging station may impose restrictions on the amount of time that an electric vehicle may be charged at the charging station.
(e) (1) Owners or operators of public electric vehicle charging stations that require payment of a fee shall not require persons desiring to use such public electric vehicle charging station to pay a subscription fee or otherwise obtain a membership in any club, association or organization as a condition of using such public electric vehicle charging station.
(2) Notwithstanding subdivision (1) of this subsection, owners or operators of public electric vehicle charging stations that require payment of a fee may have different price schedules that are conditioned on a subscription or membership in a club, association or organization.
(P.A. 16-135, S. 7; P.A. 19-161, S. 9.)
History: P.A. 16-135 effective July 1, 2016; P.A. 19-161 amended Subsec. (c) to add provision re violation of subsection to be an infraction.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-20. Inadequate service or unreasonable rates; petition to authority. Small community water system rates and service. (a) As used in this section, “private water company” means a corporation, company, association, joint stock association, partnership, other entity or person, or lessee thereof, owning, leasing, maintaining, operating, managing or controlling any pond, lake, reservoir, stream, well or distributing plant or system employed for the purpose of supplying water to not less than two service connections or twenty-five persons, but does not include a municipal waterworks system established under chapter 102, a district, metropolitan district, municipal district or special services district established under chapter 105, chapter 105a or any other general statute or any public or special act which is authorized to supply water, or any other waterworks system owned, leased, maintained, operated, managed, or controlled by any unit of local government under any general statute or any public or special act.
(b) If any public service company or private water company unreasonably fails or refuses to furnish adequate service at reasonable rates to any person within the territorial limits within which the company has, by its charter, authority to furnish the service or, in the case of a nonfranchised, nonchartered private water company, the general territorial limits within which it operates, and if no other specific remedy is provided in this title or in regulations adopted thereunder, the person may bring a written petition to the Public Utilities Regulatory Authority alleging the failure or refusal. The authority shall investigate and, not more than sixty days after receipt of a petition, (1) if appropriate, issue an order prescribing the service to be furnished by the company, the conditions under which and maximum rates or charges at which the service shall be furnished, or (2) order that a hearing be held on the matter or that the matter be set for alternative dispute resolution. If at any time during such sixty-day period, any party in interest requests a hearing, the authority shall, after notice to all parties and not more than ninety days after receiving the request, hold a hearing and, if appropriate, issue an order prescribing the service to be furnished by the company and the conditions under which and maximum rates or charges at which the service shall be furnished.
(c) The authority, on its own initiative, or upon request by the Commissioner of Public Health, may initiate an investigation to determine whether the rates of a small community water system are inadequate for such water system to maintain economic viability and provide adequate service to its customers. As used in this subsection, “small community water system” means a water system that is not required to submit a water supply plan under section 25-32d. The authority shall, not more than one hundred fifty days after the commencement of such investigation, if appropriate, issue an order prescribing the appropriate service to be furnished by the water system and the appropriate rates or charges that are necessary to furnish such service. Prior to the issuance of any such order raising rates or charges of such water system's customers, the authority, in consultation with the Office of Consumer Counsel and the Attorney General, shall consider the financial impact that any such rate increase may have on such water system's ratepayers. If such rate increase is one hundred per cent or more, such increase shall be phased in over the course of a two-year period. If at any time during such investigation any party in interest requests a hearing, the authority shall, after notice to all parties and not more than thirty days after receiving the request, hold a hearing and, if appropriate, issue an order prescribing the service to be furnished by the small community water system and the appropriate rates or charges at which the service shall be furnished. If such hearing is held, the authority shall have commensurate additional time to issue such order.
(1949 Rev., S. 5410; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 60, 348; P.A. 81-297, S. 2; 81-358, S. 1; P.A. 97-8; P.A. 98-29, S. 1, 3; P.A. 11-80, S. 1; P.A. 15-89, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 81-297 required department to hold hearing within 150 days after receiving petition; P.A. 81-358 made petition procedure available to persons residing within general territorial limits of a nonfranchised, nonchartered water company; P.A. 97-8 added as a condition to bringing a petition that no other specific remedy be available in title 16 or in regulations, deleted provision re automatic hearing procedures and added Subdiv. (1) re issuing orders, Subdiv. (2) re ordering hearings or alternate dispute resolution, and provisions holding hearings upon request; P.A. 98-29 added new Subsec. (a) defining “private water company”, designated existing provisions as Subsec. (b) and inserted references to private water companies, effective May 19, 1998; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, in Subsec. (b), effective July 1, 2011; P.A. 15-89 added Subsec. (c) re small community water system rates and service, effective June 22, 2015.
Right to require and considerations proper as to extension of gas main. 91 C. 134. Application of section to telephone service. 99 C. 284. Public utility is not under duty to extend service at regular rates except where reasonable. 114 C. 628. Section is not exclusive remedy; equity may enjoin shutting off of service where there is honest dispute over bill. 123 C. 180. Entitles a person living within a franchised area of utility to an extension of service only when extension of service would be reasonable under the circumstances. 142 C. 359. A public utility company need not provide service without a reasonable payment therefor, and reasonableness of amounts charged ought to be questioned in an administrative proceeding before commission and not in a collateral proceeding. 144 C. 195. Cited. 145 C. 243. Jurisdiction of commission is not exclusive; in action by water company on promissory note where defendants relied on doctrine of unilateral mistake and inequitable conduct in execution of contract, court having obtained jurisdiction should retain it as to whole controversy. 149 C. 442. Cited. 159 C. 327; 169 C. 344.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-21. Change of rates fixed pursuant to charter or contract. Whenever any rate of any public service company chartered by or organized under the laws of this state exists or is charged pursuant to charter, contract or any agreement or understanding, and is in whole or in any respect discriminatory or more or less than just, reasonable and adequate to provide properly for the public convenience, necessity and welfare, such company or any town, city or borough within which, or between which and any other town, city or borough in this state, any such company is furnishing service, or any ten patrons of any such company, may bring a written petition to the Public Utilities Regulatory Authority alleging that such rate is discriminatory or more or less than just, reasonable and adequate. Thereupon, the authority shall fix a time and place for a hearing upon such petition and shall mail notice thereof to the parties in interest and give public notice thereof at least one week prior to such hearing. Upon such hearing, the authority may, if it finds such rate to be discriminatory or more or less than just, reasonable and adequate to enable such company to provide properly for the public convenience, necessity and welfare, determine and prescribe just and reasonable maximum rates or charges to be thereafter made by such company.
(1949 Rev., S. 5411; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 61, 348; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
Is declaratory of power already possessed by commission; power to make rates includes power to modify rate-fixing contracts; municipal charter held to give no power to fix rates on water. 101 C. 156. Application to contracts between water company and city fixing rates. 106 C. 577. Company may increase rates above those specified in contract only by petition to commission and on its finding and order. 132 C. 496. Cited. 169 C. 344.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-22. Rates; transfer of assets or franchise; burden of proof. At any hearing involving a rate or the transfer of ownership of assets or a franchise of a public service company, the burden of proving that said rate under consideration is just and reasonable or that said transfer of assets or franchise is in the public interest shall be on the public service company. The provisions of this section shall not apply to the regulation of a telecommunications service which is a competitive service, as defined in section 16-247a.
(1949 Rev., S. 5412; P.A. 75-486, S. 13, 69; P.A. 94-83, S. 14, 16.)
History: P.A. 75-486 made section applicable to transfers of asset ownership or franchise; P.A. 94-83 added provision re applicability to competitive telecommunications service, effective July 1, 1994.
Cited. 158 C. 626; 183 C. 128.
Cited. 24 CS 446; 29 CS 253; Id., 379; 30 CS 36; Id., 149.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-23. Regulations and service prescribed by authority deemed reasonable. All regulations, practices and service prescribed by the Public Utilities Regulatory Authority shall be in force and prima facie reasonable, unless suspended or found otherwise in an action brought for that purpose or until changed or modified by the authority.
(1949 Rev., S. 5413; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 62, 348; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-24. Classification of service. The Public Utilities Regulatory Authority shall have power to require each public service company furnishing gas or electricity to establish classifications of service based upon the quantity used, the time when used, the purpose for which used, the duration of use and any other reasonable consideration, and to establish all relevant factors, including rates and charges, that take into consideration competition from alternative services and the interest of all parties concerned.
(1949 Rev., S. 5414; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 63, 348; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-24a. Low-income discounted rates for electric and gas service. (a) On or before June 30, 2012, the Department of Energy and Environmental Protection shall conduct a proceeding regarding development of low-income discounted rates for service provided by electric distribution and gas companies, as defined in section 16-1, to low-income customers with an annual income that does not exceed sixty per cent of median income. Such proceeding shall include, but not be limited to, a review, for individuals who receive means-tested assistance administered by the state or federal governments, of the current and future availability of rate discounts through the department's electricity purchasing pool operated pursuant to section 16a-14e, energy assistance benefits available through any plan adopted pursuant to section 16a-41a, state funded or administered programs, conservation assistance available pursuant to section 16-245m, assistance funded or administered by said department or the Department of Social Services, or matching payment program benefits available pursuant to subsection (b) of section 16-262c. The department shall (1) coordinate resources and programs, to the extent practicable; (2) develop rates that take into account the indigency of persons of poverty status and allow such persons' households to meet the costs of essential energy needs; (3) require the households to have a home energy audit paid from the Energy Efficiency Fund as a prerequisite to qualification; (4) prepare an analysis of the benefits and anticipated costs of such low-income discounted rates; and (5) review utility rate discount policies or programs in other states.
(b) The department shall determine which, if any, of its programs shall be modified, terminated or have their funding reduced because such program beneficiaries would benefit more by the establishment of a low-income or discount rate. The department shall establish a rate reduction that is equal to the anticipated funds transferred from the programs modified, terminated or reduced by the department pursuant to this section and the reduced cost of providing service to those eligible for such discounted or low-income rates, any available energy assistance and other sources of coverage for such rates, including, but not limited to, generation available through the electricity purchasing pool operated by the department. The department may issue recommendations regarding programs administered by the Department of Social Services.
(c) The department shall order (1) filing by each electric distribution company of proposed rates consistent with the department's decision pursuant to subsection (a) of this section not later than sixty days after its issuance; and (2) appropriate modification of existing low-income programs.
(d) The cost of low-income and discounted rates and related outreach activities pursuant to this section shall be paid (1) through the normal rate-making procedures of the department, (2) on a semiannual basis through the systems benefits charge for an electric distribution company, and (3) solely from the funds of the programs modified, terminated or reduced by the department pursuant to this section and the reduced cost of providing service to those eligible for such discounted or low-income rates, any available energy assistance and other sources of coverage for such rates, including, but not limited to, generation available through the electricity purchasing pool operated by the department.
(e) On or before February 1, 2012, the department shall report, in accordance with section 11-4a, to the joint standing committee of the General Assembly having cognizance of matters relating to energy regarding the benefits and costs of the low-income or discounted rates established pursuant to subsection (a) of this section, including, but not limited to, possible impacts on existing customers who qualify for state assistance, and any recommended modifications. If the low-income rate is not less than ninety per cent of the standard service rate, the department shall include in its report steps to achieve that goal.
(P.A. 11-80, S. 112.)
History: P.A. 11-80 effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-25. Time and place of hearings. Notice. The Public Utilities Regulatory Authority shall fix a time and place for all hearings and shall mail notice thereof to such parties in interest as the authority deems necessary and give public notice thereof at least one week prior to any such hearing.
(1949 Rev., S. 5415; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 64, 348; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
Cited. 162 C. 51.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-25a. Hearings on Office of Consumer Counsel petitions. If the Office of Consumer Counsel files a petition with the Public Utilities Regulatory Authority concerning matters affecting utility services for consumers in the state, the authority shall, not later than thirty days after receiving the petition, notify the Office of Consumer Counsel whether it will hold a hearing on the petition. If the authority so notifies the Office of Consumer Counsel, it shall hold the hearing not later than ninety days after providing such notice.
(P.A. 83-37; P.A. 88-22, S. 3; P.A. 11-80, S. 1.)
History: P.A. 88-22 substituted office of consumer counsel for the division of consumer counsel; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-26. Public hearing to be held in locality affected. (a) In any matter within the jurisdiction of the Public Utilities Regulatory Authority involving rates, charges or accommodation of the public, which concerns:
(1) An electric distribution company that has a service area of not more than seventeen towns, the authority shall hold hearings on such matter in at least two towns within the service area of such company;
(2) An electric distribution company that has a service area of eighteen or more towns, the authority shall hold hearings on such matter in at least three towns within the service area of such company; or
(3) Any other public service company, the authority shall hold a hearing or hearings on such matter in at least one town within the service area of such company.
(b) The authority shall select each town described in subsection (a) of this section for a hearing to suit as nearly as practicable the convenience of persons affected by the matter. Upon petition of not fewer than twenty-five persons affected by the matter, any such hearing shall be held in the evening. The authority shall have the discretion to hold the remainder of its hearings on a matter, if any, anywhere within the state of Connecticut.
(1949 Rev., S. 5416; P.A. 75-486, S. 19, 69; P.A. 77-614, S. 162, 610; P.A. 79-429, S. 1; P.A. 80-482, S. 65, 348; P.A. 11-80, S. 1; P.A. 15-135, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority, required that at least one hearing be held within a town in the company's service area rather than in “county where such town [i.e. town to be affected] is located” and further clarified provisions; P.A. 77-614 replaced authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 79-429 required petition by at least twenty-five people for evening session rather than for hearing to be held in town within service area; P.A. 80-482 made division of public utility control an independent department and deleted reference to abolished department of business regulation; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 15-135 designated existing provisions re hearings on certain matters within jurisdiction of Public Utilities Regulatory Authority as Subsec. (a) and amended same to add Subdiv. (1) re electric distribution company that has service area of not more than 17 towns and Subdiv. (2) re electric distribution company that has service area of 18 or more towns and to designate existing provision re hearings for other public service company as Subdiv. (3), designated existing provisions re hearings to suit convenience of persons affected as Subsec. (b) and amended same to add provision re authority to select town for hearing, and made technical changes.
Petitioner did not have the right to have a hearing in a particular town when a whole county was affected. 29 CS 151.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-27. Returns from public service companies. Reports from community antenna television companies. Penalty. Form 8-K reports. (a) The Public Utilities Regulatory Authority shall, on or before December thirty-first, annually, furnish to each public service company, except community antenna television companies, duplicate blank report forms, which may be in such format as the authority prescribes or the same blank report forms required by the Interstate Commerce Commission or its successor agency, the Federal Communications Commission or the Federal Energy Regulatory Commission. Any company which does not receive the forms by said date shall request the authority to furnish the forms. Each such company shall return one report form with all questions fully answered to the authority not later than the following May thirty-first or, where the authority has authorized an accounting period other than December thirty-first, the company shall return its completed form no later than one hundred fifty days following the close of the company's accounting period. The authority may, for good cause shown, grant an extension of such deadline of up to sixty days, provided the company desiring an extension files a request in writing setting forth the reasons for such request. All such reports shall be for the year ending on December thirty-first, or such other annual accounting period as the authority may authorize. Each such company shall make such reports strictly according to the forms provided. If the company finds it impracticable to answer all the items in detail as required, it shall state in its report the reasons why such details cannot be given, but no such company shall be excused from giving such details for the reason that it does not keep its accounts in such manner as will enable it to do so.
(b) Each community antenna television company shall, not later than April thirtieth annually, file with the authority a report on the company's operations. Such report shall be prepared in accordance with generally accepted accounting principles and shall be for a twelve-month period corresponding to the company's fiscal year.
(c) All reports under subsections (a) and (b) of this section shall be signed and sworn to by the chief executive officer, president or vice president and chief financial officer, treasurer or assistant treasurer of the company, or by a majority of the trustees or receivers making the same.
(d) Each public service company shall also file with the authority one copy of each Securities and Exchange Commission Form 8-K “Current Report” at the same time the report is filed with the commission.
(1949 Rev., S. 5418; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 66, 348; P.A. 82-252, S. 1; P.A. 83-29, S. 2; P.A. 85-33, S. 2; 85-509, S. 3, 11; P.A. 90-221, S. 5, 15; P.A. 92-25, S. 2; P.A. 96-222, S. 18, 41; P.A. 07-217, S. 60; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 82-252 permitted department to use forms required by Federal Energy Regulatory Commission, allowed companies option to return forms 30 days after receipt and authorized chief executive officers, chief financial officers and assistant treasurers to sign reports; P.A. 83-29 changed deadline for report from March thirty-first to April thirtieth; P.A. 85-33 required companies to request forms if not received and added new Subsec. requiring companies to file SEC form 8-K, incorporated as Subsec. (d); P.A. 85-509 designated existing provisions as Subsecs. (a) and (c), limited Subsec. (a) to public service companies other than community antenna television companies, transferred language from Sec. 16-28 re procedure for making reports to Subsec. (a) and inserted new Subsec. (b) re community antenna television company reports; P.A. 90-221 changed deadline for reports in Subsec. (a) from April thirtieth to May thirty-first and added provision allowing the department to grant an extension of time in which to file report and in Subsec. (c) deleted penalty provision for companies' failure to file a report; P.A. 92-25 amended Subsec. (a) allowing companies having accounting periods other than December thirty-first to return form no later than 150 days following the close of their accounting periods; P.A. 96-222 amended Subsec. (a) to insert “or its successor agency” after “Interstate Commerce Commission”, effective July 1, 1996; P.A. 07-217 made a technical change in Subsec. (c), effective July 12, 2007; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-28. Correction of returns and reports. When a report filed by a public service company under subsection (a) of section 16-27 or an annual report filed by a community antenna television company under subsection (b) of said section seems to the Public Utilities Regulatory Authority defective or erroneous, the authority may notify the company making the same and require the amendment of such report within fifteen days from the time of giving such notice, under the same penalty as is provided for refusing or neglecting to make such report; and the authority may examine the officers, agents, employees, books, records, accounts, vouchers, plant and equipment of such company and may correct such items in such report as, upon such examination, the authority may find ought to be corrected.
(1949 Rev., S. 5419; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 67, 348; P.A. 85-509, S. 4, 11; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 85-509 made technical changes for consistency with amendments to Sec. 16-27; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-29. Reports from municipalities. The Public Utilities Regulatory Authority shall, annually, on or before December thirty-first, or June thirtieth in a municipality which has adopted a uniform fiscal year, furnish to every municipality or department thereof owning, leasing, operating or managing a plant for the supplying or furnishing of any public utility, except water service, blanks for annual reports in such form as the authority may prescribe. Each such municipality or department shall return one of such reports to the authority on or before the following May thirty-first, or the following October thirty-first in a municipality which has adopted a uniform fiscal year, with all questions thereon fully answered. The authority may, for good cause shown, grant an extension of such deadlines of up to sixty days, provided such municipality or department desiring an extension files a request, in writing, setting forth the reasons for such a request. All reports shall be for the year ending December thirty-first, or June thirtieth in a municipality which has adopted a uniform fiscal year and shall be sworn to by the general superintendent of the plant or utility for which the report is required and by such other person or persons as may be designated by such municipality or department. Each such municipality or department shall make such annual reports strictly according to the form provided and, if it finds it impracticable to answer all the items in detail as required, shall state in the report the reasons why such details cannot be given. No such municipality or department shall be excused from giving such details for the reason that it does not keep its accounts in such manner as will enable it to do so. The authority may prescribe the method for keeping the accounts pertaining to such utility, except water service, and all other utilities reporting to the authority. When any such report seems to the authority defective or erroneous, it may notify the municipality making the same and require the amendment of such report within fifteen days from the time of giving such notice; and the authority may examine the officers, agents, employees, books, records, accounts, vouchers, plant and equipment of such municipality or department pertaining to such utility, except water service, and may correct such items in such report as, upon such examination, the authority may find ought to be corrected.
