Connecticut Seal

Senate Bill No. 653

Public Act No. 05-38

AN ACT INCREASING THE CONTRACT AMOUNT FOR WHICH A MUNICIPALITY MUST RECEIVE A BOND ON A CONSTRUCTION OR PUBLIC WORKS PROJECT.

Be it enacted by the Senate and House of Representatives in General Assembly convened:

Section 1. Section 49-41 of the general statutes is repealed and the following is substituted in lieu thereof (Effective October 1, 2005):

(a) Each contract exceeding [fifty] one hundred thousand dollars in amount for the construction, alteration or repair of any public building or public work of the state or of any subdivision thereof shall include a provision that the person to perform the contract shall furnish to the state or the subdivision on or before the award date, a bond in the amount of the contract which shall be binding upon the award of the contract to that person, with a surety or sureties satisfactory to the officer awarding the contract, for the protection of persons supplying labor or materials in the prosecution of the work provided for in the contract for the use of each such person, provided no such bond shall be required to be furnished (1) in relation to any general bid in which the total estimated cost of labor and materials under the contract with respect to which such general bid is submitted is less than fifty thousand dollars, (2) in relation to any sub-bid in which the total estimated cost of labor and materials under the contract with respect to which such sub-bid is submitted is less than fifty thousand dollars, or (3) in relation to any general bid or sub-bid submitted by a consultant, as defined in section 4b-55. Any such bond furnished shall have as principal the name of the person awarded the contract.

(b) Nothing in this section or sections 49-41a to 49-43, inclusive, shall be construed to limit the authority of any contracting officer to require a performance bond or other security in addition to the bond referred to in subsection (a) of this section, except that no such officer shall require a performance bond in relation to any general bid in which the total estimated cost of labor and materials under the contract with respect to which such general bid is submitted is less than twenty-five thousand dollars or in relation to any sub-bid in which the total estimated cost of labor and materials under the contract with respect to which such sub-bid is submitted is less than fifty thousand dollars.

(c) No contract for the construction, alteration or repair of any public building or public work of the state or of any subdivision thereof that requires a person to supply the state or subdivision with a bond may include a provision that requires the person to obtain the bond from a specific surety, agent, broker or producer. No contracting officer may require that a bond be obtained from a specific surety, agent, broker or producer.

Approved May 17, 2005