OLR Research Report


October 10, 1997 97-R-1133

TO:

FROM: Judith Lohman, Principal Analyst

RE: Court Decisions on Project Labor Agreements

You asked why courts have allowed project labor agreements on large construction projects but not on small ones.

SUMMARY

A review of recent federal, New Jersey and New York court decisions on the legality of using project labor agreements (PLAs) in public construction projects (there are no Connecticut rulings on this issue) shows that PLAs are not ruled valid or invalid based exclusively on the project's size. But in deciding whether particular PLAs are permissible under state competitive bidding laws, New York and New Jersey courts have cited the size and complexity of the project involved as one element in their decisions.

PLAs are agreements negotiated between a construction project manager or general contractor and a coalition of building trades unions to govern the labor relations aspects of a particular project. They typically require use of union hiring halls; a uniform procedure for resolving labor disputes; comprehensive, long-term no-strike commitments; and agreement of all contractors and subcontractors to its terms. The last requirement is achieved by making agreement to the PLA a part of the project bid specifications.

The U.S. Supreme Court has ruled that the National Labor Relations Act (NLRA) does not bar use of PLAs on public construction projects. Project size does not appear to have been a factor in the Court's decision. In state cases over whether PLAs violate state competitive bidding laws, the New York Supreme Court ruled that they do not if (1) they contain provisions protecting nonunion contractors and employees and (2) the public contracting authority can show a rational basis for its decision to use a PLA. The size and complexity of the project was one element cited by the New York court in deciding whether there was the requisite rational basis. In a similar case, the New Jersey Supreme Court invalidated a PLA based in part on the fact that the project involved was neither large nor complex.

In a letter to the Connecticut education commissioner, the Connecticut attorney general, Richard Blumenthal, states that the competitive bidding requirements of Connecticut's school construction law neither condone nor prohibit local school boards from using PLAs in school construction projects. He therefore advises the State Board of Education to allow a local board of education to use a PLA, if it decides it would be in the public interest.

NLRA PREEMPTION: U.S. SUPREME COURT

The U.S. Supreme Court's 1993 decision on PLAs turned on whether NLRA preempts the enforcement by a state authority, acting as owner of a construction project, of an otherwise legal prehire collective bargaining agreement negotiated by private parties. The Court ruled that it did not.

The case concerned the Boston Harbor Project. The Massachusetts Water Resources Authority (MWRA), a public entity, was under a federal court order to clean up the harbor. To carry out the massive construction required, it selected Kaiser Engineers, Inc. as project manager. Kaiser negotiated a PLA with the local Building and Construction Trades Council (BCTC). Among other things the PLA:

1. recognized the BCTC as the exclusive bargaining representative for all craft employees on the project,

2. required a specific method to be used in resolving all labor disputes,

3. required all employees on the project to be subject to a union security provision requiring them to become union members within seven days of being hired,

4. required that the BCTC hiring hall be the primary method of supplying the craft labor force for the project,

5. contained a 10-year no-strike commitment, and

6. required all contractors and subcontractors to be bound by the agreement.

The last provision was enforced by making agreement to the PLA one of the project bid specifications.

A group of nonunion construction contractors sued on the grounds that the bid specification was preempted by the NLRA, among other claims. The federal appeals court ruled in their favor, finding that the bid specification was preempted because it would mean that MWRA was regulating activities that Congress intended to be unrestricted by government power.

On appeal, the Supreme Court overturned the lower court's decision. In his opinion on behalf of the unanimous Court, Justice Blackmun described the type of local regulation the NLRA preempts as articulated by previous Supreme Court rulings (the NLRA contains no express preemption clause).

1. The NLRA bars state and local regulation of activities protected by section 7 of the act the basic right of employees to bargain collectively and engage in concerted action for that purpose or for their mutual benefit and protection) or that constitute an unfair labor practice under section 8. Such regulations are preempted so as to prevent conflict between state and local regulation and the federal regulatory authority assigned to the National Labor Relations Board.

2. State and local regulation is also barred in areas the NLRA leaves to be controlled by the free play of economic forces.

These are the two “protected zones.” But, Blackmun wrote, when courts say the NLRA bars a state from regulating within a protected zone, that is not the same as saying it cannot operate there. A state does not regulate simply by acting. There is a distinction between government as regulator and government as proprietor or purchaser. When operating in the latter capacity, the government has the same rights as private entities.