(1949 Rev., S. 5420; P.A. 74-172, S. 1, 2; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 68, 348; P.A. 81-472, S. 25, 159; P.A. 85-33, S. 3; P.A. 90-221, S. 6, 15; P.A. 11-80, S. 1; P.A. 13-78, S. 5.)
History: P.A. 74-172 added references to dates applicable to municipalities which have adopted the uniform fiscal year; P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced authority with division of public utility control within the department of business regulation; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 81-472 made technical changes; P.A. 85-33 extended deadline for return of reports by one month to April thirtieth or October thirty-first and made technical changes; P.A. 90-221 changed report deadline from April thirtieth to May thirty-first and added provision allowing the department to grant an extension of time in which the file report; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 13-78 added provisions re exception for water service, effective June 5, 2013.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-30. Returns from motor bus companies. Penalty. Section 16-30 is repealed, effective June 29, 1993.
(1949 Rev., S. 5421; P.A. 73-334; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 79-610, S. 8, 43; P.A. 93-307, S. 32, 34.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-31. Remission of forfeitures by the Attorney General. Section 16-31 is repealed.
(1949 Rev., S. 5145; P.A. 90-221, S. 14, 15.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32. Annual audit report. (a) Except as provided in subsection (b) of this section, each public service company shall have an annual comprehensive audit and report made of its accounts and operations by independent public accountants satisfactory to the Public Utilities Regulatory Authority. A copy of such annual audit report shall be filed with the authority, together with the company's annual report. In the absence of such an audit report, or if the authority, after notice and opportunity for a hearing, determines that such audit report is insufficient or unsatisfactory, the authority shall cause such an audit to be made at the expense of the company either by independent public accountants satisfactory to the authority or by any staff of the authority engaged in the activities contemplated by subsection (b) of section 16-8. The authority may waive the compliance with the provisions of this section by any public service company whose annual gross income is less than one hundred thousand dollars.
(b) In lieu of the audit and report described in subsection (a) of this section, a telephone company may elect to file with the Public Utilities Regulatory Authority the annual consolidated report on Securities and Exchange Commission Form 10-K that the parent company of the telephone company submits to said commission, provided such report includes an independently audited financial statement of the parent company. A telephone company serving more than seventy-five thousand customers shall also file with the authority unaudited financial statements regarding operations specific to the state of Connecticut.
(1949 Rev., S. 5422; 1967, P.A. 141; 1969, P.A. 195; P.A. 75-486, S. 14, 69; P.A. 77-222; 77-614, S. 162, 610; P.A. 80-482, S. 69, 348; P.A. 82-252, S. 2; P.A. 89-291, S. 3, 8; P.A. 96-222, S. 19, 41; P.A. 11-80, S. 1; P.A. 14-134, S. 30; P.A. 17-45, S. 1.)
History: 1967 act changed limit on gross income for waiver from $3,000 to $5,000; 1969 act raised limit to $10,000; P.A. 75-486 replaced public utilities commission with public utilities control authority and added provisions for additional audit performed by independent auditors or authority staff if report found to be insufficient or unsatisfactory; P.A. 77-222 raised gross income limit to $25,000; P.A. 77-614 replaced the authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division of public utility control an independent department and deleted reference to abolished department of business regulation; P.A. 82-252 deleted obsolete reference to railroad companies and increased annual gross income of companies that may be excluded from section provisions, from under $25,000 to under $50,000; P.A. 89-291 increased annual gross income requirement to $100,000, effective July 1, 1989, and applicable to audits covering fiscal years commencing on or after January 1, 1989; P.A. 96-222 inserted “or its successor agency” after “Interstate Commerce Commission”, effective July 1, 1996; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 14-134 deleted reference to telegraph companies and express companies, effective June 6, 2014; P.A. 17-45 designated existing provisions re annual audit and report as Subsec. (a), added Subsec. (b) re telephone company may elect to file annual consolidated report on Securities and Exchange Commission Form 10-K, effective June 13, 2017.
Cited. 174 C. 556.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32a. Filing re procurement practices. Public hearing. Regulations re competitive bidding. The Public Utilities Regulatory Authority shall by regulation require public service companies to file statements of their procurement policies and practices whenever there is a material change to such policies or practices. Where, after investigation, the authority determines that competitive bidding seems likely to reduce procurement costs without impairing quality, continuity or dependability of service or the ability to respond to emergencies, the authority may, after notice and public hearing, establish such regulations as it deems necessary to provide for competitive bidding in appropriate cases, but only if the contract price exceeds fifty thousand dollars in each such case.
(P.A. 75-486, S. 12, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 70, 348; P.A. 98-121, S. 1; P.A. 11-80, S. 1.)
History: P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division of public utility control an independent department and deleted reference to abolished department of business regulation; P.A. 98-121 inserted “whenever there is a material change to such policies or practices”; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32b. Regional water authority or water district to submit annual report. Each regional water authority and each regional water district shall, annually, submit to the Public Utilities Regulatory Authority, on or before May thirty-first, its annual report for the preceding calendar year, in such form and manner as the authority may prescribe. The authority may, for good cause shown, grant an extension of such deadline of up to sixty days, provided the regional water authority or regional water district desiring an extension files a request in writing setting forth the reasons for such request.
(P.A. 90-221, S. 4, 15; P.A. 11-80, S. 1.)
History: Pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32c. Water company rate adjustments. Application. Notice to customers. (a) Notwithstanding the provisions of section 16-19, a water company, as defined in section 16-1, may charge rates in excess of or less than those approved by the Public Utilities Regulatory Authority, after a limited hearing as deemed appropriate by the authority, by adjusting existing rates to compensate for increases or decreases only in the company's following expenses: (1) The price of water purchased for redistribution to its customers from another water company or governmental authority whose rates have been adjusted; (2) the price of gas or electricity purchased from a gas or electric distribution company, electric supplier or governmental authority whose rates have been adjusted; (3) federal, state and local taxes or other government assessments on revenue, income or property; (4) fees charged by any federal or state agency or other government entity that has jurisdiction over the company; (5) fees, or changes in fees, charged for federal and state mandated monitoring of the quality of the company's water supply; and (6) changes in expenses due to inflation that, in the opinion of the authority, are subject to an inflation adjustment in rate schedule proceedings held pursuant to section 16-19. The amount of any adjustment of rates shall not exceed the aggregate net amount of increases and decreases in the expenses set forth in this subsection on an annualized basis, provided that such adjustment shall not cause the company's projected return on equity for the following twelve-month period to exceed the return on equity authorized in the company's most recent proceeding for an amendment of rates pursuant to section 16-19. A company may adjust its rates pursuant to this section only (A) when the aggregate effect of increases or decreases in such expenses equals or exceeds one half of one per cent of the company's operating revenues for the twelve-month period commencing after the authority issued a decision on the company's most recent application for an amendment of rates pursuant to section 16-19, and (B) once in any twelve-month period. A company shall not adjust its rates pursuant to this section in any twelve-month period following approval of an amendment of rates by the authority pursuant to section 16-19.
(b) A company applying to the authority for an adjustment of rates pursuant to subsection (a) of this section shall include in its application (1) the amount by which each of the expenses set forth in subsection (a) of this section shall increase or decrease, (2) the basis for each such increase or decrease, (3) the total amount of the proposed adjustment of rates, (4) the proposed amount by which each class of customers' rates will increase or decrease, (5) the date the proposed adjusted rates will be in effect, (6) a sworn statement which attests to the accuracy of the figures and calculations upon which any proposed adjustment of rates is based and which states that the proposed adjustment will not cause the company to exceed the return on equity authorized in the company's most recent proceeding for an amendment of rates pursuant to section 16-19, and (7) a copy of the notice the company provided pursuant to subsection (c) of this section to all affected customers advising them of the proposed adjustment of rates. The authority may hold a public hearing not more than forty-five days after receiving an application for an adjustment of rates to verify the accuracy of the figures and calculations submitted to the authority by the company and to determine that such an adjustment shall not cause the company to exceed the return on equity authorized in the company's most recent proceeding for an amendment of rates pursuant to section 16-19. The authority shall review the complete application to determine whether the proposed adjustment of rates reflects prudent and efficient management of the company's operations in accordance with the criteria set forth in section 16-19e. The authority shall issue a decision on an application for an adjustment of rates not more than ninety days after the filing of the complete application. If, within fifteen months after the filing of a company's annual audit report, as required by section 16-32, the authority finds that the company exceeded the return on equity authorized in the company's most recent proceeding for an amendment of rates pursuant to section 16-19 because of an adjustment of rates made pursuant to this section, the authority shall order the company to refund, with interest and on an equitable basis, the amount realized by the company in excess of its return on equity authorized in the company's most recent proceeding for an amendment of rates pursuant to section 16-19 to its rate-paying customers and to adjust its rates as determined by the authority to be necessary to prevent the company from further exceeding its authorized rate of return.
(c) Before a company applies for an adjustment of rates pursuant to subsection (a) of this section, the company shall notify each customer who would be affected by the proposed adjustment, by mail, that the company is applying for an adjustment of rates, the total amount of the proposed adjustment, the amount by which each class of customers' rates would increase or decrease and the date the proposed adjusted rates would go into effect.
(P.A. 93-213; P.A. 96-153, S. 2; P.A. 98-28, S. 96, 117; P.A. 11-80, S. 1; P.A. 14-134, S. 66.)
History: P.A. 96-153 amended Subsec. (a) to add Subdivs. (5) and (6) re fees for mandated monitoring and inflation-caused expenses, to delete Subpara. (B) re one-year time limit for rate adjustments and to reletter Subpara. (C) accordingly, amended Subsec. (b) to add Subdiv. (7) requiring that copy of notice be sent to affected customers, to make technical changes and to increase time periods for department to hold public hearing and issue a decision, amended Subsec. (c) re notice to customers and deleted Subsec. (d) re exemption of requirements to class “A” water companies and filing of report by the department; P.A. 98-28 amended Subsec. (a) by adding electric distribution companies and electric suppliers, effective July 1, 1998; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 14-134 amended Subsec. (a) to delete reference to electric company, effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32d. Reserved for future use.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32e. Emergency plans to be filed by public service companies, telecommunications companies, voice over Internet protocol service providers and municipal utilities. Hearings. Revisions. Staffing of electric distribution companies' emergency operations centers. (a) As used in this section, “emergency” means any (1) hurricane, tornado, storm, flood, high water, wind-driven water, tidal wave, tsunami, earthquake, volcanic eruption, landslide, mudslide, snowstorm, drought or fire explosion, or (2) attack or series of attacks by an enemy of the United States causing, or which may cause, substantial damage or injury to civilian property or persons in the United States in any manner by sabotage or by the use of bombs, shellfire or atomic, radiological, chemical, bacteriological or biological means or other weapons or processes.
(b) Not later than July 1, 2012, and every two years thereafter, each public service company, as defined in section 16-1, each telecommunications company, as defined in section 16-1, that installs, maintains, operates or controls poles, wires, conduits or other fixtures under or over any public highway for the provision of telecommunications service authorized by section 16-247c, each voice over Internet protocol service provider, as defined in section 28-30b, and each municipal utility furnishing electric, gas or water service shall file with the Public Utilities Regulatory Authority, the Department of Emergency Services and Public Protection and each municipality located within the service area of the public service company, telecommunications company, voice over Internet protocol service provider or municipal utility an updated plan for restoring service which is interrupted as a result of an emergency, except no such plan shall be required of a public service company or municipal utility that submits a water supply plan pursuant to section 25-32d. Plans filed by public service companies and municipal utilities furnishing water shall be prepared in accordance with the memorandum of understanding entered into pursuant to section 4-67e. Each such plan for restoring service which is interrupted as a result of an emergency shall include measures for (1) communication and coordination with state officials, municipalities and other public service companies and telecommunications companies during a major disaster, as defined in section 28-1, or an emergency; and (2) participation in training exercises as directed by the Commissioner of Emergency Services and Public Protection. Each such plan shall include such company's, provider's or municipal utility's response for service outages affecting more than ten per cent, thirty per cent, fifty per cent and seventy per cent of such company's, provider's or municipal utility's customers. On or before September 1, 2012, and biannually thereafter, the authority shall submit a report, in accordance with section 11-4a, to the joint standing committee of the General Assembly having cognizance of matters relating to public utilities summarizing such plans. Not later than September 15, 2012, and every two years thereafter, the Public Utilities Regulatory Authority may conduct public hearings on such plans and, in consultation with the Department of Emergency Services and Public Protection, the Department of Public Health and the joint standing committee of the General Assembly having cognizance of matters relating to public utilities, revise such plans to the extent necessary to provide properly for the public convenience, necessity and welfare. If the Public Utilities Regulatory Authority revises the emergency plan of a public service company, telecommunications company, voice over Internet protocol service provider or municipal utility, such company, provider or municipal utility shall file a copy of the revised plan with each municipality located within the service area of the company, provider or municipal utility. Any information provided in any such plan shall be considered confidential, not subject to disclosure under the Freedom of Information Act, as defined in section 1-200, and any such information shall not be transmitted to any person except as needed to comply with this section.
(c) At the discretion of the Commissioner of Emergency Services and Public Protection or after an emergency or major disaster is declared in the state by the Governor under the laws of this state or by the President of the United States under federal law, each telephone company, certified telecommunications provider, holder of a certificate of video franchise authority or holder of a certificate of cable franchise authority, as those terms are defined in section 16-1, with more than twenty-five thousand subscribers, shall provide a representative to staff the emergency operations center of an affected electric distribution company, as defined in section 16-1, as needed to ensure communication and coordination during emergency response and restoration efforts.
(P.A. 86-204, S. 1, 2; P.A. 88-135, S. 2; P.A. 89-291, S. 4, 8; 89-327, S. 3, 7; P.A. 93-381, S. 9, 39; P.A. 95-257, S. 12, 21, 58; P.A. 96-46, S. 1; P.A. 97-92; P.A. 04-219, S. 6; P.A. 11-51, S. 134; 11-80, S. 1; P.A. 12-148, S. 6.)
History: P.A. 88-135 substituted office of “emergency management” for office of “civil preparedness” in Subsec. (b); P.A. 89-291 changed date of initial report and hearing in Subsec. (b); P.A. 89-327 amended Subsec. (b) to require that emergency plans be prepared in accordance with the memorandum of understanding; P.A. 93-381 replaced department of health services with department of public health and addiction services, effective July 1, 1993; P.A. 95-257 replaced Commissioner and Department of Public Health and Addiction Services with Commissioner and Department of Public Health, effective July 1, 1995; P.A. 96-46 amended Subsec. (b) to add telecommunications companies to the list of utilities that must file emergency plans, to change filing requirement from biennially to every five years and to make the provision re public hearings held by the department discretionary rather than mandatory; P.A. 97-92 amended Subsec. (b) to add an exception from filing requirement for a public service company or municipal utility that submits a water supply plan pursuant to Sec. 25-32d; P.A. 04-219 amended Subsec. (b) to substitute Department of Emergency Management and Homeland Security for Office of Emergency Management, effective January 1, 2005; pursuant to P.A. 11-51, “Department of Emergency Management and Homeland Security” was changed editorially by the Revisors to “Department of Emergency Services and Public Protection” in Subsec. (b), effective July 1, 2011; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority” in Subsec. (b), effective July 1, 2011; P.A. 12-148 amended Subsec. (b) to require voice over Internet protocol service providers to file emergency plans, to change filing requirement from every 5 years to every 2 years, to add provisions re contents of emergency plans, to require authority to submit biennial reports to General Assembly re emergency plans, to allow biennial public hearings and to make information in emergency plans confidential and not subject to disclosure under the Freedom of Information Act, added Subsec. (c) re emergency operations center staffing and made technical changes, effective June 15, 2012.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32f. Gas company supply and demand forecast reports. On or before October first of each even-numbered year, a gas company, as defined in section 16-1, shall furnish a report to the Public Utilities Regulatory Authority containing a five-year forecast of loads and resources. The report shall describe the facilities and supply sources that, in the judgment of such gas company, will be required to meet gas demands during the forecast period. The report shall be made available to the public and shall be furnished to the chief executive officer of each municipality in the service area of such gas company, the regional council of governments which encompasses each such municipality, the Attorney General, the president pro tempore of the Senate, the speaker of the House of Representatives, the joint standing committee of the General Assembly having cognizance of matters relating to public utilities, any other member of the General Assembly making a request to the authority for the report and such other state and municipal entities as the authority may designate by regulation. The report shall include: (1) A tabulation of estimated peak loads and resources for each year; (2) data on gas use and peak loads for the five preceding calendar years; (3) a list of present and projected gas supply sources; (4) specific measures to control load growth and promote conservation; and (5) such other information as the authority may require by regulation. A full description of the methodology used to arrive at the forecast of loads and resources shall also be furnished to the authority. The authority shall hold a public hearing on such reports upon the request of any person. On or before August first of each odd-numbered year, the authority may request a gas company to furnish to the authority an updated report. A gas company shall furnish any such updated report not later than sixty days following the request of the authority.
(P.A. 87-32; P.A. 89-50; 89-291, S. 5, 8; P.A. 94-1; June Sp. Sess. P.A. 98-1, S. 6, 121; P.A. 02-16, S. 1; June Sp. Sess. P.A. 05-1, S. 22; P.A. 06-196, S. 230; P.A. 07-242, S. 115; June Sp. Sess. P.A. 07-1, S. 130; P.A. 11-6, S. 125; 11-80, S. 1; P.A. 13-247, S. 312; 13-298, S. 15.)
History: P.A. 89-50 added new Subsec. (b) re submission of gas conservation plans; P.A. 89-291 changed submission date of 10-year forecast report; P.A. 94-1 changed annual reports to biennial reports and added provisions re updated reports and plans and supply and load management; June Sp. Sess. P.A. 98-1 made a technical change in Subsec. (a), effective June 24, 1998; P.A. 02-16 changed the forecast period from 10 years to 5 years throughout, amended Subsec. (a) to add “upon the request of any person” and made a technical change in Subsec. (b); June Sp. Sess. P.A. 05-1 amended Subsec. (b) to make technical changes, to delete provisions re the content of the plan and substitute broader language re compliance with section, to delete language re public hearings and submission of updated plans and substitute language re an uncontested proceeding, added Subsec. (c) re assistance from and review by the Energy Conservation Management Board, cost-effectiveness testing, contents of the programs included in the plan, source of funding, and authority for expenditures, and added Subsec. (d) re the lack of requirement for conservation charge, effective July 1, 2005; P.A. 06-196 made a technical change in Subsec. (c)(2), effective June 7, 2006; P.A. 07-242 amended Subsec. (b) to provide that tax imposed by Sec. 12-264 shall fund the plan, that services shall be available to all gas company customers, and that each company shall apply to board for expense reimbursement, made a technical change in Subsec. (c)(1) and deleted former Subsec. (d) re conservation charge, effective July 1, 2007; June Sp. Sess. P.A. 07-1 amended Subsec. (b) to specify that Comptroller shall deposit excess revenue before accounts for the General Fund have been closed for each fiscal year, effective July 1, 2007; P.A. 11-6 amended Subsec. (b) to remove provision re funding of plan by revenue from tax imposed by Sec. 12-264, effective May 4, 2011; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; pursuant to P.A. 13-247, “regional planning agency” was changed editorially by the Revisors to “regional council of governments”, effective January 1, 2015; P.A. 13-298 deleted Subsec. (a) designator and former Subsecs. (b) and (c) re gas conservation plan and programs contained in the plan, effective July 8, 2013.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32g. Electric wire maintenance plans. Regulations. Not later than January 1, 2008, and annually thereafter, each electric distribution company shall submit to the Public Utilities Regulatory Authority a plan for the maintenance of poles, wires, conduits or other fixtures, along public highways or streets for the transmission or distribution of electric current, owned, operated, managed or controlled by such company, in such format as the authority shall prescribe. Such plan shall include a summary of appropriate staffing levels necessary for the maintenance of said fixtures and a program for the trimming of tree branches and limbs located in close proximity to overhead electric wires where such branches and limbs may cause damage to such electric wires. The authority shall review each plan and may issue such orders as may be necessary to ensure compliance with this section. The authority may require each electric distribution company to submit an updated plan at such time and containing such information as the authority may prescribe. The authority shall adopt regulations, in accordance with the provisions of chapter 54, to carry out the provisions of this section.
(P.A. 87-68, S. 1, 2; P.A. 98-28, S. 97, 117; P.A. 07-242, S. 6; P.A. 11-80, S. 1; P.A. 14-134, S. 67.)
History: P.A. 98-28 added electric distribution companies and made technical changes, effective July 1, 1998; P.A. 07-242 changed “January 1, 1988,” to “January 1, 2008, and annually thereafter” and required summary of appropriate staffing levels in plan; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 14-134 deleted references to electric company, effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32h. Performance standards for electric distribution companies and gas companies in emergencies. Emergency response report. (a) As used in this section, “utility” means any electric distribution company or gas company, as those terms are defined in section 16-1, and “emergency” has the same meaning as provided in section 16-32e.
(b) The Public Utilities Regulatory Authority shall initiate a docket to establish industry specific standards for acceptable performance by each utility in an emergency to protect public health and safety, to ensure the reliability of such utility's services to prevent and minimize the number of service outages or disruptions and to reduce the duration of such outages and disruptions, to facilitate restoration of such services after such outages or disruptions, and to identify the most cost-effective level of tree trimming and system hardening, including undergrounding, necessary to achieve the maximum reliability of the system and to minimize service outages. On or before November 1, 2012, the authority shall submit a report identifying the standards established by the authority pursuant to such docket and any recommendations concerning legislative changes necessary to implement such standards to the joint standing committee of the General Assembly having cognizance of matters relating to energy in accordance with the provisions of section 11-4a. The authority shall allow, in a future rate proceeding, each utility to recover the reasonable costs incurred by such utility to maintain or improve the resiliency of such utility's infrastructure necessary to meet the standards established pursuant to this section pursuant to a plan first approved by the authority.
(c) The authority shall, in the docket initiated pursuant to subsection (b) of this section, review:
(1) Each such utility's current practices concerning service restoration after an emergency. Such review shall include, but not be limited to, an analysis of each such utility's (A) estimates concerning potential damage and service outages prior to any emergency, (B) damage and service outage assessments after any emergency, (C) restoration management after any emergency, including access to alternate restoration resources via regional and reciprocal aid contracts, (D) planning for at-risk and vulnerable customers, (E) policies concerning communication with state and local officials and customers, including individual customer restoration estimates and the timeliness and usefulness of such estimates, and (F) need for mutual assistance during any emergency;
(2) The adequacy of each such utility's infrastructure, facilities and equipment, which shall include, but not be limited to, an analysis of (A) whether such utility is following standard industry practice concerning operation and maintenance of such infrastructure, facilities and equipment, and (B) whether such utility had access to adequate replacement equipment for such infrastructure, facilities and equipment during the course of such emergency;
(3) Coordination efforts between each electric distribution company and any telecommunications company, community antenna television company, holder of a certificate of cable franchise authority or certified competitive video service provider, as those terms are defined in section 16-1, including coordinated planning before any emergency;
(4) Tree trimming policies of each electric distribution company and shall determine (A) the amount spent by each electric distribution company for tree trimming in each year since such company's most recent rate case, (B) each such company's system average interruption duration index, as described in section 16-245y, caused by falling trees and limbs, (C) the impact of expanding the area adjacent to distribution lines for tree trimming, including an analysis of the benefits and the costs of such expansion to ratepayers and the likelihood that such expansion would decrease damage to infrastructure, facilities and equipment used to distribute electricity and decrease service outage frequency or duration, (D) the percentage of service outages during Tropical Storm Irene and the October, 2011 snowstorm caused by trees and limbs outside the current trim area based on an analysis of the quantity and effectiveness of prior tree trimming, and (E) the standards appropriate for road-side tree care in the state, vegetation management practices in utility rights-of-way, right tree-right place standards, and any other tree maintenance standard recommended by the State Vegetation Management Task Force established by the Department of Energy and Environmental Protection;
(5) The use of mediation in resolving objections to proposed activities relating to vegetation management, as defined in section 16-234, and the circumstances in which stump grinding may be performed within the utility protection zone, as defined in section 16-234, provided, the utility, as defined in section 16-234, shall recover all reasonable incremental costs incurred by such utility pursuant to the directives of the authority, as established pursuant to this subdivision, through the nonbypassable federally mandated congestion charge, as defined in subsection (a) of section 16-1; and
(6) Any other policy, practice or information that the authority determines is relevant to a review of each such utility's ability to ensure the reliability of such utility's services in an emergency and to prevent, minimize and restore any long-term service outages or disruptions caused by such emergency.
(d) The authority shall, in the docket initiated pursuant to subsection (b) of this section, establish standards for acceptable performance in an emergency in which more than ten per cent of any utility's customers are without service for more than forty-eight consecutive hours. The standards established by the authority shall include, but not be limited to, provisions for:
(1) Minimum staffing and equipment levels for each utility, based on the number of customers served by such utility and the nature of the infrastructure deployed to serve such utility's customers, in such emergency;
(2) Targets for recovery and restoration of service in emergencies for service outages affecting more than ten per cent, thirty per cent, fifty per cent and seventy per cent of such utility's customers;
(3) A communication plan between each utility and its customers, including, but not limited to, communication during other than normal business hours;
(4) Safety standards for employees of each utility, mutual aid crews and private contractors;
(5) Filing mutual aid agreements by utilities and assessing each utility's ability to rely on mutual storm restoration assistance from other utilities in the region;
(6) Communication and coordination protocols defining interactions between each utility and the appropriate state, municipal or emergency operations center official concerning emergency preparation, road clearing and the establishment of restoration priorities;
(7) Tree trimming, cutting and removal by each electric distribution company to reduce service outages caused by trees and limbs;
(8) Communication and coordination, in consultation with the Department of Emergency Services and Public Protection, between each utility and the public including, but not limited to, standards concerning the use of any emergency notification system to notify the public of service restoration estimates and any dangerous conditions;
(9) Timely notification by each utility to any relevant state or municipal agency or official including, but not limited to, any public safety agency or official, of any emergency and standards for coordination and communication between such utility and such agency or official;
(10) Communication and coordination between any appropriate electric distribution, gas, telephone or telecommunications company or voice over Internet protocol service provider, as defined in section 28-30b; and
(11) The operation of the call center of each utility.
(e) The authority shall establish as it deems fit any other standards for acceptable performance by any utility to ensure the reliability of such utility's services in any emergency, to prevent and minimize any service outages or disruptions lasting more than forty-eight consecutive hours and affecting more than ten per cent of any utility's customers and to facilitate restoration of such services after such outages or disruptions.
(f) Any mutual aid agreement filed with the authority pursuant to this section shall not be considered a public record or file subject to disclosure under the Freedom of Information Act, as defined in section 1-200.
(g) The authority may initiate any additional docket to establish standards for acceptable performance by each utility in an emergency, in accordance with this section, upon determination by the authority that the changed circumstances of any utility necessitates such docket.
(h) Not later than April 15, 2013, and annually thereafter, each utility shall provide an emergency response report to the Public Utilities Regulatory Authority. Such report shall include information and analysis concerning such utility's ability during the preceding year to meet the emergency preparedness and response standards established by the authority pursuant to this section. In addition to the annual report required in this subsection, the authority may require any utility to submit a supplemental emergency response report after any storm, emergency or event causing significant service outages.
(P.A. 12-148, S. 3; P.A. 14-134, S. 68; 14-151, S. 1.)
History: P.A. 12-148 effective June 15, 2012; P.A. 14-134 amended Subsec. (d)(7) by deleting reference to electric company, effective June 6, 2014; P.A. 14-151 amended Subsec. (c) by adding new Subdiv. (5) re use of mediation to resolve objections re vegetation management and redesignating existing Subdiv. (5) as Subdiv. (6), effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32i. Performance review of electric distribution companies and gas companies after emergencies. Hearing. Penalty. The Public Utilities Regulatory Authority shall review the performance of each electric distribution company and gas company, as those terms are defined in section 16-1, after any emergency, as defined in section 16-32e, (1) in which more than ten per cent of any such company's customers were without service for more than forty-eight consecutive hours, or (2) at the authority's discretion. The authority, upon a finding that any such company failed to comply with any standard of acceptable performance in emergency preparation or restoration of service in an emergency, adopted pursuant to section 16-32h, or with any order of the authority, shall make orders, after a hearing that is conducted as a contested case in accordance with chapter 54, to enforce such standards or orders and may levy civil penalties against such company, pursuant to section 16-41, not to exceed a total of four per cent of such electric distribution or gas company's annual distribution revenue, for noncompliance in any such emergency. In determining the amount of any penalty, the authority shall consider whether such company received approval and reasonable funding allowances, as determined by the authority, from the authority to meet infrastructure resiliency efforts to improve such company's performance. Any such penalty shall be assessed in the form of credits to the accounts of ratepayers of such electric distribution or gas company. Any such penalty shall not be included as an operating expense of such company for purposes of ratemaking.
(P.A. 12-148, S. 4; Sept. Sp. Sess. P.A. 20-5, S. 9.)
History: P.A. 12-148 effective June 15, 2012; Sept. Sp. Sess. P.A. 20-5 increased potential civil penalty to 4 per cent of annual distribution revenue and replaced “a credit to” with “credits to the accounts of”, effective October 2, 2020.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32j. Procedures for expedited road clearing after emergencies. On or before January 1, 2013, the Department of Energy and Environmental Protection, in coordination and consultation with each public service company, as defined in section 16-1, the Department of Transportation, the Department of Emergency Services and Public Protection and an association of municipalities, shall develop procedures to expedite the process of road clearing for public safety personnel after an emergency, as defined in section 16-32e.
(P.A. 12-148, S. 11.)
History: P.A. 12-148 effective June 15, 2012.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32k. Vegetation management practices review. Report. On and after June 6, 2014, the Department of Energy and Environmental Protection shall review the vegetation management practices of each electric distribution company. Not later than one year after the final decision has been issued by the Public Utilities Regulatory Authority for the docket described in subsection (c) of section 16-32h, and every two years thereafter, the authority shall submit a report, in accordance with the provisions of section 11-4a, to the joint standing committee of the General Assembly having cognizance of matters relating to energy. Such report shall include a review of the vegetation management practices of each electric distribution company.
(P.A. 14-151, S. 2.)
History: P.A. 14-151 effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32l. Residential customer credits for distribution-system service outage. Recovery of costs. Waiver of requirements. (a) For the purposes of this section, “emergency” has the same meaning as provided in subdivision (1) of subsection (a) of section 16-32e and “electric distribution company” has the same meaning as provided in section 16-1.
(b) Notwithstanding any other provision of the general statutes, on and after July 1, 2021, each electric distribution company shall provide to residential customers of such company a credit of twenty-five dollars, on the balance of such customer's account, for each day of distribution-system service outage that occurs for such customers for more than ninety-six consecutive hours after the occurrence of an emergency.
(c) Any costs incurred by an electric distribution company pursuant to this section shall not be recoverable.
(d) Not later than fourteen calendar days after the occurrence of an emergency, an electric distribution company may petition the authority for a waiver of the requirements of this section. Any petition for a waiver made under this subsection shall include the severity of the emergency, employee safety issues and conditions on the ground, and shall be conducted as a contested case proceeding. The burden of proving that such waiver is reasonable and warranted shall be on the electric distribution company. In determining whether to grant such waiver, the authority shall consider whether the electric distribution company received approval and reasonable funding allowances, as determined by the authority, to meet infrastructure resiliency efforts to improve such company's performance.
(e) On or before January 1, 2021, the Public Utilities Regulatory Authority shall initiate a proceeding to consider the implementation of the residential customer credit and waiver provisions of this section and establish circumstances, standards and methodologies applicable to each electric distribution company and necessary to implement the provisions of this section, including any modifications to the ninety-six-consecutive-hour standard in subsection (b) of this section. The authority shall issue a final decision in such proceeding on or before July 1, 2021.
(Sept. Sp. Sess. P.A. 20-5, S. 10.)
History: Sept. Sp. Sess. P.A. 20-5 effective October 2, 2020.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32m. Residential customer compensation for expiration of medicine and food due to distribution-system service outage. Recovery of costs. Waiver of requirements. (a) For the purposes of this section, “emergency” has the same meaning as provided in subdivision (1) of subsection (a) of section 16-32e and “electric distribution company” has the same meaning as provided in section 16-1.
(b) On and after July 1, 2021, each electric distribution company shall provide to each residential customer compensation in an amount of two hundred fifty dollars, in the aggregate, for any medication and food that expires or spoils due to a distribution-system service outage that lasts more than ninety-six consecutive hours in duration after the occurrence of an emergency.
(c) Any costs incurred by an electric distribution company pursuant to this section shall not be recoverable.
(d) Not later than fourteen calendar days after the occurrence of an emergency, an electric distribution company may petition the authority for a waiver of the requirements of this section. Any petition for a waiver made under this subsection shall include the severity of the emergency, employee safety issues and conditions on the ground, and shall be conducted as a contested case proceeding. The burden of proving that such waiver is reasonable and warranted shall be on the electric distribution company. In determining whether to grant such waiver, the authority shall consider whether the electric distribution company received approval and reasonable funding allowances, as determined by the authority, to meet infrastructure resiliency efforts to improve such company's performance.
(e) On or before January 1, 2021, the Public Utilities Regulatory Authority shall initiate a proceeding to consider the implementation of the compensation reimbursement and waiver provisions of this section and establish circumstances, standards and methodologies applicable to each electric distribution company and necessary to implement the provisions of this section, including any modifications to the ninety-six-consecutive-hour standard in subsection (b) of this section. The authority shall issue a final decision in such proceeding on or before July 1, 2021.
(Sept. Sp. Sess. P.A. 20-5, S. 11.)
History: Sept. Sp. Sess. P.A. 20-5 effective October 2, 2020.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-32n. Cost-benefit analysis concerning resources expended and existing staffing levels during storm events. Minimum staffing levels and acceptable performance standards for electric distribution companies. Penalties. (a) As used in this section, “electric distribution company” has the same meaning as provided in section 16-1.
(b) Not later than January 1, 2021, each electric distribution company shall submit to the joint standing committee of the General Assembly having cognizance of matters relating to energy, in accordance with the provisions of section 11-4a, and the Public Utilities Regulatory Authority the following:
(1) A cost-benefit analysis identifying the resources expended in response to the last five storm events classified as a level three, four or five. Such analysis shall include a review of the number of line crew workers and shall distinguish between line crew workers (A) directly employed by the electric distribution company and working full time within the state, (B) directly employed by the electric distribution company working primarily in another state, and (C) hired as contractors or subcontractors.
(2) An analysis of any such company's (A) estimates concerning potential damage and service outages prior to the last five storm events classified as a level three, four or five, (B) damage and service outage assessments after the last five storm events classified as a level three, four or five, (C) restoration management after the last five storm events classified as a level three, four or five, including access to alternate restoration resources via regional and reciprocal aid contracts, (D) planning for at-risk and vulnerable customers, (E) communication policies with state and local officials and customers, including individual customer restoration estimates and the accuracy of such estimates, (F) infrastructure, facilities and equipment, which shall include, but not be limited to, an examination of (i) whether such infrastructure, facilities and equipment are in good repair and capable of meeting operational standards, (ii) whether such company is following standard industry practice concerning operation and maintenance of such infrastructure, facilities and equipment, (iii) the age and condition of such infrastructure, facilities and equipment, (iv) whether maintenance of such infrastructure, facilities and equipment has been delayed, and (v) whether such company had access to adequate replacement equipment for such infrastructure, facilities and equipment during the course of the last five storm events classified as a level three, four or five, and (G) compliance with any emergency response standards adopted by the authority.
(c) Not later than January 1, 2021, the authority shall initiate a docket, or incorporate into an existing docket, to review the report provided by each electric distribution company pursuant to subsection (b) of this section. The authority shall submit the final decision of such docket, in accordance with the provisions of section 11-4a, to the joint standing committee of the General Assembly having cognizance of matters relating to energy.
(d) After issuing its final decision in the docket initiated pursuant to subsection (c) of this section, the authority shall establish standards for minimum staffing levels for any electric distribution company for outage planning and restoration personnel, including linemen, technicians and system engineers, tree trimming crews and personnel responsible for directing operations and communicating with state, municipal and regional officials. Such staffing standards may reflect different staffing levels based on the severity of any emergency.
(e) The authority may establish as it deems fit any other standards for acceptable performance by any electric distribution company to ensure the reliability of such company's services in any emergency and to prevent, minimize and restore any long-term service outages or disruptions caused by such emergency.
(f) The authority, upon a finding that any electric distribution company failed to comply with any standard of acceptable performance adopted pursuant to this section or any order of the authority, shall make orders to enforce such standards and may levy civil penalties against such company, pursuant to section 16-41. Any such penalty shall not be included as an operating expense of such company for purposes of ratemaking.
(Sept. Sp. Sess. P.A. 20-5, S. 12.)
History: Sept. Sp. Sess. P.A. 20-5 effective October 2, 2020.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-33. Obstructing authority; false entries and returns to; penalty. Any person who wilfully makes any false return or report to the Public Utilities Regulatory Authority, or to any member thereof, or to any agent or any employee acting therefor, or who testifies falsely to any material fact in any matter wherein an oath or affirmation is required or authorized, or who makes any false entry or memorandum upon any account, book, paper, record, report or statement of any company, or who wilfully destroys, mutilates, alters or by any other means or device falsifies or destroys the record of any such account, book, paper, record, report or statement, with the intent to mislead or deceive the authority, or any member thereof, or any agent or employee acting therefor, or who wilfully obstructs or hinders the authority, or any of its members, agents or employees, in the making of any examination of the accounts, affairs or condition of any company, and any person who, with like intent, aids or abets another in any of the acts hereinbefore set forth, shall be guilty of a class D felony.