Since the MWRA was acting as a purchaser and proprietor on the Boston Harbor project, it was not subject to the same preemption limitations. And since an agreement such as the Boston Harbor PLA would be legal between two private parties, the Court ruled it legal even though one of the parties was a government entity if the entity was acting in the same capacity as any other proprietor or purchaser. (Building & Construction Trades Council v. Associated Builders & Contractors, Inc., 113 S. Ct. 1190 (1993)).

STATE COMPETITIVE BIDDING LAWS

New York

In two 1994 decisions, the New York Supreme Court ruled that PLAs do not violate the state's competitive bidding law. The court found that those laws neither require nor prohibit such agreements and that they are permitted when they have a rational relationship with the public interest. The rational relationship must be demonstrated by the public authority's investigation, analysis, and justification.

One case involved a PLA covering the New York Thruway Authority's refurbishment of the Tappan Zee Bridge and the other involved one covering the Dormitory Authority of New York's project at the state Health Department's Roswell Park Cancer Institute. Both PLAs contained (1) uniform procedures for dealing with all labor disputes; (2) a comprehensive no-strike clause; (3) a standard work week; (4) permission for flexible scheduling; (5) requirements that employees be hired through union hiring halls, except that contractors could retain up to 12% of their existing workforce; (6) provisions barring union halls from discriminating on the basis of union membership; and (7) no requirement that employees join union, although they had to pay a sum equal to union dues.

Both rulings were issued in 1994. The Thruway Authority ruling was issued first and thus contained a more detailed discussion of the court's reasoning. The court decided that, in looking at a PLA, the public authority and the court must consider the public interest promoted by the competitive bidding law: “that of obtaining the best work at the lowest possible price while guarding against favoritism, improvidence, extravagance, fraud and corruption.” The court concluded that the Thruway Authority's decision to use a PLA on the Tappan Zee Bridge project “is rationally based” on those interests.

In support of its conclusion, the court noted that the project was the largest and most complex repair undertaken since the bridge was originally constructed. It also cited the fact that, in 23 previous major construction projects on the bridge, union contractors had been successful bidders on 20. The authority also had reason to be concerned that the 19 different unions working on the job, with their differing contracts, jurisdictions, and contract expiration dates, might cause delays and higher administrative overhead in the absence of a global PLA.

In rejecting the allegation that the PLA was anti-competitive, the court cited the fact that it did not have the effect of barring nonunion contractors from bidding, nor did it require all employees on the project to be union members. Discrimination against nonunion employees was expressly barred in the hiring hall referral process and contractors were permitted to retain up to 12% of their existing employees. (New York State Chapter, Inc., Associated Contractors of America, et. al. v. New York State Dormitory Authority, et. al., 620 N.Y.S. 2d. 855 (1994)).

The court decision on the Dormitory Authority PLA was the same (New York State Chapter, Inc., Associated Contractors of America, et. al. v. New York State Dormitory Authority, et. al., No. 71912, Dec. 22, 1994).

New Jersey

The New Jersey Supreme Court ruled in two cases that PLAs violated that state's competitive bidding laws. In one case, the Court cited the size of the project as a factor in its decision.

In George Harms Construction Co. v. New Jersey Turnpike Authority (137 N. J. 8 (1994)), the court invalidated a PLA because it designated a particular labor organization as the sole source of labor for a public construction project.

In Tormee Construction, Inc., et. al. v. Mercer County Improvement Authority (41 Construction Labor Reports 1368), the court invalidated a PLA for a county library building project. The court pointed out that the project was not large or complicated, that the PLA in question did not permit contractors to hire a stated percentage of their nonunion employees, and that it did not bind the appropriate labor unions or assure coordination among them. In addition, the PLA covered only two unions rather than all the unions involved in the project. Finally, the court found that the PLA did not satisfy the governor's executive policy that, before a PLA may be used in a public project in New Jersey, it must be determined that it will “promote labor stability and advance the state's interest in cost, efficiency, quality, safety and/or timeliness.”

Connecticut – Attorney General's Letter

In a letter dated April 7, 1997 (copy enclosed), Attorney General Richard Blumenthal advised the education commissioner that the school construction law requiring school construction contracts to be awarded to the lowest responsible qualified bidder do not bar use of PLAs. The attorney general stated that no Connecticut court has ruled on the issue of whether PLAs violate competitive bidding laws. But he cited the New York Thruway ruling in describing the rationale underlying the Connecticut competitive bidding law. The attorney general's advice was that the State Board of Education let a local school board decide whether to bind contractors to a PLA, as long as the local board can justify the requirement in terms of the public interest.