(1949 Rev., S. 5423, 8708; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 71, 348; P.A. 11-80, S. 1; P.A. 13-258, S. 62.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 13-258 changed penalty from fine of not more than $5,000 or imprisonment of not more than 5 years to a class D felony.
Cited. 159 C. 556.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-34. Annual reports to Governor. Section 16-34 is repealed.
(1949 Rev., S. 5424; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 4, 40, 345, 348; P.A. 81-348, S. 3.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-34a. Annual report re lost and unaccounted for gas. Docket to investigate. (a) Not later than July 1, 2015, and annually thereafter, the Public Utilities Regulatory Authority shall submit a report, in accordance with the provisions of section 11-4a, to the joint standing committee of the General Assembly having cognizance of matters relating to energy. Such report shall include (1) a description of the reasons for each gas company's percentage of lost and unaccounted for gas, (2) recommendations for each gas company's gas leak reduction strategy, (3) a description of each gas company's current gas leak monitoring system program, and (4) the number of leaks and causes of such leaks throughout the entire gas distribution system in the state and any other information the authority determines to be relevant.
(b) The authority shall initiate a docket to investigate the lost and unaccounted for gas of a gas company if the percentage of lost and unaccounted for gas of such gas company in any calendar year exceeds a total of three per cent. In such docket, a gas company shall report (1) leak detection and monitoring procedures, (2) emissions reduction strategies in addition to leak repair, and (3) any additional requirements the authority determines to be relevant. In such docket, the authority shall establish a cost mechanism to comply with long-term emissions reductions required by section 22a-200a and to incentivize a gas company to (A) reduce lost and unaccounted for gas, including the number of leaks throughout the entire gas distribution system in the state, (B) replace aging infrastructure, and (C) comply with any additional requirements the authority determines to be relevant. Such cost mechanism may be incorporated in the purchased gas adjustment clause pursuant to section 16-19b.
(P.A. 14-152, S. 1.)
History: P.A. 14-152 effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-35. Appeals to Superior Court. Uncontested proceedings re acquiring electricity products or services. (a) Any person, including but not limited to a company, town, city, borough or corporation aggrieved by any order, authorization or decision of the Public Utilities Regulatory Authority, except an order, authorization or decision of the authority approving the taking of land, in any matter to which such person was or ought to have been made a party or intervenor, may appeal therefrom in accordance with the provisions of section 4-183. Such person so appealing shall give bond to the state, with sufficient surety, for the benefit of the adverse party, in such sum as the authority fixes, to pay all costs in case such person fails to sustain such appeal. No municipality or political subdivision shall be determined not to be aggrieved solely because there are other persons who are similarly affected by the order, authorization or decision of the authority.
(b) Any person who may appeal an order, authorization or decision of the authority under subsection (a) of this section who was an intervenor or, after timely application, was denied intervenor status to the authority proceeding, shall be limited to raise on appeal only those issues that (1) such person addressed during the proceeding or were addressed in the final decision, or (2) such person raised in his request for intervenor status if he was denied intervenor status.
(c) Notwithstanding any provision of this title and title 16a, proceedings in which the Public Utilities Regulatory Authority conducts a request for proposals or any other procurement process for the purpose of acquiring electricity products or services for the benefit of ratepayers shall be uncontested.
(1949 Rev., S. 5425; 1971, P.A. 870, S. 42; P.A. 75-486, S. 15, 69; P.A. 76-436, S. 357, 681; P.A. 77-603, S. 41, 125; 77-614, S. 162, 610; P.A. 80-482, S. 4, 40, 72, 345, 348; P.A. 96-247, S. 1; P.A. 11-80, S. 1; P.A. 13-298, S. 12.)
History: 1971 act replaced superior court with court of common pleas, effective September 1, 1971, except that courts with cases pending retain jurisdiction unless pending matters deemed transferable; P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 76-436 replaced court of common pleas with superior court, effective July 1, 1978; P.A. 77-603 replaced previous appeal provision with statement that appeals are to be made in accordance with Sec. 4-183; P.A. 77-614 replaced the authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division of public utility control an independent department and deleted reference to abolished department of business regulation; P.A. 96-247 lettered existing section as Subsec. (a), made technical changes and added provision prohibiting a determination that a municipality or political subdivision is not aggrieved solely because other persons are similarly affected and added Subsec. (b) re issues that may be raised on appeal; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 13-298 added Subsec. (c) re uncontested proceedings for acquiring electricity products or services, effective July 8, 2013.
Superior Court on appeal has the same discretionary powers as commissioners; 57 C. 172, but see 78 C. 301; 97 C. 459. Where it does not appear that proceeding was under special act making commissioners' decision final, appeal was held valid under section. 70 C. 328. Legality of condition imposed by municipality in approving layout proper question for appeal. 74 C. 102. So question as to powers of commissioners. 78 C. 226. Provision for notice is directory. Id., 301. Nature of appeal. Id.; 80 C. 638; 86 C. 36; 88 C. 471; 89 C. 537; 91 C. 134; Id., 698; 97 C. 459; 99 C. 285. One to whom notice of hearing is not required to be given may appear before commissioners and appeal. 82 C. 135. Court does not try case de novo; appellant must show he is aggrieved by an illegal or unauthorized act. 86 C. 36, but see 99 C. 285. Appeal is confined to judicial or quasi-judicial questions. 97 C. 459. Appeal lies in condemnation matter as well under special charter as general law. 81 C. 18. Party whose interests are affected may appear before commissioners and appeal from their decision. 82 C. 135; 84 C. 34. Way in which party is aggrieved need not be stated. Id., 33. Unnecessary injury to abutting owners in construction of road proper ground of appeal. Id., 46. Questions open on appeal from order for relocation of tracks in highway; unreasonable order is unlawful; reasonableness affected by cost of change compared with railroad's whole income. 95 C. 31, 32. Scope of review by Superior Court. 145 C. 243. Cited. 147 C. 229; 148 C. 336; 149 C. 481; 154 C. 674, 678; 158 C. 626; 159 C. 327; 161 C. 215; 162 C. 51; 165 C. 114. Federal criteria for establishing aggrievement had no relevance here. 165 C. 687. Cited. 166 C. 328; 168 C. 478; 170 C. 3. Right of appeal is purely statutory and is allowed only if conditions fixed by statute are met. 171 C. 387. Cited. 175 C. 30; 176 C. 191; 183 C. 128; 197 C. 320; 210 C. 349; 216 C. 627; 219 C. 51; 234 C. 624; 235 C. 334.
Cited. 37 CA 423. Sec. 4-183(a) places jurisdictional requirement of a final decision on appeals taken under this section. 64 CA 134.
Cited. 29 CS 152; 30 CS 149. Interim rate increase order by commission, with refund provision, not applicable and final order renders appeal moot; right of appeal is not constitutional, but statutory privilege requiring strict compliance with rules of law; not repealed by enactment of Ch. 54, but constitutes “other means of review, redress, relief, or trial de novo” referred to in Sec. 4-183(a). 31 CS 65. Cited. 33 CS 175; 38 CS 24; 40 CS 520; 42 CS 217.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Secs. 16-36 to 16-39. Venue. Procedure on appeal. Notice when parties are numerous. Supersedeas. Sections 16-36 to 16-39, inclusive, are repealed.
(1949 Rev., S. 5426–5429; 1971, P.A. 179, S. 6; 870, S. 43, 106; P.A. 76-436, S. 358, 359, 681; P.A. 77-603, S. 42, 125.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-40. Rights and duties of trustees and receivers. When any company is operated by a trustee or receiver, such trustee or receiver shall have all the powers and shall be subject to all the duties, obligations and penalties which such company would otherwise have or to which it would be subject under the provisions of this title, except so far as the same may be inconsistent with the rights, duties or obligations of such trustee or receiver as an officer of the court appointing him.
(1949 Rev., S. 5430.)
Cited. 162 C. 51.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-41. Imposition of civil penalties by authority. (a) Each (1) public service company and its officers, agents and employees, (2) electric supplier or person providing electric generation services without a license in violation of section 16-245, and its officers, agents and employees, (3) certified telecommunications provider or person providing telecommunications services without authorization pursuant to sections 16-247f to 16-247h, inclusive, and its officers, agents and employees, (4) person, public agency or public utility, as such terms are defined in section 16-345, subject to the requirements of chapter 293, (5) person subject to the registration requirements under section 16-258a, (6) cellular mobile telephone carrier, as described in section 16-250b, (7) Connecticut electric efficiency partner, as defined in section 16-243v, (8) company, as defined in section 16-49, (9) entity approved to submeter pursuant to section 16-19ff, and (10) person involved in the transportation of gas, as such terms are defined in section 16-280a, shall obey, observe and comply with all applicable provisions of this title and each applicable order made or applicable regulations adopted by the Public Utilities Regulatory Authority by virtue of this title as long as the same remains in force. Any such company, electric supplier, certified telecommunications provider, cellular mobile telephone carrier, Connecticut electric efficiency partner, entity approved to submeter, person, any officer, agent or employee thereof, public agency or public utility which the authority finds has failed to obey or comply with any such provision of this title, order or regulation shall be fined, ordered to pay restitution to customers or ordered to pay a combination of a fine and restitution by order of the authority in accordance with the penalty prescribed for the violated provision of this title or, if no penalty is prescribed, not more than ten thousand dollars for each offense, except that the penalty shall be a fine, restitution to customers or a combination of a fine and restitution of not more than forty thousand dollars for failure to comply with an order of the authority made in accordance with the provisions of section 16-19 or 16-247k or within thirty days of such order or within any specific time period for compliance specified in such order. The authority may direct a portion of any fine levied pursuant to this section to be paid to a nonprofit agency engaged in energy assistance programs named by the authority in its decision or notice of violation. Any such nonprofit agency that receives a portion of a fine pursuant to this subsection shall administer such funds as directed by the authority and submit an annual report to the authority, at the end of each fiscal year and in a form determined by the authority, that details the expenditure of such funding. No such nonprofit agency shall use more than ten per cent of such funding for administrative purposes. For the fiscal years ending June 30, 2023, and June 30, 2024, the authority shall direct not less than ninety-five per cent of any fine levied pursuant to this section to nonprofit agencies engaged in energy assistance programs. Each distinct violation of any such provision of this title, order or regulation shall be a separate offense and, in case of a continued violation, each day thereof shall be deemed a separate offense. Each such penalty and any interest charged pursuant to subsection (g) or (h) of section 16-49 shall be excluded from operating expenses for purposes of rate-making.
(b) Any regional water authority, any regional water district, any municipal gas or electric plant established under chapter 101, any municipal waterworks system established under chapter 102, or any other municipality or department thereof owning, leasing, operating or managing a plant for the supplying or furnishing of any public utility, which the Public Utilities Regulatory Authority finds has failed to comply with the procedures of section 16-29, shall be subject to a civil penalty of not more than five thousand dollars for any annual report which is not submitted or submitted late in violation of said section.
(c) If the authority has reason to believe that a violation has occurred for which a civil penalty is authorized by subsection (a) or (b) of this section, it shall notify the alleged violator by certified mail, return receipt requested, or by personal service. The notice shall include:
(1) A reference to the sections of the title, regulation or order involved;
(2) A short and plain statement of the matter asserted or charged;
(3) A statement of the prescribed civil penalty for the violation; and
(4) A statement of the person's right to a hearing.
(d) The person to whom the notice is addressed shall have twenty days from the date of receipt of the notice in which to deliver to the authority a written application for a hearing. If a hearing is requested, then, after a hearing and upon a finding that a violation has occurred, the authority may issue a final order assessing a civil penalty under this section which shall not be greater than the maximum penalty permitted by law. If a hearing is not requested, or if such a request is later withdrawn, then the notice shall, on the first day after the expiration of the twenty-day period or on the first day after the withdrawal of the request for hearing, whichever is later, become a final order of the authority and the matters asserted or charged in the notice shall be deemed admitted, unless the notice is modified by a consent order before it becomes a final order. A consent order shall be deemed a final order.
(e) All hearings under this section shall be conducted under sections 4-176e to 4-184, inclusive. The final order of the authority assessing a civil penalty shall be subject to appeal under section 4-183. No challenge to any final order of the authority assessing a civil penalty shall be allowed as to any issue which could have been raised by an appeal of an earlier order of the authority. Any civil penalty authorized by this section shall become due and payable (1) at the time of receipt of a final order in the case of a civil penalty assessed in such order after a hearing, (2) on the first day after the expiration of the period in which a hearing may be requested if no hearing is requested, or (3) on the first day after the withdrawal of a request for hearing.
(f) A civil penalty assessed in a final order of the authority under this section may be enforced in the same manner as a judgment of the Superior Court. The final order shall be delivered to the respondent by personal service or by certified mail, return receipt requested. After entry of such final order, the authority may file a transcript without the payment of costs, in the office of the clerk of the superior court in the judicial district in which the respondent resides, has a place of business, owns real property, or in which any real property which is the subject of the proceedings is located or, if the respondent is not a resident of the state of Connecticut, in the judicial district of Hartford. Upon the filing, the clerk shall docket the order in the same manner and with the same effect as a judgment entered in the superior court within the judicial district. Upon the docketing, the order may be enforced as a judgment of the court.
(1949 Rev., S. 5431; P.A. 75-486, S. 16, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 73, 348; P.A. 81-297, S. 1; Nov. Sp. Sess. P.A. 81-8, S. 2, 4; P.A. 85-552, S. 2, 8; P.A. 87-71, S. 1, 13; P.A. 88-230, S. 1, 12; 88-317, S. 63, 107; P.A. 90-98, S. 1, 2; 90-221, S. 7, 15; P.A. 93-142, S. 4, 7, 8; May 25 Sp. Sess. P.A. 94-1, S. 19, 130; P.A. 95-220, S. 4–6; P.A. 98-28, S. 35, 117; P.A. 99-105, S. 1, 4; 99-222, S. 13, 19; P.A. 00-91, S. 2; P.A. 05-241, S. 3; P.A. 06-196, S. 200; P.A. 07-242, S. 96; P.A. 11-80, S. 1; P.A. 13-298, S. 37; Sept. Sp. Sess. P.A. 20-5, S. 13; P.A. 22-20, S. 6; Nov. Sp. Sess. P.A. 22-1, S. 7.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority, added exception to allow $20,000 maximum fine for failure to comply within time limit with orders under Sec. 16-19 and excluded penalties and interest from consideration as operating expenses; P.A. 77-614 replaced the authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division of public utility control an independent department and deleted reference to abolished department of business regulation; P.A. 81-297 added Subsecs. (b) to (e) authorizing department to impose civil penalties and setting forth procedure for such penalties; Nov. Sp. Sess. P.A. 81-8 changed reference in Subsec. (a) from Subsec. (b) to Subsec. (g) of Sec. 16-49 to conform to amendment of said section in the same act; P.A. 85-552 made technical change in Subsec. (a), substituting reference to Sec. 16-49(f) for reference to Sec. 16-49(g); P.A. 87-71 amended Subsec. (a) to include persons, public agencies and public utilities subject to the requirements of chapter 293; P.A. 88-230 replaced “judicial district of Hartford-New Britain” with “judicial district of Hartford”, effective September 1, 1991; P.A. 88-317 amended reference to Secs. 4-177 to 4-184 in Subsec. (d) to include new sections added to Ch. 54, effective July 1, 1989, and applicable to all agency proceedings commencing on or after that date; P.A. 90-98 changed the effective date of P.A. 88-230 from September 1, 1991, to September 1, 1993; P.A. 90-221 inserted new Subsec. (b) establishing a penalty for regional water authorities or districts or municipalities which fail to file reports to the department and renumbered the remaining Subsecs; P.A. 93-142 changed the effective date of P.A. 88-230 from September 1, 1993, to September 1, 1996, effective June 14, 1993; May 25 Sp. Sess. P.A. 94-1 made technical change, effective July 1, 1994; P.A. 95-220 changed the effective date of P.A. 88-230 from September 1, 1996, to September 1, 1998, effective July 1, 1995; P.A. 98-28 amended Subsec. (a) by adding electric suppliers, persons providing electric generation services without a license and their officers, agents and employees, effective July 1, 1998; P.A. 99-105 amended Subsec. (a) to apply provisions to companies, as defined in Sec. 16-49, to add reference to Sec. 16-49(h) and to make technical changes, effective July 1, 1999; P.A. 99-222 amended Subsec. (a) by adding reference to certified telecommunications provider or person providing telecommunications services without authorization and its officers, agents and employees, by changing to $10,000 the maximum penalty for violating a provision of title 16 if no other penalty is prescribed, by changing to $40,000 the maximum penalty for failure to comply with order made in accordance with Sec. 16-19, by adding reference to Sec. 16-247k and by making technical changes, effective June 29, 1999 (Revisor's note: In codifying and merging the provisions of P.A. 99-105 and P.A. 99-222 the Revisors inserted “(3)” before and a comma after new language re certified telecommunications providers, deleted the word “each” from before the word “certified” and inserted the word “and” before the words “its officers, agents and employees”); P.A. 00-91 added new Subsec. (a)(5) re persons subject to registration requirements under Sec. 16-258a, redesignating former Subdiv. (5) as Subdiv. (6); P.A. 05-241 added new Subsec. (a)(6) re cellular mobile telephone carriers, redesignating existing Subdiv. (6) as Subdiv. (7) and adding reference to cellular mobile telephone carrier therein, effective July 8, 2005; P.A. 06-196 made technical changes in Subsec. (a), effective June 7, 2006; P.A. 07-242 amended Subsec. (a) to add provisions re Connecticut electric efficiency partners, effective July 1, 2007; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 13-298 amended Subsec. (a) to add Subdiv. (9) re entity approved to submeter and to make conforming changes, effective July 1, 2013; Sept. Sp. Sess. P.A. 20-5 amended Subsec. (a) to authorize restitution as a form of penalty and permit authority to direct portion of levied fine, effective October 2, 2020; P.A. 22-20 amended Subsec. (a) by adding new Subdiv. (10) re person involved in the transportation of gas as defined in Sec. 16-280a and amended Subsec. (d) by changing provision re civil penalties to the maximum penalty permitted by law; Nov. Sp. Sess. P.A. 22-1 amended Subsec. (a) to require nonprofit agencies receiving funds from fines to file annual expenditure reports and use no more than 10 per cent of the funds for administrative purposes, and, in fiscal years 2023 and 2024, to require the Public Utilities Regulatory Authority to direct at least 95 per cent of any fines to nonprofit agencies engaged in energy assistance programs, effective November 29, 2022.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-42. Not to affect labor contracts. Nothing in this title shall be construed to authorize the Public Utilities Regulatory Authority to interfere in any manner with contracts between public service companies and their employees.
(1949 Rev., S. 5432; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 74, 348; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-43. Merger or sale of public service companies. Issuance and approval of securities. Net proceeds from sale of water company land. Allocation of economic benefits of sale of water company land. (a) A public service company shall obtain the approval of the Public Utilities Regulatory Authority to directly or indirectly (1) merge, consolidate or make common stock with any other company, or (2) sell, lease, assign, mortgage, except by supplemental indenture in accord with the terms of a mortgage outstanding May 29, 1935, or otherwise dispose of any essential part of its franchise, plant, equipment or other property necessary or useful in the performance of its duty to the public. Any such disposition of an essential part of such other real property of a public service company shall be by public auction or other procedure for public sale, provided such auction or public sale shall be conducted upon notice of auction or sale published at least once each week for two weeks preceding the date of such auction or sale in a newspaper having a substantial circulation in the county in which such property is located. The public service company shall submit evidence to the authority of the notice given. On a showing of good cause by such company to use a means of disposal other than by public auction or other procedure for public sale, the authority may, on a finding of such good cause, authorize the use of an alternative sales process. No public auction or other procedure for public sale shall be required for the sale or other disposition of real property by a water company to the state, a municipality or land conservation organization if at least seventy per cent of the area of the real property sold or disposed of is to be used for open space or recreational purposes, as defined in subsection (f) of section 16-50d, and if the consideration received for such sale or disposition is not less than the appraised value of such property. A public service company other than a water company may sell, lease, assign, mortgage or otherwise dispose of improved real property with an appraised value of two hundred fifty thousand dollars or less or unimproved real property with an appraised value of fifty thousand dollars or less without such approval. The authority shall follow the procedures in section 16-50c for transactions involving unimproved land owned by a public service company other than a water company. A water company supplying water to more than five hundred consumers may sell, lease, assign, mortgage, or otherwise dispose of real property, other than public watershed or water supply lands, with an appraised value of fifty thousand dollars or less without such approval. The authority shall not accept an application to sell watershed or water supply lands until the Commissioner of Public Health issues a permit pursuant to section 25-32. The condemnation by a state department, institution or agency of any land owned by a public service company shall be subject to the provisions of this subsection. On February 1, 1996, and annually thereafter, each public service company shall submit a report to the Public Utilities Regulatory Authority of all real property sold, leased, assigned, mortgaged, or otherwise disposed of without the approval of said authority during the previous calendar year. Such report shall include for each transaction involving such property, without limitation, the appraised value of the real property, the actual value of the transaction and the accounting journal entry which recorded the transaction.
(b) A public service company shall obtain the approval of the Public Utilities Regulatory Authority to (1) issue any notes, bonds or other evidences of indebtedness or securities of any nature, (2) lend or borrow any moneys for a period of more than one year for any purpose other than paying the expenses, including taxes, of conducting its business or for the payment of dividends, or (3) amend any provision of an indenture or similar financial instrument if such amendment would affect the issuance or terms of any such notes, bonds or other evidences of indebtedness or securities. The authority shall approve or disapprove each such issue or amendment within sixty days after the filing of a written application for such approval unless the applicant agrees to an extension of time. If not disapproved within said sixty days or within such extension, such issue shall be deemed to be approved. The authority shall not require a company to issue its common stock under terms or conditions not required by the general statutes. The provisions of this subsection shall apply to a community antenna television company only with regard to any noncable communications services which the company may provide.
(c) Any managerial service contract made by a public service company shall be voidable on order of the authority, but may be enforced as between the parties unless disapproved.
(d) Any water company selling land that at any time has been in the water company's rate base shall use the net proceeds from the sale of such land for capital projects which improve or protect the water supply system or for the acquisition of a water supply source or land to protect a water supply source. In the case of a water company required to file a water supply plan pursuant to section 25-32d, the capital projects or acquisition shall be consistent with such plan.
(e) For the purposes of rate making, the authority shall use an accounting method for allocating the economic benefits of sales of land by a water company, as defined in section 16-1, that at any time has been in the water company's rate base that equitably allocates all of the economic benefits of any such sale between the ratepayers and the shareholders of the company based on the facts of each application for sale, except as follows:
(1) For any sale of land where the property is not more than ten acres and has not been taxed under the provisions of sections 12-107c to 12-107e, inclusive, during the previous ten years, the authority shall equitably allocate all of the economic benefits of any such sale between the ratepayers and the shareholders of the company. Any such allocation shall be based on the facts of each application for sale and the authority may allocate all of the economic benefits of any such sale to either the ratepayers or the shareholders.
(2) For a sale of class I or class II land to another water company for water supply purposes or to the state, a municipality, or a land conservation organization, which land has a permanent conservation easement in accordance with section 25-32, the authority shall equitably allocate, in a contested case proceeding, all of the economic benefits of any such sale between the ratepayers and the shareholders of the company.
(3) For the sale of land for an educational use, as defined in section 16-43b, the authority shall allocate the economic benefits of any such sale in accordance with past practices for nonopen space transactions pursuant to subsection (a) of this section.
(4) For the sale of class III land where the property is more than ten acres and promotes a perpetual public interest in the use of land for open space or recreation purposes, as defined in section 16-43b, the authority shall allocate the benefits in accordance with the following:
(A) If twenty-five per cent of the land or less is to be used for open space or recreational purposes, the authority shall allocate one hundred per cent of the benefits to the ratepayers;
(B) If more than twenty-five per cent but less than eighty per cent of the land is to be used for open space or recreational purposes, the authority shall calculate the benefit allocated to a water company's shareholders by multiplying by a factor of eighty per cent of the portion of class III land in the transaction that is reserved for open space;
(C) If eighty per cent or more but less than ninety per cent of the area of such land is to be used for open space or recreational purposes, the authority shall allocate the benefits of such sale in favor of a water company's shareholders in an amount that is proportionate to the percentage of class III land in such sale that is to be used for open space or recreational purposes;
(D) If not less than ninety per cent of the area of such land is to be used for open space or recreational purposes, the authority shall allocate one hundred per cent of the benefits to the shareholders.
(f) For the sale of class III land by a water company that at any time has been in the water company's rate base and that is to be used for open space or recreational purposes, the water company shall file with the authority a certified copy of a conservation easement that is recorded on the land records for the portion of class III land preserved as open space. Such conservation easement shall state that the land subject to such easement shall be permanently dedicated for land uses such as public parks or forests or natural areas, including, but not limited to, reservoirs and water company land. Such land shall be preserved predominantly in its natural scenic and open space condition that may allow for camping, hiking, forestry, fishing, wildlife or natural resource conservation, which easement shall prohibit all other building or development except as may be required for source protection and to meet water quality standards, if used as a public water supply.
(1949 Rev., S. 5433; 1969, P.A. 644, S. 3; P.A. 74-303, S. 2; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 323, 610; P.A. 80-156; 80-482, S. 75, 348; P.A. 82-252, S. 3; P.A. 85-509, S. 5, 11; P.A. 88-354, S. 3, 11; P.A. 89-301, S. 6; P.A. 90-221, S. 10; P.A. 93-381, S. 9, 39; P.A. 95-48, S. 1; 95-211, S. 4; 95-257, S. 12, 21, 58; P.A. 98-157, S. 9, 15; P.A. 01-49, S. 5; P.A. 03-163, S. 1; P.A. 04-200, S. 1; P.A. 05-288, S. 216; June Sp. Sess. P.A. 05-1, S. 36; P.A. 07-252, S. 86; P.A. 11-80, S. 1; Sept. Sp. Sess. P.A. 20-5, S. 6.)
History: 1969 act added proviso in Subdiv. (2) re bonds etc. for construction of power plants on islands in Long Island Sound prior to July 1, 1971; P.A. 74-303 required health commissioner's approval before commission approves sale of watershed or water supply lands by water companies; P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation and commissioner of health with commissioner of health services, effective January 1, 1979; P.A. 80-156 allowed extensions of time for approval or disapproval; P.A. 80-482 made division of public utility control an independent department and deleted reference to abolished department of business regulation; P.A. 82-252 required department approval for state condemnation of public service company land and amendment by any such company of indenture or similar financial instrument which affects notes, bonds or other evidences of indebtedness or securities, deleted obsolete provision exempting railroad companies' securities which are subject to Interstate Commerce Commission jurisdiction from provisions of section and divided section into two subsections; P.A. 85-509 provided that, on and after December 30, 1986, the provisions of Subsec. (a)(2) shall apply to a community antenna television company only with regard to noncable communications services; P.A. 88-354 amended Subsec. (a) by adding provision requiring that a permit be issued under Sec. 25-32 prior to acceptance of an application by the department and added new Subsec. (c) re the use by a water company of the net proceeds from the sale of water company land, and Subsec. (d) re an accounting method for the net proceeds of class III water company land; P.A. 89-301 amended Subsec. (c) by adding provision applying section to land that has ever been in the rate base; P.A. 90-221 added provision in Subsec. (d) concerning the allocation of economic benefits gained from the sale of water company land for open space or recreational purposes; P.A. 93-381 replaced commissioner of health services with commissioner of public health and addiction services, effective July 1, 1993; P.A. 95-48 divided Subsec. (a) into Subsecs. (a) and (b), relettered Subsecs. (b) to (d) as (c) to (e), amended Subsec. (a) by adding Subdiv. indicators and Subparas. (A) and (B) re property with appraised value of $50,000 or less and reporting requirement, amended Subsec. (b) by dividing Subsec. into Subdivs., deleting provision re constructing generating facility in Long Island Sound and adding provision re applicability to community antenna television companies, and made technical changes; P.A. 95-211 replaced reference to class III land with reference to land for which the commissioner has issued a permit; P.A. 95-257 replaced Commissioner and Department of Public Health and Addiction Services with Commissioner and Department of Public Health, effective July 1, 1995; P.A. 98-157 amended Subsec. (e) to modify the method of apportioning economic benefits of land sales, effective July 1, 1998; P.A. 01-49 amended Subsec. (a) to make a technical change; P.A. 03-163 amended Subsec. (a) to change the appraised value amount for a public service company other than a water company from $50,000 or less to $250,000 or less for improved real property and $50,000 or less for unimproved real property, to require that the department follow procedures in Sec. 16-50c for transactions involving unimproved land owned by public service companies other than water companies, and to make technical changes; P.A. 04-200 amended Subsec. (d) to authorize purchase of water supply source, amended Subsec. (e) to revise the method of allocating the net proceeds from the sale of water company land by adding provisions re allocation of economic benefits between ratepayers and shareholders, by adding Subdiv. (1) re property not more than ten acres and not taxed under certain provisions, Subdiv. (2) re class I or II land, Subdiv. (3) re land for an educational use, and Subdiv. (4) re tiered approach for class III land, and by making conforming changes, and added Subsec. (f) re the filing of a certified copy of a conservation easement for the sale of class III land for use as open space, effective June 3, 2004; P.A. 05-288 made a technical change in Subsec. (e)(4)(B), effective July 13, 2005; June Sp. Sess. P.A. 05-1 amended Subsec. (a) to require a public sale or an approved alternate sales process for the disposition of an essential part of real property, effective July 1, 2005; P.A. 07-252 amended Subsec. (a) to add provision eliminating requirement for public auction or other procedure for public sale with respect to sale or other disposition of real property by a water company to the state, a municipality or a land conservation organization, effective July 1, 2007; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; Sept. Sp. Sess. P.A. 20-5 amended Subsec. (b) to extend deadline for approval or disapproval of issuance of securities to 60 days, effective November 1, 2020.
Commission is prohibited from requiring par value stock of any corporation to be issued at a price in excess of par. 144 C. 516. Cited. 172 C. 362; 192 C. 506.
Cited. 42 CS 217.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-43a. Validity of securities issued pursuant to order of authority. Any stock, notes, bonds or other evidences of indebtedness or securities of any nature issued or sold pursuant to or in reliance on and in accordance with any order, authorization or decision of the Public Utilities Regulatory Authority pursuant to this title shall be valid and binding in accordance with their terms notwithstanding such order, authorization or decision of the authority is later vacated, modified, or otherwise held to be wholly or partly invalid, unless operation of such order, authorization or decision of the authority has been stayed or suspended by the authority or the reviewing court prior to such issuance.
(P.A. 78-100; 78-303, S. 85, 136; P.A. 80-482, S. 76, 348; P.A. 11-80, S. 1.)
History: P.A. 78-303 allowed substitution of division of public utility control within the department of business regulation for public utilities control authority to comply with provisions of P.A. 77-614; P.A. 80-482 made division of public utility control an independent department and deleted reference to abolished department of business regulation; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-43b. Definitions applicable to apportionment of land sales benefits. For purposes of subsection (e) of section 16-43, “open space or recreational purposes” means public parks or forests or natural areas, including, but not limited to, reservoirs and water company land, which are preserved predominantly in their natural scenic and open condition which may allow for camping, hiking, forestry, fishing, wildlife or natural resource conservation and “educational use” means the use by any town, city or borough, whether consolidated or unconsolidated, and any school district or regional school district for the purposes of schools and related facilities.
(P.A. 98-157, S. 10, 15; P.A. 04-200, S. 3.)
History: P.A. 98-157 effective July 1, 1998 (Revisor's note: In codifying this section the Revisors editorially changed “... camping; hiking; forestry; fishing; wildlife or ...” to “... camping, hiking, forestry, fishing, wildlife or ...”); P.A. 04-200 defined “educational use”, effective June 3, 2004.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-43c. Sale of water company land to certain municipal corporations for construction of a school. Notwithstanding the provisions of this chapter or section 12-217dd, any land acquired from a water company, as defined in section 16-1, by a municipal corporation for the purposes of construction of a school and related facilities in a town with a population between eleven thousand six hundred and eleven thousand nine hundred, as enumerated by the 2000 federal decennial census, shall be treated as open space for purposes of establishing the right to acquire, ratemaking and taxes.
(P.A. 04-156, S. 1; P.A. 05-288, S. 217.)
History: P.A. 04-156 effective June 1, 2004; P.A. 05-288 made technical changes, effective July 13, 2005.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-43d. Sale of existing electric generation plants. If any existing electric generation plant within the state is offered for sale, the Public Utilities Regulatory Authority shall authorize the electric distribution companies to purchase and operate such plants if the authority, through a contested case proceeding, determines that such purchase and operation is in the public interest, provided any acquisition plan shall include provisions for payment of property taxes on the value of the purchased plant and provisions for employee protections. An electric distribution company purchasing such generation plants shall be entitled to recover the costs of such purchase in an annual retail generation rate contested case consistent with the principles set forth in sections 16-19, 16-19b and 16-19e, provided the return on equity associated with such purchase and operation shall be established in said contested case proceeding and updated at least once every four years. The authority shall review and approve the cost recovery provisions in the proceeding to determine that such purchase and operation are in the public interest.
(P.A. 07-242, S. 83; P.A. 11-80, S. 1; P.A. 14-134, S. 124.)
History: P.A. 07-242 effective June 4, 2007; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 14-134 deleted reference to Sec. 16-244f(b)(3), effective June 6, 2014.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-44. Notice of formation, consolidation or discontinuance of public service companies; change of name. Penalty. Whenever any company is organized for the purpose of doing business as a public service company, or whenever any company so organized acquires any plant or any part of a plant or equipment, or begins doing business as a public service company, or whenever any foreign public service company commences business in this state, or whenever any public service company doing business in this state merges with any other company or companies or permanently discontinues doing business as a public service company, or changes its corporate name, the secretary of the company shall, within ten days from the date thereof, notify the Public Utilities Regulatory Authority of the action of the company or companies, on blanks to be furnished by the authority on request. The secretary of any public service company who fails to comply with the provisions of this section shall be fined not more than two hundred fifty dollars.
(1949 Rev., S. 5434; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 77, 348; P.A. 82-150, S. 7; P.A. 11-80, S. 1; P.A. 12-80, S. 10.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 82-150 made technical changes; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011; P.A. 12-80 replaced penalty of a fine of not more than $200 or imprisonment of not more than 60 days or both with a fine of not more than $250.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-44a. Disclosure of salaries of directors and officers of public service companies. (a) Each public service company, as defined in section 16-1, regulated pursuant to sections 16-19 and 16-19e and serving more than three thousand three hundred customers shall (1) on each customer's bill, notify customers at least annually that a listing of the salaries of its directors and officers can be obtained from the Public Utilities Regulatory Authority at the customer's request, and (2) not later than July first, annually, submit to the authority a listing of the salaries of all its directors and officers during the preceding fiscal year. Any such public service company that files Securities and Exchange Commission Form 10-K, Part III with the authority pursuant to an order of the authority shall be deemed to be in compliance with subdivision (2) of this subsection.
(b) The authority shall maintain and make available to the public a listing of the salaries of directors and officers of each public service company regulated pursuant to sections 16-19 and 16-19e and serving more than three thousand three hundred customers. The authority shall mail such listing to any person that requests it.
(P.A. 97-30, S. 1, 2; P.A. 11-80, S. 1.)
History: P.A. 97-30 effective May 6, 1997; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-45. Increase or reduction of capital stock by public service companies. Any public service company which is authorized to increase its authorized capital stock in accordance with the laws applicable to corporations organized under the general law may increase or reduce its authorized capital stock at a meeting of its stockholders warned and held for that purpose by a vote of at least two-thirds of each class of stock issued and outstanding at the time of such vote, or at a meeting of the stockholders called upon thirty days' notice by a vote of at least two-thirds of each class of stock represented at such meeting. Nothing herein shall be construed to affect in any way the powers and authority of the Public Utilities Regulatory Authority with respect to issuance of securities by public service companies.
(1949 Rev., S. 5436; 1949, 1951, S. 2609d; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 78, 348; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
See Sec. 16-43(b) re issuance and approval of notes, bonds, securities, etc.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-46. Dissolution or termination of public service company. Cessation of public service operations. (a) No public service company shall cease operations as a public service company, dissolve or terminate its corporate existence without the consent of the Public Utilities Regulatory Authority, except a water company, as defined in section 16-262n, shall not cease its operations, or unilaterally discontinue the provision of water service to customers without the consent of both the Public Utilities Regulatory Authority and the Department of Public Health. Upon receipt of a request from a water company to cease its operations or discontinue the provision of water service, the Public Utilities Regulatory Authority, in conjunction with the Department of Public Health, shall hold a public hearing and issue a final decision setting forth the actions the water company shall take to ensure a continuous supply of potable water at adequate volume and pressures, in accordance with the procedures and criteria set forth in sections 16-262n to 16-262q, inclusive.
(b) Any public service company may, with such consent, or in the case of a water company, as defined in section 16-262n, for which a decision has been issued pursuant to section 16-262o, such water company shall, dissolve and terminate its corporate existence in the manner provided for dissolution and termination by such company's charter or certificate of incorporation, provided, if such charter or certificate requires stockholder approval, such approval shall be by not less than two-thirds of the voting power of the shares entitled to vote thereon. If there is no provision for dissolution and termination in such charter or certificate, such company may, with the consent of the Public Utilities Regulatory Authority, or in the case of a water company, the consent of both the Public Utilities Regulatory Authority and the Department of Public Health, dissolve and terminate its corporate existence in any manner provided in part XIV of chapter 601 in the case of a company organized with capital stock or part XI of chapter 602 in the case of a company organized without capital stock. Such dissolution and termination shall take effect upon (1) for a corporation, the filing with the Secretary of the State of a certificate of dissolution, and (2) for an unincorporated entity, the filing of a certificate of dissolution with the Public Utilities Regulatory Authority and the Department of Public Health. In the event of such cessation, dissolution or termination, all claims and rights of creditors shall constitute liens upon the property and franchises of the company and shall continue in existence as long as may be necessary to preserve the same.
(1949 Rev., S. 5437; P.A. 75-486, S. 1, 69; P.A. 77-484; 77-614, S. 162, 610; P.A. 80-482, S. 79, 348; P.A. 95-118, S. 3; 95-257, S. 12, 21, 58; P.A. 96-256, S. 183, 209; 96-271, S. 160, 254; P.A. 06-196, S. 201; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-484 replaced previous provision for dissolution upon unanimous vote of persons present at stockholders' meeting with detailed provisions for various manners of dissolution; P.A. 77-614 replaced the authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division of public utility control an independent department and deleted reference to abolished department of business regulation; P.A. 95-118 divided section into Subsecs. and added provisions re water company hearing, decision issued pursuant to Sec. 16-262o, involvement of Department of Public Health and Addiction Services and effective date of dissolution of unincorporated entity; P.A. 95-257 replaced Commissioner and Department of Public Health and Addiction Services with Commissioner and Department of Public Health, effective July 1, 1995; P.A. 96-256 amended Subsec. (b) to replace reference to “part VIII of chapter 600” with “part XI of chapter 602”, effective January 1, 1997; P.A. 96-271 amended Subsec. (b) to replace reference to “part X of chapter 599” with “part XIV of chapter 601”, effective January 1, 1997; P.A. 06-196 made technical changes in Subsec. (b), effective June 7, 2006; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-47. Holding companies. Approval of authority re exercise of control. Investigation and hearing. Annual reports. Injunctive relief. (a) As used in this section and section 16-47a, (1) “holding company” means any corporation, association, partnership, trust or similar organization, or person which, either alone or in conjunction and pursuant to an arrangement or understanding with one or more other corporations, associations, partnerships, trusts or similar organizations, or persons, directly or indirectly, controls a gas, electric distribution, water, telephone or community antenna television company, and (2) “control” means the possession of the power to direct or cause the direction of the management and policies of a gas, electric distribution, water, telephone or community antenna television company or a holding company, whether through the ownership of its voting securities, the ability to effect a change in the composition of its board of directors or otherwise, provided, control shall not be deemed to arise solely from a revocable proxy or consent given to a person in response to a public proxy or consent solicitation made pursuant to and in accordance with the applicable rules and regulations of the Securities Exchange Act of 1934 unless a participant in said solicitation has announced an intention to effect a merger or consolidation with, reorganization, or other business combination or extraordinary transaction involving the gas, electric distribution, water, telephone or community antenna television company or the holding company. Control shall be presumed to exist if a person directly or indirectly owns ten per cent or more of the voting securities of a gas, electric distribution, water, telephone or community antenna television company or a holding company, provided the authority may determine, after conducting a hearing, that said presumption of control has been rebutted by a showing that such ownership does not in fact confer control.
(b) No gas, electric distribution, water, telephone or community antenna television company, or holding company, or any official, board or commission purporting to act under any governmental authority other than that of this state or of its divisions, municipal corporations or courts, shall interfere or attempt to interfere with or, directly or indirectly, exercise or attempt to exercise authority or control over any gas, electric distribution, water, telephone or community antenna television company engaged in the business of supplying service within this state, or with or over any holding company doing the principal part of its business within this state, without first making written application to and obtaining the approval of the Public Utilities Regulatory Authority, except as the United States may properly regulate actual transactions in interstate commerce.
(c) No corporation, association, partnership, trust or similar organization, or person shall take any action that causes it to become a holding company with control over a gas, electric distribution, water, telephone or community antenna television company engaged in the business of supplying service within this state, or acquire, directly or indirectly, control over such a holding company, or take any action that would if successful cause it to become or to acquire control over such a holding company, without first making written application to and obtaining the approval of the authority. Any such corporation, association, partnership, trust or similar organization, or person applying to the authority for such approval shall pay the reasonable expenses incurred by the authority in carrying out its duties under this subsection, and accordingly, shall deposit with the authority a bond, executed by a surety company authorized to do business in this state, in the amount of fifty thousand dollars, conditioned to indemnify the authority for such expenses.
(d) The Public Utilities Regulatory Authority shall investigate and hold a public hearing on the question of granting its approval with respect to any application made under subsection (b) or (c) of this section and thereafter may approve or disapprove any such application in whole or in part and upon such terms and conditions as it deems necessary or appropriate. In connection with its investigation, the authority may request the views of the gas, electric distribution, water, telephone or community antenna television company or holding company which is the subject of the application with respect to the proposed acquisition. After the filing of an application satisfying the requirements of such regulations as the authority may adopt in accordance with the provisions of chapter 54, but not later than thirty business days after the filing of such application, the authority shall give prompt notice of the public hearing to the person required to file the application and to the subject company or holding company. Such hearing shall be commenced as promptly as practicable after the filing of the application, but not later than sixty business days after the filing, and the authority shall make its determination as soon as practicable, but not later than two hundred days after the filing of the application, provided it may, before the end of such period and upon notifying all parties and intervenors to the proceedings, extend the period by thirty days, or unless the person required to file the application agrees to an extension of time. The authority may, in its discretion, grant the subject company or holding company the opportunity to participate in the hearing by presenting evidence and oral and written argument. If the authority fails to give notice of its determination to hold a hearing, commence the hearing, or render its determination after the hearing within the time limits specified in this subdivision, the proposed acquisition shall be deemed approved. In each proceeding on a written application submitted under said subsection (b) or (c), the authority shall, in a manner which treats all parties to the proceeding on an equal basis, take into consideration (1) the financial, technological and managerial suitability and responsibility of the applicant, (2) the ability of the gas, electric distribution, water, telephone or community antenna television company or holding company which is the subject of the application to provide safe, adequate and reliable service to the public through the company's plant, equipment and manner of operation if the application were to be approved, and (3) for an application concerning a telephone company, the effect of approval on the location and accessibility of management and operations and on the proportion and number of state resident employees. The authority shall only grant its approval of an application filed on or after January 1, 2021, made under subsection (c) of this section, if the holding company effects a change in the composition of the board of directors to include a proportional percentage of Connecticut-based directors equivalent to the percentage that Connecticut service areas represent of the total service areas covered by the holding company.
(e) During any proceeding under subsection (b) or (c) of this section, the authority may order any party to such proceeding and the officers, directors, employees and agents of such party to refrain for a specific time period from communicating, directly or indirectly, with the record and beneficial owners of securities of the gas, electric distribution, water, telephone or community antenna television company or holding company which is the subject of such proceedings, in regard to the matters submitted to the authority for its approval under said subsection (b) or (c). If the authority issues such an order, it shall also order all other parties to the proceeding and the officers, directors, employees and agents of such parties to refrain for the same time period from communicating, directly or indirectly, with such record and beneficial owners of such securities, in regard to such matters. No order issued pursuant to this subsection shall prohibit any party from complying with disclosure and reporting obligations under any other provision of the general statutes or under federal law.
(f) Each holding company shall, not later than three months after the close of its fiscal year, annually, file with the authority a copy of its annual report to stockholders for such fiscal year. If the holding company does not print such an annual report, it shall file instead, not later than the same date, a comprehensive audit and report of its accounts and operations prepared by an independent public accounting firm approved by the authority. The provisions of this subsection shall not apply to any holding company in the form of a person.
(g) Any action contrary to the provisions of subsections (b) or (c) of this section shall be voidable on order of the authority.
(h) Whenever any corporation, association, partnership, trust or similar organization, or person takes or engages in any action which may or would violate subsection (b) or (c) of this section or any order adopted pursuant to said subsection (b) or (c), the Superior Court, upon application of the authority or any holding company or gas, electric distribution, water, telephone or community antenna television company affected by such action, may enjoin any such corporation, association, partnership, trust or similar organization, or person from continuing or doing any act in violation of said subsection (b) or (c) or may otherwise enforce compliance with said subsection (b) or (c), including but not limited to, the reinstatement of authority or control over the holding company or gas, electric distribution, water, telephone or community antenna television company or holding company to those persons who exercised authority or control over such company before such action.
(i) The provisions of this section shall not be construed to require any person to make written application to or obtain the approval of the authority with respect to any telephone company or holding company of a telephone company over which such person exercises authority or control or operates as a holding company on June 30, 1987.
(1949 Rev., S. 5438; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 80, 348; P.A. 82-252, S. 4, 6; 82-472, S. 176, 183; P.A. 85-549, S. 1, 3; P.A. 86-40, S. 1, 2; P.A. 87-446, S. 1, 3; P.A. 94-74, S. 10, 11; P.A. 98-28, S. 98, 117; P.A. 09-218, S. 1; P.A. 11-80, S. 1; P.A. 14-134, S. 69; Sept. Sp. Sess. P.A. 20-5, S. 7.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; P.A. 82-252 divided section into Subsecs., included trusts and similar organizations in definition of “holding company”, applied section provisions to community antenna television companies, added Subsecs. (c), (d) and (f), respectively prohibiting any corporation, association, trust or similar organization, or person from taking action to become a holding company without department approval, requiring holding companies to file annual reports and authorizing injunctive relief for violations of Subsec. (c); P.A. 82-472 made a technical change in Subsecs. (a) and (c) by clarifying that partnerships are included in the definition of “holding company”; P.A. 85-549 amended Subsecs. (b) and (c) to eliminate provisions limiting protection under said Subsecs. to companies incorporated by this state, added new Subsec. (d) re time limit on department approval or disapproval of application and added new Subsec. (e) re department orders restricting communications with owners of securities of company which is subject to proceedings, relettered former Subsecs. (d), (e) and (f) as (f), (g) and (h), respectively, and applied provisions of Subsec. (h) to violations of Subsec. (b); P.A. 86-40 added provisions in Subsec. (d) re department considerations in proceedings on written applications; P.A. 87-446 made section applicable to telephone companies, added definition of “control” and provisions re presumption of control, made technical changes re application and approval process, and added Subsec. (i); P.A. 94-74 amended Subsec. (d) by requiring investigation and hearing, changing hearing notice deadline from 20 to 30 days, hearing commencement deadline from 20 to 30 days and determination deadline from 90 to 120 days, adding “financial, technological and managerial” to Subdiv. (1), and adding Subdiv. (3) re applications concerning a telephone company, effective July 1, 1994; P.A. 98-28 added electric distribution companies, effective July 1, 1998; P.A. 09-218 amended Subsec. (a) by designating existing definitions as Subdivs. (1) and (2) and adding reference to Sec. 16-47a, effective July 8, 2009; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011; P.A. 14-134 deleted references to electric company, effective June 6, 2014; Sept. Sp. Sess. P.A. 20-5 amended Subsec. (d) to extend hearing deadline to 60 business days, extend determination deadline to 200 days with option to extend additional 30 days with notice, and add provision conditioning approval of applications filed on or after Jan. 1, 2021 upon an effective change in composition of board of directors, effective January 1, 2021.
Commission's approval of a transfer which in time might result in an allocation of water outside of franchise area upheld. 146 C. 1.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-47a. Code of conduct for gas company transactions with affiliates. (a) As used in this section, “affiliate” means a person, as defined in section 16-1, or class of persons that, with a gas company, as defined in said section 16-1, is under the control of the same holding company, or a person or class of persons that the Public Utilities Regulatory Authority may, after notice and hearing, find has such a relation to a gas company conducting business and financial transactions that involve cross-subsidization or preferential treatment between the company and such person or class of persons as to make it necessary to protect ratepayers.
(b) The Public Utilities Regulatory Authority shall establish a code of conduct that sets minimum standards for gas company transactions with affiliates to achieve, at a minimum, the following goals, provided such code shall not interfere with interactions with regulated affiliates that are consistent with appropriate and efficient business practice or the public interest:
(1) Provide rules for when the purchases or sales of goods or services between a gas company and an affiliate should be by written contract based on such factors as the nature, value and term of the purchase or sale;
(2) Provide rules with respect to sharing or giving access to certain types of customer identifying or commercially sensitive information to affiliates that may differ between regulated and unregulated affiliates;
(3) Provide for a system of records and reporting for transactions between a gas company and its affiliates;
(4) Establish standards to ensure that any payment by a gas company to any affiliate or from any affiliate to a gas company is appropriate and reasonable;
(5) Provide a standard for avoidance of conflict of interest between a gas company and affiliates;
(6) Ensure that any such transactions shall not have an improper and adverse impact on the costs or revenues of the gas company, on the rates and charges paid by gas company customers or on the quality of service provided by the gas company;
(7) Ensure that gas company ratepayers do not subsidize affiliate operations;
(8) Ensure fair, appropriate and equitable standards for purchases, sales, leases, asset transfers and cost or profit-sharing transactions or any type of financing or encumbrance involving a gas company and its affiliates; and
(9) Ensure that gas supply and distribution services are provided by a gas company in an appropriate manner to affiliates and nonaffiliates alike.
(c) In addition to the powers granted to the authority in section 16-8c, during a rate proceeding under 16-19, the authority may summon witnesses from an affiliate with which a gas company has had direct or indirect transactions, examine the affiliate under oath and order production, inspect and audit the books, records or other information relevant to any transaction that the authority has reason to believe has or will have an adverse impact on the costs and revenues of the affiliated gas company. Proprietary commercial and proprietary financial information of an affiliate provided pursuant to this section shall be confidential and protected by the authority as the authority deems appropriate, subject to the provisions of section 1-210.
(d) Each gas company shall submit to the authority records and such information as the authority may require, at intervals determined by the authority and in such form as the authority may order regarding affiliate transactions.
(e) The authority may, upon its own motion, investigate a gas company's compliance with the code of conduct, and any such investigation shall be a contested case, as defined in section 4-166.
(f) The authority may make orders to enforce the code of conduct, including, but not limited to, cease and desist orders and may levy civil penalties pursuant to section 16-41 against entities subject to the code of conduct.
(g) The code of conduct shall not prohibit communications necessary to restore gas company service or to prevent or respond to emergency conditions.
(h) On or before November 1, 2010, the authority shall adopt regulations, in accordance with the provisions of chapter 54, to establish the code of conduct in accordance with subsection (b) of this section, related accounting and reporting requirements and procedures for gas company and affiliate compliance with this section.
(i) Any methodology for the allocation of costs between a gas company and other companies under the control of the same holding company currently approved by, or under current orders issued by, the Securities and Exchange Commission under the Public Utility Holding Company Act of 1935 or the Federal Energy Regulatory Commission under the Public Utility Holding Company Act of 2005, shall be entitled to a rebuttable presumption of reasonableness. Charges rendered to a gas company by an affiliate that is a traditional centralized service company shall be at cost and entitled to a rebuttable presumption of reasonableness.
(P.A. 09-218, S. 2; P.A. 11-80, S. 1.)
History: P.A. 09-218 effective July 8, 2009; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-48. Electricity and gas; transmission between this state and other states. The Public Utilities Regulatory Authority is authorized to enter into compacts in the name of the state of Connecticut with the states of New York, Vermont, Massachusetts, Rhode Island, New Jersey and Pennsylvania, or any one or more of said states, through such body in such state or states as may be designated by law to act, for the purpose of establishing joint regulation and control of rates for electricity and gas transmitted between such states; provided the power to enter into such compacts shall be authorized by the Congress of the United States. The authority shall report the terms of any such compact to the General Assembly of this state at its first regular session after such compact has been agreed upon; but no such agreements or compacts shall become effective until approved by the General Assembly and the Congress of the United States.
(1949 Rev., S. 5439; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 610; P.A. 80-482, S. 81, 348; P.A. 11-80, S. 1.)
History: P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced public utilities control authority with division of public utility control within the department of business regulation, effective January 1, 1979; P.A. 80-482 made division an independent department and deleted reference to abolished department of business regulation; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-48a. Consumer Counsel and Public Utility Control Fund established. There is established a fund to be known as the “Consumer Counsel and Public Utility Control Fund”. The fund may contain any moneys required by law to be deposited in the fund and shall be held by the Treasurer separate and apart from all other moneys, funds and accounts. The interest derived from the investment of the fund shall be credited to the fund. Amounts in the fund may be expended only pursuant to appropriation by the General Assembly. Any balance remaining in the fund at the end of any fiscal year shall be carried forward in the fund for the fiscal year next succeeding.
(June Sp. Sess. P.A. 91-14, S. 15, 30.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-49. Expenses of the Department of Energy and Environmental Protection's Bureau of Energy and Technology, the Office of Consumer Counsel, the Office of Policy and Management and the operations of the Public Utilities Regulatory Authority. Assessment of regulated companies. (a) As used in this section:
(1) “Company” means (A) any public service company other than a telephone company, that had more than one hundred thousand dollars of gross revenues in the state in the calendar year preceding the assessment year under this section, except any such company not providing service to retail customers in the state, (B) any telephone company that had more than one hundred thousand dollars of gross revenues in the state from telecommunications services in the calendar year preceding the assessment year under this section, except any such company not providing service to retail customers in the state, (C) any certified telecommunications provider that had more than one hundred thousand dollars of gross revenues in the state from telecommunications services in the calendar year preceding the assessment year under this section, except any such certified telecommunications provider not providing service to retail customers in the state, (D) any electric supplier that had more than one hundred thousand dollars of gross revenues in the state in the calendar year preceding the assessment year under this section, except any such supplier not providing electric generation services to retail customers in the state, or (E) any certified competitive video service provider issued a certificate of video franchise authority by the Public Utilities Regulatory Authority in accordance with section 16-331e that had more than one hundred thousand dollars of gross revenues in the state in the calendar year preceding the assessment year under this section, except any such certified competitive video service provider not providing service to retail customers in the state;
(2) “Telecommunications services” means (A) in the case of telecommunications services provided by a telephone company, any service provided pursuant to a tariff approved by the authority other than wholesale services and resold access and interconnections services, and (B) in the case of telecommunications services provided by a certified telecommunications provider other than a telephone company, any service provided pursuant to a tariff approved by the authority and pursuant to a certificate of public convenience and necessity; and
(3) “Fiscal year” means the period beginning July first and ending June thirtieth.
(b) On or before July 15, 1999, and on or before May first, annually thereafter, each company shall report its intrastate gross revenues of the preceding calendar year to the Public Utilities Regulatory Authority, which amount shall be subject to audit by the authority. For each fiscal year, each company shall pay the authority the company's share of all expenses of the department's Bureau of Energy and Technology, the Office of Consumer Counsel, the Office of Policy and Management's expenses related to the duties under sections 16-330b and 16-330c and the operations of the Public Utilities Regulatory Authority for such fiscal year. On or before September first, annually, the authority shall give to each company a statement which shall include: (1) The amount appropriated to the department's Bureau of Energy and Technology, the Office of Consumer Counsel, the Office of Policy and Management's expenses related to the duties under sections 16-330b and 16-330c and the operations of the Public Utilities Regulatory Authority for the fiscal year beginning July first of the same year; (2) the total gross revenues of all companies; and (3) the proposed assessment against the company for the fiscal year beginning on July first of the same year, adjusted to reflect the estimated payment required under subdivision (1) of subsection (c) of this section. Such proposed assessment shall be calculated by multiplying the company's percentage share of the total gross revenues as specified in subdivision (2) of this subsection by the total revenue appropriated to the department's Bureau of Energy and Technology, the Office of Consumer Counsel, the Office of Policy and Management's expenses related to the duties under sections 16-330b and 16-330c and the operations of the Public Utility Regulatory Authority, as specified in subdivision (1) of this subsection.
(c) Each company shall pay the authority: (1) On or before June thirtieth, annually, an estimated payment for the expenses of the following year equal to twenty-five per cent of its assessment for the fiscal year ending on such June thirtieth, (2) on or before September thirtieth, annually, twenty-five per cent of its proposed assessment, adjusted to reflect any credit or amount due under the recalculated assessment for the preceding fiscal year, as determined by the authority under subsection (d) of this section, provided if the company files an objection in accordance with subsection (e) of this section, it may withhold the amount stated in its objection, and (3) on or before the following December thirty-first and March thirty-first, annually, the remaining fifty per cent of its proposed assessment in two equal installments.
(d) Immediately following the close of each fiscal year, the authority shall recalculate the proposed assessment of each company, based on the expenses, as determined by the Comptroller, of the department's Bureau of Energy and Technology, the Office of Consumer Counsel, the Office of Policy and Management's expenses related to the duties under sections 16-330b and 16-330c and the operations of the Public Utilities Regulatory Authority for such fiscal year. On or before September first, annually, the authority shall give to each company a statement showing the difference between its recalculated assessment and the amount previously paid by the company.
(e) Any company may object to a proposed or recalculated assessment by filing with the authority, not later than September fifteenth of the year of said assessment, a petition stating the amount of the proposed or recalculated assessment to which it objects and the grounds upon which it claims such assessment is excessive, erroneous, unlawful or invalid. After a company has filed a petition, the authority shall hold a hearing. After reviewing the company's petition and testimony, if any, the authority shall issue an order in accordance with its findings. The company shall pay the authority the amount indicated in the order not later than thirty days after the date of the order.
(f) The authority shall remit all payments received under this section to the State Treasurer for deposit in the Consumer Counsel and Public Utility Control Fund established under section 16-48a. Such funds shall be accounted for as expenses recovered from public service companies and certified telecommunications providers. All payments made under this section shall be in addition to any taxes payable to the state under chapters 211, 212, 212a and 219.
(g) Any assessment unpaid on the due date or any portion of an assessment withheld after the due date under subsection (c) of this section shall be subject to interest at the rate of one and one-fourth per cent per month or fraction thereof, or fifty dollars, whichever is greater.
(h) Any company that fails to report in accordance with this section shall be subject to civil penalties in accordance with section 16-41.
(1953, S. 2610d; 1959, P.A. 48, S. 1; 354, S. 1; 1969, P.A. 611, S. 1; 1972, P.A. 138, S. 2; P.A. 74-179, S. 1, 2; P.A. 75-486, S. 4, 69; P.A. 76-335, S. 1; P.A. 77-614, S. 162, 164, 610; P.A. 80-482, S. 82, 348; Nov. Sp. Sess. P.A. 81-8, S. 1, 4; P.A. 83-55, S. 1, 3; 83-587, S. 31, 96; P.A. 84-296, S. 1, 2; P.A. 85-246, S. 10; 85-552, S. 1, 8; P.A. 88-17; 88-22, S. 4; P.A. 90-148, S. 24, 34; June Sp. Sess. P.A. 91-14, S. 16, 30; P.A. 94-74, S. 5, 11; P.A. 98-28, S. 36, 117; P.A. 99-105, S. 2, 4; P.A. 11-80, S. 30; P.A. 13-119, S. 6; P.A. 21-159, S. 8.)
History: 1959 acts increased the assessment under Subsec. (a) from 45% to 50%, provided for certification of assessments under Subsec. (b) to be on or before first day of September rather than first day of August and deleted provision that deposit of assessments in general fund be accounted for as expenses recovered from public service companies; 1969 act increased limit on amount of assessment from $250,000 to $450,000; 1972 act increased percentage of expenses assessed to 56% and limit on assessment amount to $600,000; P.A. 74-179 deleted provision re limit on dollar amount of assessment and exempted companies with gross earnings not exceeding $100,000 rather than $300,000; P.A. 75-486 replaced public utilities commission with public utilities control authority, raised percentage of expenses assessed to 70% in Subsec. (a) and added exception re Subsec. (c) and replaced 6% interest with rate established by authority in Subsec. (b); P.A. 76-335 included expenses of office of consumer counsel under Subsec. (a); P.A. 77-614 replaced authority with division of public utility control within the department of business regulation and office of consumer counsel with division of consumer counsel within the same department, effective January 1, 1979; P.A. 80-482 made division of public utility control an independent department, placed division of consumer counsel within it and deleted references to abolished department of business regulation; Nov. Sp. Sess. P.A. 81-8 redefined “public service company” to exempt any company not providing service at retail directly to consumers in the state, deleted most of Subsec. (a) and all of Subsecs. (b) and (c), and added new Subsecs. (b) to (h), providing for assessment on current basis of public service companies for all expenses of department of public utility control and division of consumer counsel for fiscal years beginning July 1, 1981, to July 1, 1983, and for 70% of such expenses for following fiscal years; P.A. 83-55 extended assessment of public service companies for all expenses of department and division through fiscal year beginning July 1, 1984; P.A. 83-587 made technical change in Subsec. (c); P.A. 84-296 extended assessment of public service companies for all expenses of department and division through fiscal year beginning July 1, 1986; P.A. 85-246 deleted reference to street railway companies in Subsec. (a); P.A. 85-552 repealed Subsec. (b) re assessments for the fiscal year beginning July 1, 1981, and relettered the remaining Subsecs. accordingly, repealed provision assessing public service companies for 70%, instead of for all, expenses of department for fiscal years beginning on and after July 1, 1987, and added Subsec. (h) re report to general assembly; P.A. 88-17 defined the term “certified competitive telecommunications provider” and applied provisions to such providers; P.A. 88-22 substituted office of consumer counsel for the division of consumer counsel; P.A. 90-148 amended Subsec. (a) to distinguish between telephone companies with less than $100,000 of gross revenue and those with more than said amount for purposes of assessment under this section, amended Subsec. (b) to make the assessment thereunder for department expenses applicable with respect to state fiscal years ending prior to July 1, 1990, and inserted a new Subsec. (c), with appropriate changes in lettering for succeeding Subsecs., providing assessment procedures for department expenses virtually identical to those in Subsec. (b), except as described in Subdiv. (3), applicable in the case of state fiscal years ending after July 1, 1990, with such changes in procedure occurring in the reference to gross revenues of telecommunications providers because of the change in state taxes imposed on such providers commencing January 1, 1990, and in the provision for an estimated payment of expenses for the following year, first payable on or before June 30, 1990; June Sp. Sess. P.A. 91-14 amended Subsec. (f) to provide that on and after July 1, 1991, moneys deposited with state treasurer shall be credited to consumer counsel and public utility control fund, rather than general fund; P.A. 94-74 changed applicability from public service companies and certified competitive telecommunications providers to public service companies and persons, firms and corporations certified to provide intrastate telecommunications services, collectively referred to as “companies”, deleted references to chapter 210a and provisions re fiscal years ending prior to July 1, 1990, and calendar years ending on or before December 31, 1989, divided Subsec. (c) into Subsecs. (b) and (c), corrected reference in Subsec. (b) to source of estimated payment requirement and made technical corrections to Subsecs. (e), (f) and (g), effective July 1, 1994; (Revisor's note: In 1997 in Subsecs. (a) and (b) references to “subdivision (24)” and “subsection (24)” of Sec. 12-407 were changed editorially by the Revisors to “subdivision (26)” in all cases to conform section with Sec. 12-407 and customary statutory usage); P.A. 98-28 added Subsec. (a)(3) concerning certain electric suppliers and making technical changes, effective July 1, 1998; P.A. 99-105 amended Subsec. (a) by deleting former Subdivs. (1) and (2), adding new Subdiv. (1) defining “company”, incorporating therein former Subdiv. (3) as Subpara. (D), and by adding new Subdivs. (2) and (3) defining “telecommunications services” and “fiscal year”, amended Subsec. (b) by inserting provision subjecting companies to audits, by deleting references to personnel fringe benefits and expenses for central state services and by referring to the defined term “company” in lieu of existing references to various entities, amended Subsec. (c) to require a hearing after a company has filed a petition in lieu of upon the request of the company filing a petition, added reference in Subsec. (g) to “fifty dollars, whichever is greater”, deleted former Subsec. (h) and inserted new Subsec. (h) re penalties, and made numerous technical changes, effective July 1, 1999; P.A. 11-80 amended Subsec. (a)(1) by adding Subpara. (E) re certified competitive video service providers, amended Subsec. (a)(2) by replacing “department” with “authority”, amended Subsec. (b) by requiring companies to send revenues to Public Utilities Regulatory Authority rather than department, replacing “department” with “authority” and changing entities for which expenses are covered from Department of Public Utility Control and Office of Consumer Counsel to Department of Energy and Environmental Protection's Bureau of Energy, Office of Consumer Counsel and Public Utilities Regulatory Authority, amended Subsec. (c) by replacing “department” with “authority”, amended Subsec. (d) by replacing “department” with “authority” and changing the entities for which expenses are covered from department and Office of Consumer Counsel to department's Bureau of Energy, Office of Consumer Counsel and Public Utilities Regulatory Authority, and amended Subsecs. (e) and (f) by replacing “department” with “authority”, effective July 1, 2011; P.A. 13-119 amended Subsec. (a)(1)(E) to replace “Department of Energy and Environmental Protection” with “Public Utilities Regulatory Authority”, effective June 18, 2013; P.A. 21-159 amended Subsecs. (b) and (d) by replacing “Bureau of Energy” with “Bureau of Energy and Technology” and adding Office of Policy and Management's expenses related to duties under Secs. 16-330b and 16-330c as covered expenses, effective July 1, 2021.
See Sec. 28-31 for assessment of Nuclear Regulatory Commission licensees by the authority for the nuclear safety emergency preparedness program.
Cited. 214 C. 609.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Secs. 16-49a to 16-49c. Appropriation. Council on water company lands established. Moratorium on sale of water company lands; duties of council. Sections 16-49a to 16-49c, inclusive, are repealed.
(1972, P.A. 138, S. 1; P.A. 75-405, S. 1, 2, 5; 75-486, S. 1, 69; 75-567, S. 55, 80; P.A. 76-123, S. 1, 2; P.A. 77-614, S. 19, 162, 320, 323, 587, 610; P.A. 78-303, S. 85, 136; P.A. 80-482, S. 83, 348; P.A. 83-487, S. 32, 33.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-49d. Applications for sales of water company lands submitted prior to June 25, 1975. Section 16-49d is repealed, effective October 1, 2002.
(P.A. 75-405, S. 5; P.A. 83-487, S. 7, 33; S.A. 02-12, S. 1.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-49e. Public service company may request identification from person opening an account. Telecommunications company may request identification prior to providing service. (a) As used in this section, “identification” means a Social Security number, the number of an identity card issued pursuant to section 1-1h, the number of a motor vehicle operator's license issued pursuant to section 14-36, a valid passport issued by the United States or a foreign government, a resident alien card or an alien registration card issued by the United States Immigration and Naturalization Service, any other valid forms of identification issued by the federal government or a state or municipal government, or any other means of identification approved by the Public Utilities Regulatory Authority. A public service company, as defined in section 16-1, may request a person opening an account with the company to provide the company with two forms of identification, one of which contains a picture of the person, at the time of opening the account. If a person opening an account fails to provide the requested identification, the public service company shall open an account for such person and allow fifteen days for such person to provide the company with identification. If such person fails to provide the required identification within fifteen days, the public service company may terminate service to such person.
(b) A telecommunications company that is certified to provide telecommunications service pursuant to section 16-247g may not require a prospective residential customer to provide identification as a condition of providing telecommunications service, except to the extent that a public service company is permitted pursuant to subsection (a) of this section.
(c) Nothing in this section shall be construed to preclude a company from accepting additional forms of identification, provided the company accepts the forms of identification specified in subsection (a) of this section.
(P.A. 95-274, S. 1; P.A. 02-8, S. 1; P.A. 11-80, S. 1.)
History: P.A. 02-8 designated existing provisions as Subsec. (a) and amended same to expand definition of “identification” to include a passport, a resident alien card, an alien registration card, or any other valid form of identification issued by the federal government or a state or municipal government, to allow a public service company to request two forms of identification, one of which contains a picture of the person, and to make conforming changes, added Subsec. (b) to allow a telecommunications company to request identification to the same extent as a public service company, and added Subsec. (c) to allow companies to accept additional forms of identification, effective April 22, 2002; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority” in Subsec. (a), effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-49f. Verification of Social Security number prior to opening new account. Minor not liable for services fraudulently obtained using minor's Social Security number. (a) A public service company, as defined in section 16-1, that requires the disclosure of a potential customer's Social Security number in order to open a new customer account shall verify the validity of the Social Security number prior to opening a new customer account to ensure that such number does not belong to a minor, as defined in section 1-1d. Such public service company shall cross reference the Social Security number provided with such customer's legal name, aliases, date of birth, age, current address and phone number. A public service company may use a third-party company to carry out the purpose of this subsection.
(b) A minor shall not be liable for payment of an unpaid bill to a public service company for services fraudulently obtained by an adult using such minor's Social Security number.
(June Sp. Sess. P.A. 15-5, S. 56.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-50. Employees. Consultants. Section 16-50 is repealed.
(1949 Rev., S. 5396; June, 1955, S. 2608d; P.A. 75-486, S. 1, 69; P.A. 77-367; 77-614, S. 162, 587, 610; P.A. 82-150, S. 9.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-50a. Local filing of maps on acquisition of property. Any public service company which acquires land or any easement or right-of-way therein for any of its purposes shall, if it has prepared a map or maps in connection with such acquisition, file, in the clerk's office in each town in which such land is located, a copy of such map or maps and said clerk shall accept such copy or copies for filing. Maps filed as required by this section shall conform to the provisions of section 7-31 as to materials and size.
(1963, P.A. 457; 1967, P.A. 226.)
History: 1967 act qualified exemption from Sec. 7-31 for maps by requiring conformity “as to materials and size”.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-50b. Declaration of policy. It is found and declared that conservation of undeveloped lands and preservation of open spaces, together with orderly control and development of remaining natural resources is the settled public policy of Connecticut and bears a substantial relationship to the public health and safety and common welfare, in order to provide for establishment and maintenance of necessary public recreational and conservation areas, and that undeveloped lands owned by public service companies constitute a significant portion of all remaining undeveloped lands in Connecticut, and particularly in thickly-settled areas of Connecticut, and that the state and municipalities, wherein substantial undeveloped tracts owned by public service companies are located, have been unable to provide for acquisition of such lands for public recreational and conservation purposes, and that the public policy of Connecticut to preserve open spaces requires for its effectiveness a procedure for the state and municipalities to determine whether acquisition of such tracts as may be or become available would be in furtherance and continuation of local, regional and state programs, and that public service companies by reason of their statutory privilege of land acquisition by condemnation and statutory protection of acquisition of their land by condemnation are a proper subject for a special statutory procedure for the disposition of undeveloped lands owned by such companies, and that it is further found and declared that sections 16-50b to 16-50e, inclusive, do not interfere with the operation and conduct of said public service companies.
(1967, P.A. 577, S. 1; 1972, P.A. 189, S. 1.)
History: 1972 act included reference to state's role in land acquisition and to state programs.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-50c. Notification of intent to dispose of unimproved real property. Approval or disapproval by authority. Hearing. (a) Whenever any public service company, as defined in section 16-1, except a water company, owning any contiguous area of unimproved real property containing three acres or more, intends to sell, lease or otherwise dispose of such land, or a portion thereof, except to the state, the United States or a municipality, such company shall first notify in writing, by certified mail, return receipt requested, the Public Utilities Regulatory Authority, the Commissioner of Public Health, the Commissioner of Energy and Environmental Protection and the chief executive officer or officers of the municipality in which such land is situated, of such intention to sell, lease or otherwise dispose of such land, and no agreement to sell, lease or otherwise dispose of such land may be entered into by such public service company except as provided in this section. The authority shall approve or disapprove the disposition of such unimproved property pursuant to subsection (a) of section 16-43, not more than one hundred fifty days after said authority has received notice pursuant to this section and failure to take action within such period shall be deemed to constitute approval. The authority shall hold a hearing on all such land transactions in which the acquisition cost of the parcels involved or the transfer consideration is in excess of fifty thousand dollars. The hearing shall be held in the municipality where such land is located. If such land is located in more than one municipality, the authority shall determine in which municipality the hearing shall be held. If the hearing is scheduled for more than one day or continues for more than one day, the authority may reconvene the hearing at the offices of the authority. The municipality in which such land is situated shall be a party to all proceedings before the authority involving such land brought pursuant to sections 16-50b to 16-50e, inclusive. The Public Utilities Regulatory Authority may, by order, exempt from the provisions of this subsection and sections 16-50d and 16-50e any sale, lease, transfer or other disposition of land by a public service company, other than a water company, to another public service company if such sale, lease, transfer or other disposition of land is related to a plan of divestiture or other corporate reorganization approved by the authority.
(b) On or before January 1, 1998, and on or before January first of each year thereafter, any private, nonprofit land-holding organization may provide in writing to the Public Utilities Regulatory Authority its mailing address and a list of the municipalities in this state in which such organization may own land or any municipality adjacent to such municipalities which address is suitable for the purpose of receiving notice of the sale, lease or other disposition of water company land as provided in this section. On or before February 1, 1998, and on or before February first of each year thereafter, said authority shall publish and make available to every water company, as defined in section 16-1, a list setting forth for the Nature Conservancy, the Trust for Public Land, the Land Trust Service Bureau and each private, nonprofit land-holding organization which has provided such information, such organization's mailing address and the municipalities in which such organization may own land and the adjacent municipalities. Such list shall be valid until January thirty-first of the following calendar year. Information contained on such list shall be carried forward on each succeeding year's list unless a change in such information, or the discontinuation of such information on such list, is requested by the entity which submitted it and any changes in, or discontinuation of, information to be incorporated in the following year's list shall be submitted to the Public Utilities Regulatory Authority on or before January first for inclusion on the list to be published on February first. Whenever, one hundred twenty days after July 1, 1998, any water company, as defined in section 16-1, owning any contiguous area of real property containing three acres or more, intends to sell, lease or otherwise dispose of such land, or a portion thereof, such company shall, not later than ninety days prior to offering such land for sale or otherwise negotiating with or notifying any other potential purchaser, or any agent of a potential purchaser, (1) notify in writing, by certified mail, return receipt requested, the Public Utilities Regulatory Authority, the Commissioner of Public Health, the Commissioner of Energy and Environmental Protection, any water company, as defined in section 25-32a, with an existing or potential source of supply or service area in any municipality in which such land is situated, any water company, as defined in said section 25-32a, with an existing or potential source of supply or service area in a contiguous municipality, the chief executive officer or officers of the municipality in which such land is situated, the Nature Conservancy, the Trust for Public Land, the Land Trust Service Bureau and any private, nonprofit land-holding organization set forth on the list published annually by the Public Utilities Regulatory Authority pursuant to this section which organization has indicated to the authority that it may own land in the municipality in which the land is located or in an adjacent municipality provided such notice shall inform recipients of information pertaining to the acreage and location of the land to be sold, leased, or otherwise disposed of and such notice shall state that additional information, including a map of the property, is available at the company and further provided, for any application submitted to the Public Utilities Regulatory Authority for disposition of such land within two years after such ninety-day period, no further notice shall be required, and (2) provide further public notice by causing a notice to be published in a newspaper of general circulation in the municipalities where such water company land is situated not more than forty-five days or less than thirty days before and not more than thirty days after filing an application for approval with the authority of such intention to sell, lease or otherwise dispose of such land. Such public notice shall be published in a display form that shall serve substantially to notify the public of the availability of the property and shall be published in print no smaller than ten-point type size. If a recipient of notice under this subsection enters into a contract to purchase such land, the closing on the sale shall take place not later than twelve months after the contract is entered into unless the period for closing is extended by mutual agreement of the parties to the contract. No agreement to sell, lease or otherwise dispose of such land may be entered into by such water company except as provided in this section. Any private, nonprofit land-holding organization which is considering acquiring the interest in the land which the water company intends to sell, lease or dispose of must identify itself as a potential acquirer by giving written notice to the Public Utilities Regulatory Authority and to the water company by certified mail, return receipt requested, not more than ninety days after the water company files an application for approval. The authority shall approve or disapprove the disposition of such property pursuant to subsection (a) of section 16-43 not more than one hundred fifty days after its receipt of an application for such sale, lease or other disposition pursuant to this subsection and failure to take action within such period shall be deemed to constitute approval. The authority shall hold a hearing on all such land transactions in which the acquisition cost of the parcels involved or the transfer consideration is in excess of fifty thousand dollars. The hearing shall be held in the municipality where such land is located. If such land is located in more than one municipality, the authority shall determine in which municipality the hearing shall be held. If the hearing is scheduled for more than one day or continues for more than one day, the authority may reconvene the hearing at the offices of the authority. An application shall not be filed with the authority until the Commissioner of Public Health issues a permit pursuant to section 25-32. The municipality in which such land is situated shall be a party to all proceedings before the authority involving such land brought pursuant to sections 16-50b to 16-50e, inclusive.
(c) If, by the end of the ninety-day period for written notice under subdivision (1) of subsection (b) of this section, no recipient of such notice has entered into an agreement or option to acquire the land, the water company may offer the land for sale, lease or other disposition to any person. Any such recipient of notice, upon entering into a contract which provides for an option to acquire such land, shall pay reasonable consideration for such option with due regard for the market value of the land. Such consideration shall be applied, without interest, as a credit against the purchase price if the option is exercised. Any such consideration shall not be refundable unless the authority disapproves the disposition of such land.
(1967, P.A. 577, S. 2; 1972, P.A. 189, S. 2; P.A. 74-256, S. 1, 4; P.A. 75-486, S. 17, 69; P.A. 77-614, S. 321, 610; P.A. 78-303, S. 132, 136; 78-378, S. 1, 2, 6; P.A. 80-482, S. 84, 348; P.A. 87-70, S. 1, 4; P.A. 88-354, S. 1; P.A. 89-261, S. 2; 89-301, S. 4; P.A. 90-221, S. 1, 15; P.A. 91-93, S. 1, 2; P.A. 93-381, S. 9, 39; P.A. 95-48, S. 2; 95-118, S. 1; 95-257, S. 12, 21, 58; P.A. 97-314, S. 2; P.A. 98-157, S. 8, 15; P.A. 99-225, S. 22, 33; P.A. 00-53, S. 3; P.A. 01-49, S. 6; P.A. 11-80, S. 1.)
History: 1972 act required notification of commissioner of environmental protection of intention to dispose of land; P.A. 74-256 required commission to approve or disapprove disposition of land within 150 days, else inaction deemed approval; P.A. 75-486 replaced public utilities commission with public utilities control authority, exempted from notice requirement dispositions of land to United States or to municipality and required hearing if land cost exceeds $20,000; P.A. 77-614 affirmed notification of public utilities control authority despite conflicting provision replacing authority with division of public utility control within the department of business regulation; P.A. 78-303 made technical corrections; P.A. 78-378 required notification of commissioner of health services; P.A. 80-482 made division of public utility control an independent department and deleted reference to abolished department of business regulation; P.A. 87-70 changed “parcel of unimproved real property” to “contiguous area of unimproved real property”, made a technical change in the reference to Sec. 16-43, and required that the municipality in which the real property is located be a party to all proceedings involving such property brought before the department of public utility control; P.A. 88-354 organized the section into Subsecs., amended Subsec. (a) to exempt water companies from provisions and added new Subsec. (b) regarding the sale of water company lands; P.A. 89-261 included provision in Subsecs. (a) and (b) re hearing in municipality where land is located; P.A. 89-301 amended Subsec. (b) by clarifying the time period for the notice required under Subdiv. (2); P.A. 90-221 in Subsec. (b) changed the date the department must approve or disapprove the sale, lease or other disposal of property from 150 days after the department's receipt of notice of the disposition to 150 days after the department's receipt of an application for sale, lease or other disposal; P.A. 91-93 added a provision allowing the department to exempt a sale, transfer or other disposition of land by a public service company if such disposition is related to a plan of divestiture; P.A. 93-381 replaced commissioner of health services with commissioner of public health and addiction services, effective July 1, 1993; P.A. 95-48 deleted “subdivision (1) of” in reference to Sec. 16-43; P.A. 95-118 amended Subsec. (b) by specifying form of notice published in newspapers and requiring private, nonprofit land-holding organization to identify itself as potential acquirer; P.A. 95-257 replaced Commissioner and Department of Public Health and Addiction Services with Commissioner and Department of Public Health, effective July 1, 1995; P.A. 97-314 amended Subsec. (b) to require notice of the sale of water company land to certain specified private, non-profit, land-holding organizations and other unspecified organizations; P.A. 98-157 amended Subsec. (a) to increase the hearing threshhold amount from $20,000 to $50,000, amended Subsec. (b) to add provisions re adjacent municipalities, requirements re list of organizations and 90-day time period, to revise provisions re notice, to add time requirement re closings, to increase the hearing threshold amount from $20,000 to $50,000, and to make technical changes, and added new Subsec. (c) to provide additional procedures for notice re disposition of unimproved real property, effective July 1, 1998; P.A. 99-225 amended Subsec. (b) to add provisions re certain information to be carried forward on the list required to be maintained by the Department of Public Utility Control re notice of water company land sales, effective June 29, 1999 (Revisor's note: At the end of Subsec. (b) “, inclusive” was added editorially by the Revisors following “... to sections 16-50b to 16-50e”, for consistency); P.A. 00-53 made a technical change in Subsec. (b); P.A. 01-49 amended Subsec. (b) to make technical changes; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, and “Commissioner of Environmental Protection” was changed editorially by the Revisors to “Commissioner of Energy and Environmental Protection”, effective July 1, 2011.
Cited. 3 CA 53.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-50d. Action to acquire property. (a) Within one hundred eighty days after approval by the Public Utilities Regulatory Authority of the sale, lease or other disposition of land owned by a public service company, except a water company, the recipient of a notice provided pursuant to subsection (a) of section 16-50c may give written notice to the authority and to the public service company by certified mail, return receipt requested, of a desire to acquire such land and each shall have the right to acquire the interest in the land which the public service company has declared its intent to sell, lease or otherwise dispose of, provided (1) the state's right to acquire the land shall be secondary to that of the municipality, and (2) the recipient has not waived its right to acquire such land as set forth in subsection (b) of this section. In the case of the sale, lease or other disposition of land owned by a water company, within one hundred days after approval by the Public Utilities Regulatory Authority, the recipient of a notice provided pursuant to subdivision (1) of subsection (b) of section 16-50c or any nonprofit land-holding organization which has identified itself as a potential acquirer pursuant to subdivision (2) of subsection (b) of section 16-50c may give written notice to the authority and to the water company by certified mail, return receipt requested, of a desire to acquire the interest in the land which the water company has declared its intent to sell, lease or otherwise dispose of, provided the recipient has not waived its right to acquire such land as set forth in subsection (b) of this section.
(b) If the recipients of a notice provided pursuant to subsection (a) or (b) of section 16-50c, or any nonprofit land-holding organization identified as a potential acquirer pursuant to subsection (b) of section 16-50c, fails to give notice, as provided in subsection (a) or (d) of this section, or give notice to the authority and to the public service company or water company by certified mail, return receipt requested, of a desire not to acquire such land, or if a nonprofit land-holding organization fails to identify itself as a potential acquirer pursuant to subsection (b) of section 16-50c, the right to acquire such land in accordance with the terms of sections 16-50b to 16-50e, inclusive, shall have been waived by such recipient or nonprofit land-holding organization.
(c) The written notice given by a municipality, the state, a water company or a nonprofit land-holding organization pursuant to subsection (a) or (d) of this section shall constitute acceptance of the terms, conditions and price set forth in the agreement approved by the authority in accordance with the provisions of subsection (a) of section 16-43 and section 16-50c. The municipality, state, water company or nonprofit land-holding organization shall thereafter acquire the interest in land which the public service company or water company has proposed to sell, lease or otherwise dispose of within fifteen months after such written notice has been given.
(d) (1) Within one hundred eighty days after such approval by the Public Utilities Regulatory Authority has been so given with respect to land owned by a public service company other than a water company, a chief executive officer or officers or the Commissioner of Energy and Environmental Protection exercising their rights under subsection (a) of this section may give written notice to the authority and to the public service company by certified mail, return receipt requested, of the municipality's or the state's intent to acquire such land by eminent domain and each shall have the right to acquire the land which the public service company has declared its intent to sell, lease or otherwise dispose of, provided the municipality or the state has not waived its right to acquire such land as set forth in subsection (b) of this section.
(2) Within one hundred days after such approval by the Public Utilities Regulatory Authority has been so given with respect to land owned by a water company, a chief executive officer or officers or the Commissioner of Energy and Environmental Protection exercising their rights under subsection (a) of this section may give written notice to the authority and to the water company by certified mail, return receipt requested, of the municipality's or the state's intent to acquire such land by eminent domain and, subject to the order of rights set forth in subsection (f) of this section to acquire water company land, each shall have the right to acquire the land which the water company has declared its intent to sell, lease or otherwise dispose of, provided the municipality or the state has not waived its right to acquire such land as set forth in subsection (b) of this section.
(3) The procedure for acquiring the land pursuant to this subsection shall be as follows: The Comptroller in the name of the state or the municipality shall proceed in the same manner specified for redevelopment agencies in accordance with sections 8-128 to 8-133, inclusive, provided, if such land is subject to the provisions of section 25-32, such land shall not be sold or condemned as herein provided without the approval of the Department of Public Health. The price, terms and conditions approved by the authority in accordance with the provisions of subsection (a) of section 16-43 and section 16-50c shall apply to any such procedure and shall not be changed without the approval of the authority in accordance with the provisions of subsection (a) of section 16-43.
(e) In no case shall any such land be sold or transferred to a corporation, ten per cent or more of the capital stock of which is owned or controlled by the stockholders of the public service company or water company, for a consideration less than the fair market value of the land. The provisions of this subsection shall not apply to transfers of land between public service companies or water companies.
(f) When more than one person gives notice of a desire to acquire a water company source or land, the right to acquire such source or land shall be in the following order: (1) A water company, as defined in section 25-32a, for water supply purposes; (2) a municipality in which the source or land is located for water supply, open space or recreational purposes; (3) the state for open space or recreational purposes; (4) a private, nonprofit land-holding organization for open space or recreational purposes; (5) a municipality for any public purpose, including, but not limited to, an educational use; and (6) the state for any public purpose. Any such source or land acquired for open space or recreational purposes shall have such restriction placed in the instrument intended as a conveyance recorded in the land records in the town where the source or land is situated. No source or land acquired pursuant to this section for open space or recreational purposes may be used for any other purpose unless the source or land has been reoffered for open space or recreational purposes pursuant to the provisions of this section and no notice of a desire to acquire such source or land has been given. The authority shall approve any such reoffering, provided there is compliance with this section. In any decision pursuant to this subsection, the authority shall act in concurrence with the Commissioner of Energy and Environmental Protection. Notwithstanding the provisions of subdivision (5) of this subsection, not more than fifteen per cent of the land acquired pursuant to this section may be used by a municipality for a use other than open space or recreational purposes without a reoffering. Any such other use shall be subject to the provisions of section 7-131n. As used in this subsection, “open space or recreational purposes” means use of lands for agriculture, parks, natural areas, forests, camping, fishing, wetlands preservation, wildlife habitat, reservoirs, hunting, golfing, boating, swimming and hiking, and “educational use” means the use by any town, city or borough, whether consolidated or unconsolidated, and any school district or regional school district, for the purposes of schools and related facilities.
(1967, P.A. 577, S. 3–6; 1972, P.A. 189, S. 3; June, 1972, P.A. 1, S. 21; P.A. 73-403; P.A. 74-256, S. 2–4; P.A. 75-405, S. 3–5; 75-486, S. 1, 69; P.A. 77-614, S. 162, 323, 610; P.A. 78-378, S. 3, 4, 6; P.A. 79-240; P.A. 80-482, S. 85, 348; P.A. 87-70, S. 2–4; P.A. 88-354, S. 2; P.A. 89-301, S. 5, 7; P.A. 93-381, S. 9, 39; P.A. 95-48, S. 3; 95-118, S. 2; 95-257, S. 12, 21, 58; P.A. 04-200, S. 5; P.A. 05-288, S. 218; P.A. 11-80, S. 1.)
History: 1972 acts added reference to notice by commissioner of environmental protection and provisions re state acquisition of land, added Subsec. (e) and stated that Subsec. (e) is applicable to “matters currently pending before the public utilities commission”; P.A. 73-403 changed required notice in Subsec. (a) from 45 to 60 days, required sale to take place within 90, rather than 60, days in Subsecs. (e) and (d) and made exemption in Subsec. (e) applicable to transfers between any public service companies, not just those controlled by same holding company; P.A. 74-256 changed notice requirement in Subsec. (a) to 90 days and amended Subsec. (c) to allow sale of land within 90 days after commission approval of land disposition; P.A. 75-405 replaced “such notice” in Subsec. (a) referring to notice in Sec. 16-50c with “such approval by the public utilities commission” and required sale within 18 months, rather than 90 days in Subsec. (c), deleting alternate requirement re sale within 90 days of commission approval altogether and added proviso re health department approval; P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced authority with division of public utility control within the department of business regulation and department of health with department of health services, effective January 1, 1979; P.A. 78-378 replaced Subsec. (c) which had referred to procedure for acquiring land when price disputed with reworded provisions stating that approved notice constitutes acceptance of terms, replaced Subsec. (d) which had required state or municipality to acquire land within 90 days after it has expressed intent to do so with provisions re preferential acquisition rights and acquisition procedure and deleted provisions in Subsec. (e) re offer of land or intent to sell land, after state or municipality fails to do so, upon different terms; P.A. 79-240 amended Subsec. (d) to require health services department approval for condemnation of land; P.A. 80-482 made division of public utility control an independent department and deleted reference to abolished department of business regulation; P.A. 87-70 changed the required notice period in Subsecs. (a) and (d) from 90 days to 180 days; P.A. 88-354 amended Subsec. (a) by adding specific provision re the sale, lease or other disposition of water company land, amended Subsecs. (b) to (e), inclusive, with technical changes and added Subsec. (f) regarding priorities for the acquisition of water company land; P.A. 89-301 amended Subsec. (b) by deleting incorrect reference to Subsec. (b) in provision re manner of notice and amended Subsec. (f)(2) by specifying that municipality is the municipality in which the land is located; P.A. 93-381 replaced department of health services with department of public health and addiction services, effective July 1, 1993; P.A. 95-48 amended Subsec. (c) by changing “(1)” to “(a)” in reference to Subsec. of Sec. 16-43 and made technical changes; P.A. 95-118 added provisions re waiving right to acquire land and organization identifying itself as potential acquirer, substituted “the recipient of a notice provided pursuant to subsection (a) of section 16-50c” for “such chief executive officers or the Commissioner of Environmental Protection” in Subsec. (a), in Subsec. (c) changed Subsec. reference from (b) to (d), divided Subsec. (d) into Subdivs., separated provision re water company land, and added provision re price, terms and conditions approved by the department; P.A. 95-257 replaced Commissioner and Department of Public Health and Addiction Services with Commissioner and Department of Public Health, effective July 1, 1995; P.A. 04-200 amended Subsec. (f) to apply to water company “source”, to add “water supply” in Subdiv. (2), to add “educational use” in Subdiv. (5), and to define “educational use”, effective June 3, 2004; P.A. 05-288 made technical changes in Subsec. (f), effective July 13, 2005; pursuant to P.A. 11-80, “Department of Public Utility Control” and “department” were changed editorially by the Revisors to “Public Utilities Regulatory Authority” and “authority”, respectively, and “Commissioner of Environmental Protection” was changed editorially by the Revisors to “Commissioner of Energy and Environmental Protection”, effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-50e. Notices to town clerk. A copy of each notice required by sections 16-50c and 16-50d shall be sent by the party giving such notice to the town clerk of the municipality in which the land is situated and such town clerk shall make all such notices part of the appropriate land records.
(1967, P.A. 577, S. 7.)
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
Sec. 16-50f. Solicitation of insurance applications from employees of public service companies. Payroll deductions. (a) Any public service company providing payroll deduction services for its employees for premiums on individual policies of any line of insurance shall permit solicitation of applications for such policies by any licensed insurer or representative of the insurer. Any such insurer or representative of the insurer who claims he has been denied the right to solicit applications for insurance by a public service company in violation of this section shall file a complaint in writing with the Insurance Commissioner who shall cause an investigation to be made, and if the commissioner determines that the public service company has violated this section, he shall so notify the Public Utilities Regulatory Authority which shall make such order as is necessary to carry out the provisions of this section. This section shall not be construed to invalidate, nor require any public service company to change, a program of payroll deductions for employees' individual insurance policies in existence on October 1, 1969.
(b) Notwithstanding the provisions of subsection (a) of this section, a public service company may provide payroll deductions for its employees in connection with premiums for a mass merchandising or group plan of any line of insurance, provided that the group covered by such insurance consists predominantly of employees of the public service company.
(1969, P.A. 210, S. 1, 2; 1971, P.A. 761; P.A. 75-486, S. 1, 69; P.A. 77-614, S. 162, 163, 610; P.A. 79-129; P.A. 80-482, S. 86, 348; P.A. 82-150, S. 8; P.A. 11-80, S. 1.)
History: 1971 act added Subsec. (b) re payroll deductions for group insurance; P.A. 75-486 replaced public utilities commission with public utilities control authority; P.A. 77-614 replaced authority with division of public utility control within the department of business regulation, made insurance department a division of that department and retained insurance commissioner as its head, effective January 1, 1979; P.A. 79-129 removed from Subsec. (b) provision prohibiting sale of insurance on company property during normal working hours; P.A. 80-482 made divisions of public utility control and insurance independent departments and deleted references to abolished department of business regulation; P.A. 82-150 made technical changes; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority” in Subsec. (a), effective July 1, 2011.
(Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |