Introduction

UConn 2000 Construction Management

The University of Connecticut (UConn) was granted statutory authority to carry out a 10-year, one billion dollar infrastructure improvement program known as UConn 2000 in 1995. During the summer of 2001, several incidents related to wage violations and worker safety occurred at UConn 2000 project sites that prompted legislative interest in how the university carries out its construction management responsibilities for the program.

In March 2002, the program review committee initiated a study to examine the university's performance in managing the construction phase of UConn 2000 projects. The study focused on how UConn oversees contractor compliance in three main areas:

The study scope adopted by the committee did not include the pre-award part of the UConn 2000 capital project process so university financing practices, design activities, and most bidding and contracting procedures were not evaluated. The review did examine the university's bidder prequalification criteria and procedures because of the relationship between successful construction management and effective screening and monitoring of contractor performance.

Methods

A variety of sources and methods were used to gather information for the UConn 2000 construction management study. Relevant statutes, regulations, agency policies and written procedures were reviewed along with university status reports, plans, audits, and consultant studies concerning the UConn 2000 program. Committee staff conducted interviews with key university personnel, members of the UConn board of trustees, representatives of various building trades organizations including unions and contractor associations, officers and employees of contractors and subcontractors working on UConn 2000 projects, staff from the state labor department, the offices of the state building inspector and the state fire marshal, and several construction management industry experts. A public hearing to elicit information about UConn 2000 construction management issues was held by the program review committee in November 2002.

Committee staff examined actual construction management practices by attending job meetings, visiting work sites, and reviewing project documents for 12 of the 25 projects active in the summer and fall of 2002. All minutes from job meetings for a sample of recently completed major UConn 2000 projects were also reviewed. Committee staff observed construction field visits conducted by UConn project managers, wage compliance inspections by state Department of Labor (DOL) staff, and on-site safety inspections by the university insurance administrator's work safety manager.

The university's automated information system for all construction projects was used by committee staff to develop a database of descriptive and performance information on each major UConn 2000 project. Data on budgets, schedules and change orders for completed and in-progress projects were analyzed by project size, type, and contractor. Basic cost, completion time, and contractor information for all minor projects was also examined. To develop information about outcomes of the UConn 2000 contractor prequalification process, files from a sample of the projects prequalifed over the past three fiscal years were reviewed in detail.

A listing of contractors and subcontractors that worked on UConn 2000 projects was compiled from several sources including university insurance records and state tax department reports. Committee staff created a database on prevailing wage complaints related to UConn 2000 projects from a state Department of Labor information system and that department's case files. A similar database on federal Occupational Safety and Health Act (OSHA) cases concerning UConn 2000 projects was developed from information supplied to committee staff by OSHA regional offices. Information on UConn 2000 work-site injuries and accidents was also developed from insurance claim data supplied by the administrator of the university's owner controlled insurance program.

Report Organization

The first chapter of the report presents background information on the UConn 2000 program and an overview of general construction management methods and practices. The university's construction management process and overall performance in terms of keeping construction work on schedule, within budget, and in conformance with work quality standards is discussed in Chaper Two. Chapters Three and Four describe, respectively, state employment laws and worker safety and health requirements and the extent of contractor compliance on UConn 2000 projects. Chapters Two through Four also contain program review committee findings about the effectiveness of the university's policies and procedures for managing UConn 2000 capital projects and recommendations aimed at improving university oversight. The final chapter of the report presents committee findings related to labor relations issues and the university's construction program.

It is the policy of the Legislative Program Review and Investigations Committee to provide agencies included in the scope of a review with the opportunity to comment on committee findings and recommendations before the a final report is published. A written response to this report was solicited from the University of Connecticut. The response submitted by the university is presented in Appendix A.

Chapter One

Background and Overview

UConn 2000 is a special $1 billion capital improvement program for the University of Connecticut created by the legislature in 1995 under Public Act 95-230. The act gives the university the ability to independently finance and manage, over a 10-year period, two phases of projects that include new construction, renovation work, deferred maintenance, and equipment replacement and upgrades at its main and regional campuses.

The university, acting as owner, is responsible for managing, prioritizing, and sequencing all UConn 2000 projects. It is permitted to contract with design professionals, general contractors and one or more prime trade contractors for construction work, and may hire outside professionals to supervise construction projects. The UConn 2000 law requires the university to establish detailed plans, specifications, and construction standards for each project and to comply with all laws regarding state public works projects (e.g., wages and hours, occupational safety and health, contractor disqualification).

The statutes further establish a public bidding process for the UConn 2000 construction contracts that includes a prequalification component. For each contract, the university must:

_ objective written criteria;

_ ability and integrity; and

_ past experience with similar projects;

UConn is allowed to waive a minor irregularity in a bid, reject all bids and readvertise the project, or interview at least three responsible qualified bidders and negotiate a contract that is fair and reasonable with any one of them. By law, it must require bonds, deposits, and security for awarded contracts, withhold payment until bills and estimates are certified correct, and limit payments to the contract amount.

The UConn 2000 law requires the university to submit semiannual (October and April) status and progress reports to the governor and the education, finance, and appropriations committees of the General Assembly. The reports must include information on:

Each report must provide detailed financial information (e.g., investment earnings, principal and interest payments) for the preceding six-month period and note any actions involving project revisions, additions, deletions, and cost revisions or reallocations. Since 2000, the semiannual reports also must include information on the use of Connecticut-owned businesses including businesses owned by women and minorities.

The program's enabling legislation required the university to submit a four-year performance review to the legislature's education and finance committees in January 1999 that:

The law mandated that the committees, after considering the report, determine whether there had been insufficient progress or significant cost increases, and if so, make recommendations for appropriate action to the full General Assembly. The four-year report was submitted by UConn as required and no significant changes to the program were found necessary by the legislature.

In August 2002, the General Assembly enacted legislation establishing the UConn 21st Century program (P.A. 02-3, May 9 SS). The act added another $1 billion for a third phase of capital improvements over 10 years on the main and regional campuses and increases the funding level for the earlier phases of UConn 2000. It also changed some project bidding and approval procedures and revised revises certain reporting requirements. For example, effective July 1, 2002, UConn is required to:

Construction Management

New construction and renovation projects like those included in the UConn 2000 program can be large in scope and size, expensive, complex, and dynamic. The satisfactory completion of such projects requires effective construction management. Construction management refers to the many activities undertaken throughout the building process to control project schedules, budgets, and work quality. The factors an owner should consider to ensure the success of a major construction project are highlighted below.

 

Key Considerations

Budget

  • Determine a realistic budget to evaluate project feasibility and select design and site location.
  • Identify the source of financing.
  • Avoid excessive cost overruns.

Design

  • Ensure the facility functions as envisioned and meets needs of owner and users.
  • Provide documents and plans that are constructible, complete, and coordinated.
  • Ensure design incorporates subsurface conditions, interfaces with adjoining properties, access, and other characteristics.

Risk Assessment

  • Issue of risk closely tied to schedule, budget, and design.
  • Carefully allocate risk among participants with direct control over certain areas.

Owner's Level

of Expertise

  • Familiarity with building process and level of in-house management capabilities will influence amount of outside assistance required.
  • Owner's expertise and experience may determine the project delivery system.

Outside construction management services. Few owners, especially governmental agencies, have the proficiency or staff resources necessary to carry out all construction management responsibilities for complex capital projects. Professional construction management firms can be hired to act as an owner's representative during a building project, performing a range of services to control time, cost, and quality. A firm acting in this capacity is referred to as an agency construction manager (ACM) or contract administrator (CA).

One of the main advantages to agency construction management is the objectivity of the professional advice provided; the ACM or CA has no vested interest in the project's design or construction. Services typically offered include:

Design

  • Selection of design team
  • Budget and cost estimating
  • Constructability review of design
  • Value engineering
  • Contract bidding

Construction

  • Inspection and surveillance
  • Project controls
  • Change order review
  • Project close-out

The most frequently cited criticism is an ACM or CA adds a level of bureaucracy to a project, resulting in increased cost. However, it can be argued the services provided may actually reduce overall expenditures by promptly identifying problems and implementing corrective actions.

Project delivery methods. Construction projects can be delivered (designed and constructed) through a variety of methods. Owners must consider their own construction experience, the capabilities of in-house staff, and type of facility when selecting a project delivery method. Three common methods, all of which have been used for UConn 2000 projects, are described briefly below. A summary of the pros and cons of each of the three project delivery methods follows the descriptions.

Design-Bid-Build. For many years, most construction projects were delivered through the traditional design-bid-build process. An owner hires a design professional (e.g., architect, engineer) to develop complete plans and specifications, which are used to solicit fixed-price bids (hard bids) from general contractors (GCs) for actual construction of the project. In many cases, the general contractor submitting the lowest responsive bid is selected to perform construction. Under this method:

Design-Build. Design-build (D-B) is an alternative project delivery method developed to address certain weaknesses of the design-bid-build process. Under this method, an owner contracts with a design-build team, usually a joint venture of a general contractor and design professional, to completely design and construct a facility. At a point early in the design process, the owner and the design-builder negotiate a fixed price for the total project and all services.

Construction Manager At-Risk. This system is a hybrid of a construction manager and traditional design-bid-build method. The owner hires a CM to provide advice and assistance on the schedule, budget, constructability and related issues during the project planning phase and to act as the general contractor during construction phase. Under this method, the CM assumes the risk of subletting work to trade subcontractors and guaranteeing completion of the project for a fixed, negotiated price following completion of the design. Work also can be "fast tracked." Construction may begin prior to completion of the design and work can be bid and subcontracted in phases throughout process. A unique aspect of this method is the owner and CM at-risk negotiate a guaranteed maximum price for project.

 

Pros

Cons

Design-

Bid-Build

  • Widely applicable & well understood
  • Clearly defined roles for all parties
  • Significant owner control
  • Design completed prior to selection of GC permitting hard bid
  • Design process time consuming
  • Limited ability to assess scheduling & cost can lead to increased costs
  • Possible adversarial relationship between owner, GC, & designer
  • Increased potential for construction claims
  • GC interest in protecting profit requires thorough monitoring by owner
  • Lack of GC input in design can result in constructability issues

Design-Build

  • One party (D-B team) responsible for design & construction of project
  • D-B firm internal issues do not concern owner
  • Construction can start before design complete; ability to "fast track" phases
  • Saves time & can save money
  • Loss of owner control & involvement
  • Initial scope & preliminary design (which forms basis for contract) must be complete & accurate
  • Owner may require additional consultants for oversight
  • Best suited to conventional buildings (e.g., student housing, parking garage) not specialized facilities (e.g., high tech classrooms, science labs)
  • Good D-B team needs balance of design expertise, financial capability, construction experience, & design-build experience

CM

At-Risk

  • Owner controls design with input from CM; partnership approach
  • Construction can start before design complete; ability to "fast track" phases
  • GC perspective & input in planning & design; value engineering during construction to control costs
  • Guaranteed maximum price
  • Loss of owner control & involvement
  • CM/GC converts from advisory role of CM to contractual role of GC; may lead to more adversarial relationship with owner (over quality, schedule, budget)
  • Possible tension between designers and CM (over constructibility, cost estimates)
  • Disputes possible over anticipated design features at time price negotiated

Contractors. The construction management process requires coordination of all parties involved in large building projects, including each level of contractors, from the general (or construction manager) to the primes, subcontractors, and in some cases, independent contractors. As outlined below, each tier of contractors has a different scope of responsibility for a construction project, but they all have a strong interest in providing owners with quality work on time and on budget.

 

Responsibilities

General Contractor/

Construction Manager

  • Direct control of job site and construction; meeting scheduling requirements; purchasing materials and equipment; contracting for trade subcontractors; and ensuring quality of work performed and conformance with all contract provisions. Typically GCs/CMs perform little or no trade work on the job site.

Prime Subcontractor

  • Employed by CM/GC to perform major trade work phases of construction process such as site preparation, demolition, framing, electrical, plumbing, roofing, mechanical, and painting.

Subcontractor

  • Employed by a prime subcontractor to perform specific task or aspect of trade work such as insulation, sheetrock and taping, and landscaping.

Independent Contractor

  • May be hired by subcontractor to perform specific task (e.g., installation of carpet or furniture) in lieu of or in addition to the subcontractor's employees.

Chapter Two

UConn 2000 Construction Management

Under the 1995 UConn 2000 law, the university has broad authority to independently finance and carry out capital improvement projects at its main and regional campuses. The only statutory requirements for the construction process are that UConn prequalify contractors and award contracts to the responsible qualified bidder submitting the lowest bid in conformance with the university's standards for the project.

The structure and process established by the university to implement its construction management authority is described in this section. Information on current roles and responsibilities, key construction management activities and the scope and status of the UConn 2000 program is presented along with program review committee findings concerning project time, cost, and quality outcomes and recommendations to improve performance in these areas.

Roles and Responsibilities

Ultimate authority for decisions related to all capital projects including the UConn 2000 program rests with the university's Board of Trustees. The board must approve individual projects and any material revisions to them, the annual capital budget for the university, and any project cost revisions or reallocations.

The Division of Business and Administration has primary management responsibility for all capital projects including the UConn 2000 program at the university's main and regional campuses, extension service sites, and the law school campus in Hartford. As Figure 1 shows, the division is headed by a vice chancellor who reports to the chancellor, the university's chief operating officer, and to the president, the university's chief executive officer

The Office of Architectural and Engineering (A/E) Services within the business and administration division carries out all day-to-day design and construction activities related to UConn 2000 and other university capital projects. The professional staff of the A/E Services office includes 11 architects and engineers, who perform design, review, and project management functions and five construction engineers, individuals with industry experience personnel (e.g., former field inspectors or job superintendents), who generally oversee the construction phase of smaller, shorter term projects

To supplement its in-house resources for managing major UConn 2000 projects, the university hired an outside firm, Bechtel/Fusco (B/F), as a construction administrator in December 1996. As Figure 1 indicates, Bechtel personnel are considered part of the A/E Services operational staff and report to the office's director of design, planning, and construction management. At present, there are five B/F construction project managers/construction administrators and one support staff person working full-time for the university.

Other outside professional services are engaged by A/E Services as needed to perform a variety of construction-related functions (e.g., design, plan review, legal review, inspection and testing) depending on the size, scope, and complexity of projects. In combination, the in-house and hired resources provide the wide range of expertise needed for effective construction management

All payment and budget functions related to the university's capital projects and to facility operations are taken care of by the offices' facilities administrative services staff. They also handle any associated information technology functions such as operation of the UConn 2000 project tracking system, Capstat, and several other automated databases. The Capstat system, which was developed by the facilities administrative services director, is primarily a financial tracking system but can produce a variety of monitoring reports (e.g., project status, payments in total and by major category, change order summaries).

Another office of the business and administration division, capital project and contract administration, provides support for procurement functions related to UConn 2000 and other capital projects. When outside designers, contractors, or other types of professional services are required for a construction project, the procurement staff carry out the contracting process from advertising to finalizing legal documents. They also are responsible for UConn 2000 contractor prequalification process, described in greater detail later in the report.

Key Activities

The university's construction management process for UConn 2000 and other capital projects incorporates standard industry practices for controlling schedules, budgets, and quality. Key activities carried out by the A/E Services in-house staff and outside professionals are highlighted below. The role of the state building inspector and state fire marshal in monitoring compliance with code requirements on "threshold" projects is also noted. 1

General Oversight

  • For small, shorter term projects (e.g., simple renovations or additions and routine repairs), the five in-house professional designers from the A/E Services Office perform architectural and engineering tasks and the office's five in-house construction engineers monitor the construction phase.
  • For large or very complex projects -- generally those with estimated budgets over $10 million -- outside designers are hired to complete plans and specifications while the four in-house project managers (PMs) coordinate design development and oversee the entire construction phase with assistance of Bechtel/Fusco staff.

Daily Monitoring

  • Day-to-day responsibility for keeping projects on time, on budget, and in compliance with contract provisions rests with the A/E Services in-house construction engineers and B/F construction administrators who are responsible for:

    _ on-site monitoring (e.g., daily visits, weekly progress meeting, periodic inspections);

    _ initial processing of contractor payments;

    _ reviewing and making recommendations on contract changes (e.g., change orders, schedule revisions); and

    _ maintaining project documentation (e.g., correspondence files, payment records, testing and other reports, photographs or videos of key activities).

Code Compliance

  • One A/E Services staff person acts as the university's code compliance officer and checks aspects of work quality of all projects prior to authorizing occupancy. By statute, threshold projects are additionally subject to inspection and approval by the state building inspector and the state fire marshal. To date, 12 UConn 2000 projects have come under the state threshold process.

Contracting/

Prequalification

  • Procurement staff from the division's capital project and contract administration office carry out the contract process for all university construction projects from advertising through finalizing legal documents. Their duties include prequalifying bidders for UConn 2000 projects.

Overall, the policies and procedures employed by the university compare well with construction management models outlined in the literature and by experts interviewed by program review committee staff. As discussed earlier, the university also uses a variety of project delivery methods depending on the size, type, and scope of the construction work.

Like many public and private owners, UConn has moved from the traditional general contractor approach to the construction manager at-risk method for large, complex building projects. The construction manager approach is generally believed to offer more owner control over costs and time and result in a more collaborative work relationship that can reduce change orders and claims.

Project status and outcome measures from the Capstat system and other sources are continuously monitored by A/E Services staff and university managers to check policies and procedures for controlling time, budget and quality are working as intended. Staff periodically meet to discuss completed projects and identify what went well and where problems occurred so corrective measures can be developed for future work.

The board of trustees receives status reports on UConn 2000 projects at every meeting. These reports and other project information are reviewed in detail by the board's financial affairs subcommittee. During the initial phase of the program, the board engaged a consultant to perform a program and financial audit both to determine compliance and assess university management. The final audit report issued in 1999 basically found the UConn 2000 program to be successful and in compliance with legislative requirements and board policies. It also recommended changes to improve a number of construction management and administrative procedures, many of which have been implemented. In interviews with committee staff, board members reported they continue to be satisfied current practices are accomplishing the program's intent and it is being administered in a professional and responsible manner.

As required by statute, the university provides the governor and legislature with reports on the UConn 2000 program's status and progress every six months and submitted a four-year performance review of the program in January 1999. No major program modifications have been made by the General Assembly in response to these reports, indicating general satisfaction with the university's performance. In fact, legislation was recently enacted (the 2002 UConn 21st Century law) to add funding and extend the university authority for capital improvements for another 10 years.

Based on its examination of the university's process for managing the construction phase of its UConn 2000 projects and a review of model construction management practices, the committee made the following findings.

The university process incorporates industry best practices for controlling costs, schedule, and quality. Necessary expertise and resources are provided by a small in-house staff that is augmented with a variety of outside professional services as needed including a full-time construction administrator for major UConn 2000 projects. The university management periodically reassesses construction-related policies and procedures to identify and implement changes to improve performance and outcomes are regularly monitored by the board of trustees and the legislature.

Contractor Prequalification

Although part of the pre-award phase, contractor prequalification can contribute to effective management of construction projects by ensuring the companies bidding on a job are responsible and have the resources and experience necessary for that particular project. A good prequalification process with clearly defined, relevant criteria that are consistently applied also promotes self selection by contractors, who recognize they will only be seriously considered for projects when their qualifications meet stated requirements.

The university is required by law to use a bidder prequalification process in awarding contracts for UConn 2000 projects. The statutes further require contracts be awarded to the responsible qualified bidder submitting the lowest bid in conformance with the university's standards for the project.

Only contractors deemed qualified based on the following statutory criteria are invited to bid on UConn 2000 projects:

Effective July 1, 2002, under the UConn 21st Century legislation, the university must also specifically consider labor law compliance by contractors and their subcontractors during the prequalification process. The university has revised its contracts and other documents and modified its prequalification procedures to incorporate this provision.

The university requires contractors to submit applications for prequalification that include:

An evaluation committee consisting of A/E Services staff (i.e., the project manager assigned to the project, the director of design, planning, and construction management or the university architect) and procurement personnel (i.e., the procurement contracts manager and the associate purchasing director) review all application materials to develop the list of prequalified bidders. The vice chancellor for business and administration also sits on the committee when the estimated project value is over $10 million. In addition, the chief accountant from the business division, as a nonvoting member, reviews the financial part of all applications and provides a comparative analysis of each firm's fiscal capacity. The university's outside counsel for the UConn 2000 program also serves as an ex officio member, advising the committee on legal matters related to prequalification.

Rejected contractors can and have requested reconsideration of their applications for prequalification. In general, it is university policy to qualify an applicant as long as there is no clear reason for rejection in order to have the largest pool of responsible bidders possible.

A variation of the prequalification process was used for the two large student apartment projects (Hilltop and North Campus), which were originally intended to be financed, built, and operated by development companies under a land-lease arrangement with the university. For the apartment projects, university staff identified firms recognized as leading developers of university student housing and sent them requests for proposals. All applicants were still required to submit a questionnaire about their qualifications, financial information, and references, which were screened by an evaluation committee of university personnel. The evaluation committee also interviewed the short-listed applicants and made the final selection of companies to serve as design builders for the two projects (Capstone and JPI, respectively) based on their preliminary designs, experience and financial capability.2

To examine the impact of prequalification on the UConn 2000 program, statistics from the 25 prequalification processes conducted during the past three years were reviewed by program review committee staff. The university received on average nearly a dozen prequalification applications for each project although the number of contractors applying ranged from 2 to 17. In all but one case (the project to complete the new bio-physics building that received only two applications), at least one applicant was disqualified and in most cases (20) at least one-quarter of the contractors were rejected for a particular project. In five prequalification processes, half or more of the applicants were not approved. In a small number of cases, rejected contractors have asked to be reconsidered and a few decisions have been reversed. To date, no disqualified applicant has pursued a legal challenge of the process.

Files from 13 recent prequalifications were examined to determine the reasons contractors were disqualified from bidding on UConn 2000 projects. Based on this sample, the most common reasons for rejection were lack of relevant experience and/or insufficient financial resources. Contractors were also rejected because of performance problems on prior UConn jobs (e.g., delays, cost overruns, noncompliance with wage and safety requirements).

For example, the Suffolk Construction Company has not been prequalified for additional projects at UConn in part because of a poor working relationship with the university during the South Campus project. Another contractor, Capstone Building Corporation, was initially rejected for a second project (the Greek Housing complex) primarily because of university concerns about its subcontractors' extensive prevailing wage violations on its previous UConn 2000 project, Hilltop Apartments.

Capstone requested reconsideration and was subsequently prequalified after addressing the labor compliance matter to the university's satisfaction. As low bidder, Capstone was later awarded the job contingent upon agreeing by contract to dedicate a staff person to prevailing wage compliance and require all subcontractors to participate in labor law training and to obtain labor and material payment bonds. Those provisions are being met according to the university staff monitoring the project.

The committee also examined the distribution of UConn 2000 work among contractors as another indicator of impact of the prequalification process. As Table 1 shows, most (16) of the 20 different companies hired for the 39 major UConn 2000 projects completed or in progress as of November 2002 have been awarded one or two projects each. Only one company, Whiting-Turner, has been awarded more than three projects. Whiting-Turner was selected to carry out all dormitory sprinkler and other renovation work at the main campus, which to date has included six separate projects.

In terms of project dollar value, work is also fairly well dispersed among contractors. Only two firms have responsibility for projects accounting for more than 10 percent of the combined budgets for all 39 projects. One, Whiting-Turner, is also the contractor with the most projects. The second, Walsh, was awarded two of the UConn 2000 program's largest projects, the Stamford Campus Relocation in 1998 and the New Chemistry Building in 2000.

From this analysis, it appears the prequalification process permits the university to screen out contractors unsuited for particular projects or with poor performance records. It also can protect against over reliance on any one company to perform work.

Subcontractor prequalification. The university does not have its own prequalification process for subcontractors at present. Instead it relies on the selection policies of its general contractors and construction managers to ensure subcontractors hired for UConn projects are responsible and qualified. Most GCs/CMs use the ability of a subcontractor to be bonded as their major screening factor. Some contractors have additional requirements, such as a minimum safety rating based on worker's compensation experience and a formal process for prequalifying their subcontractors.

On nearly all projects, it is subcontractors who have the most direct impact on time, cost, quality, safety, and employment issues since they are the ones actually performing the work. The contractor ultimately is responsible for the performance of its subcontractors and can be required to take corrective action as problems develop. The committee believes hiring responsible and qualified GCs and CMs is one of the best ways to insure good quality subcontractors. In order to prevent performance problems, it is also in the university's interest to make sure subcontractors with poor records are not hired.

Table 1. Distribution of UConn 2000 Major Projects

(Completed and In Progress): November 2002

GC/CM

Number of Projects

Project

Dollar Value

Percent Total Number

Percent Total

Dollar Value

Hayes

1

$ 1,820,843

2.6%

0.2%

Conn-Strux

1

$ 2,399,032

2.6%

0.3%

Carlin

1

$ 2,682,743

2.6%

0.3%

MCC

2

$ 6,128,613

5.1%

0.8%

Haynes

1

$ 14,388,690

2.6%

1.8%

Aspinet

1

$ 17,249,347

2.6%

2.2%

HRH/Atlas

2

$ 19,579,349

5.1%

2.5%

Gilbane

3

$ 22,600,000

7.7%

2.9%

Manafort

1

$ 24,000,000

2.6%

3.0%

Precision Power

2

$ 33,523,355

5.1%

4.3%

FIP

2

$ 34,345,744

5.1%

4.4%

CR Klewin

1

$ 41,518,638

2.6%

5.3%

JPI

1

$ 45,000,000

2.6%

5.7%

Suffolk

1

$ 46,310,651

2.6%

5.9%

Turner

2

$ 53,702,682

5.1%

6.8%

Capstone

2

$ 53,930,496

5.1%

6.9%

O&G

3

$ 61,532,157

7.7%

7.8%

Konover

3

$ 74,072,518

7.7%

9.4%

Whiting-Turner

7

$ 103,371,325

17.9%

13.1%

Walsh

2

$ 129,134,651

5.1%

16.4%

Total

39

$ 787,290,834

   

Source: LPR&IC staff analysis of Capstat data.

The university can and has asked its contractors not to use proposed subcontractors because of performance problems experienced on prior UConn jobs. For example, JPI, the design builder for the current North Campus student apartment project, was directed to exclude from bidding the masonry subcontractor cited for prevailing wage violations on the Hilltop Apartments project (B&R Brick).

The ability to reject unsatisfactory subcontractors can be a powerful way to control project costs, time, and quality especially if objective evaluations of proposed companies are readily available to those involved in the hiring process.

The university does not have an established mechanism for rating or reporting on subcontractor performance. In addition, there is no comprehensive inventory of all firms that have or are working on UConn 2000 or other university construction projects.

Current assessments of subcontractor performance are informal and subjective. University staff with knowledge of problem companies may be unaware they are under consideration for additional work. It is difficult at present to even determine how many and which jobs subcontractors have worked on at the university.

The committee recommends the university develop and maintain an automated database of all companies that perform construction work. In addition, a system for evaluating contractors and subcontractor performance at the conclusion of a project that includes a way for companies to officially respond should be established and used to develop a "poor performers" list.

With this information, UConn can take steps to keep subcontractors that don't meet established performance criteria from being hired or at a minimum require additional monitoring by a GC/CM during the construction process. Like the prequalification criteria, the subcontractor rating factors should reflect university priorities (e.g., safety, timeliness, on budget, highest quality, in compliance with labor laws) and be consistently applied.

The committee believes a "poor performers" list is preferable to a subcontractor prequalification process for several reasons. Implementing such a process would take considerable staff resources and time given the number and diversity of subcontractors that perform UConn 2000 work. In addition, having the owner involved in the selection process could interfere with the contractual relationships between a GC/CM and the subcontractors they hire.

Recent legislative changes already require the university to take steps in the direction of this recommendation. Under the UConn 21st Century law, the university now must consider subcontractor compliance with labor laws as part of its contractor prequalification process. It must also report the names and addresses of all contractors and subcontractors who performed construction work on UConn campuses during the preceding six months to the legislature's finance committee by December 31 and June 30 each year.

To further promote its safety goals, the university is considering establishing a minimum standard of safe performance for its contractors and subcontractors. The relationship between a company's workers' compensation insurance rating and its safety record while performing construction work for UConn is being researched by A/E Services staff and personnel from the university's owner controlled insurance program. Information on safety prequalification standards used by public owners in other states is also being developed. The committee supports the university's efforts to identify and develop minimum standards for its construction contractors and subcontractors.

UConn 2000 Program Outcomes

Success in the construction industry is generally viewed as finishing a quality project on time and on budget. As discussed below, the majority of UConn 2000 projects have been completed without significant delays or cost overruns while more information is needed to fully assess work quality. Another important goal of UConn construction management is assuring compliance with safety requirements and employment laws. Safety is stressed as the university's highest priority in its contract documents, policy manuals, correspondence and directives. Labor law compliance has been given increased attention by UConn in response to serious prevailing wage rate violations that occurred on one project last summer. Compliance outcomes related to worker safety and labor laws are presented in detail in later sections.

Current status. In assessing the effectiveness of the university's construction management process, it is important to keep in mind the size of the UConn 2000 program. The number and scope of projects it includes make the university campuses among the largest concentrated sites of continuous construction activity in the state.

The UConn 2000 program is in its seventh year and the majority of the projects specified in its enabling legislation have been completed or are in progress. Since work began in 1996, a few projects have been added or deleted, others have been combined, and some have been postponed (e.g., moved to the UConn 21st Century program) as needs, priorities, and funding sources have changed.3 As of November 2002, the program included 44 major capital improvement projects.

As Figure 2 indicates, 27 major new construction and renovation projects involving total expenditures of over $543 million were essentially complete and another 12 with combined estimated budgets of about $244 million were underway in November 2002. Five projects expected to cost around $114 million were in the planning or design phase. Detailed information on each major project is provided in Appendix B.

The program also includes approximately 260 deferred maintenance and smaller repair and renovation jobs worth about $145 million that were finished or in progress as of November 2002. About $20 million more is anticipated to be expended on such projects during the final two years of the UConn 2000 program.

Individual UConn 2000 projects have ranged from the construction of a new, high-tech $57 million chemistry building to the $800,000 conversion of a horticulture barn to a natural history museum and include:

The workforce involved in carrying out the UConn 2000 program is substantial. In total, about 40 different contractors and at least 1,000 subcontractors have worked on UConn 2000 projects to date. Major projects have been awarded to 20 different general contractor and construction management firms, about half of which are headquartered in Connecticut, as Table 2 shows. During peak periods in the construction season, the university estimates hundreds of workers are on the many active job sites at the Storrs campus alone.

Construction management performance. Overall, the committee found serious contractor performance issues have been rare in the UConn 2000 program. To date, three major projects have experienced significant problems. They are:

Table 2. Major UConn 2000 Project Contractors: Fall 2002

GC/CM

HQ State

Major Projects Awarded

Aspinet

CT

    Wilbur Cross Building Renovation

Capstone

AL

    Hilltop Apartment Complex

    Greek Housing Complex

Carlin

CT

    White Building (Dairy Bar) Renovation

Conn-Strux

CT

    Mansfield Apartments Renovation

FIP

CT

    New School of Business

    New Towers Dining Facility

Gilbane

RI

    Gentry Building Renovation

    Old School of Business Renovation (CUE)

    Benton Museum Addition

    New School of Pharmacy/Biology

HRH/Atlas

NY

    Ice Rink Enclosure

    Ag/Bio Tech Phase I

    New Bio-Physics (Tech Quad 1A)*

Hayes

CT

    Litchfield Agricultural Center

Haynes

CT

    Waring Building Renovation

JPI

TX

    North Campus Apt & Suites

CR Klewin

CT

    Avery Pt Marine Science Center

Konover

CT

    New Central Warehouse

    New Hilltop Dormitory

    Student Union Addition

Manafort

CT

    Parking Garage South and Co-Op

MCC

CO

    Natural History Museum Conversion

    Avery Point Renovations

O&G

CT

    Music & Drama Addition

    Parking Garage North

    New Info Tech Eng. (ITE) Building (Tech Quad 2)

Precision Power

CT

    Fairfield Rd. Pedestrian Mall

    Heating Plant Upgrade

Suffolk

MA

    South Campus Dorm. & Dining Facility

Turner

NY

    Ag/Bio Tech Phase II

    Completion New Bio-Physics (Tech Quad 1A)*

Walsh

NY

    New Chemistry Building.

    Stamford Campus Relocation

Whiting-Turner

MD

    Gant Plaza Deck Repairs

    Dormitory Code Renovations/Sprinkler Projects (Alumni Quad, East Campus, Hilltop Dorms, North Campus, Northwest Quad, Shippee/Buckley)

* HRH/Atlas, the original GC for the New Bio-Physics Building project was terminated by the university in February 2000 and replaced by Turner Construction.

Source: LPR&IC staff analysis of Capstat data and A/E Services files.

These cases and several less severe schedule and budget problems on early UConn 2000 projects may be related to the university's learning curve as the owner of a $1 billion capital improvement program. In terms of keeping projects on time and on budget, performance appears to have improved as UConn staff gained construction management experience. Another factor may be the university's shift to the construction manager at-risk project delivery method.

A primary reason the university decided to try alternative project delivery methods was to avoid the issues of excessive change orders and claims that developed with the GCs who worked on the South Campus and New Bio-Physics jobs. Throughout the study, the committee staff noted the university typically takes a proactive approach to correcting construction management problems. For example, to respond to deficient design documents, an increasingly common problem in the construction industry, A/E Services hired an outside firm to review and coordinate all planning materials for its larger, more complex projects. Currently university staff are analyzing the cost effectiveness of the self-insurarnce program for large UConn 2000 construction projects. University personnel are also working with the Commission on Human Rights and Opportunities to try to improve minority business participation in the UConn 2000 program.

As part of its assessment of the effectiveness of the UConn 2000 construction management process, the committee reviewed time and cost outcomes for the 27 major projects completed as of November 2002. For the purposes of the committee study, the following definitions were used:

Using these definitions, the following analysis shows most UConn 2000 projects have been completed on time and on budget, reflecting the university's emphasis on schedule and cost, with safety as its highest priority.

Timeliness. Completing construction projects on time is a top priority for the university. Given the constraints of the academic calendar, it is critical for new or renovated classrooms and dormitories to open as planned. In cases where work can only be carried out only during summer months when few students are on campus, keeping a project on schedule becomes imperative. Delays additionally can have significant budget implications, not only in terms of higher construction costs but also from lost revenues (e.g., room and board fees).

As a result, schedules are closely monitored by the UConn field staff and regularly reviewed by the A/E Services top management. A standard agenda item discussed at all weekly owner/contractor job meetings is construction schedule and progress. Contractors are required to continuously revise and submit progress reports and, if necessary, prepare "recovery schedules," which are formal plans for making up lost time. In addition, university construction contracts usually include provisions for "liquidated damages," a standard industry practice that requires contractors to pay owners a per day monetary penalty (e.g., $1,000) when projects are not completed on time. As of November 2002, no liquidated damages had been imposed regarding UConn 2000 projects.

The committee staff analysis of the 27 major UConn 2000 projects completed as of November 2002 showed 85 percent were finished on time. Specifically:

_ The Stamford Campus Relocation, which was delayed for one semester; and

_ two projects (Litchfield Agricultural Center and Avery Point Marine Science Center) and one phase of another job (the UConn Co-Op portion of the South Garage project), which ended up a year behind schedule.

Further, 9 of the 12 major projects now in progress are expected to meet their original deadlines for completion. One current renovation project (Old School of Business) will be finished about two months late due to unforeseen site conditions and the schedule for another (Benton Museum addition) was recently extended six months. The New Bio-Physics Building, which was halted due to the original contractor's performance problems and subsequent firing by the university, is now two years behind its projected completion date. However, its revised deadline for occupancy -- late December 2002 - was met by the construction manager that took over the project.

On budget. Controlling construction cost overruns is as important to the university as keeping projects on schedule. The primary ways to keep capital projects within budget is to minimize changes that add costs or time to a project and to identify cost effective alternatives when changes are required (e.g., through value engineering). University field staff are responsible for monitoring and initially assessing proposed change orders for their assigned projects. All change orders are subject to final approval by the architecture and engineering services executive director, the University Architect. Project budgets, like schedules, are analyzed in detail at weekly job meetings and are closely tracked by A/E Services top management.

Analysis by program review committee staff indicated most UConn 2000 projects have been completed close to their preconstruction cost estimates although budgets have not been finalized for the majority of projects. Typically, final costs for a project are not calculated until all payment items (e.g., change orders, cost adjustments, subcontractor payments, retainage) are processed, which may take a number of months after the construction work is done.

Analysis of budget data available as of November 2002 for the major UConn 2000 projects shows most have been completed close to their preconstruction cost estimates. Specifically, of the 27 completed projects:

_ Five, however, had undergone major scope revisions (e.g., optional work was added, projects were combined); thus, the budget increases were due primarily to added work rather than cost overruns.

_ In at least two cases, large cost overruns were due to inadequate original cost estimates.

In addition, all but one of the 12 major projects currently in progress is projected to be finished very close to the original estimate. The construction manager that took over the remaining active project, the Bio-Physics building, is more than 95 percent done and expected to be on budget for its phase of the work. The university also anticipates if it wins its counterclaim for damages against the original contractor, the final project cost will end up close to the original estimate.

Work quality. As discussed earlier, the university uses the industry's generally accepted quality control and code compliance procedures to ensure work and materials meet contract requirements and all standards. Field staff conduct daily on-site inspections of work quality, check materials, equipment, and workmanship for compliance with plans and specifications, and arrange for independent inspection or testing of key project components and materials. Nonconformance issues such as work or materials that do not meet contract specifications, are addressed at weekly job meetings and, if necessary, referred to A/E Services top managers for resolution (e.g., withhold payment, legal action).

The long-term impact of the university's quality control efforts is difficult to assess since almost all of the work completed under the UConn 2000 program is less than five years old. More than half (15) of the 27 major completed projects were finished in the last 12 months. As a result, the majority of UConn 2000 work has not reached the warranty phase of the construction process where problems with equipment, materials, and workmanship tend to be identified and addressed.

While the university reports no significant issues have arisen to date, information related to construction project quality such as subsequent corrective work, repeated repairs, equipment failures, and warranty claims is not systematically compiled and evaluated.

A/E Services staff do monitor quality problems and maintain records on nonconformance issues on project-by-project basis. There is not a standard system for documenting quality issues at present and data related to project quality are not centrally collected and reviewed. Without such a system, the success of a project cannot be fully evaluated. Further, it is difficult to identify problems with design standards or specifications, patterns of poor contractor performance, or inadequate quality control procedures.

The program review committee recommends the university define outcome measures for work quality and establish a system for tracking and regularly evaluating data on the quality of its construction projects.

There is no formal mechanism for summing up work quality issues at the end of a project at present. Final project documentation and central record keeping of work quality indicators have not been a priority as staff effort has been focused on getting projects designed and built. Now that the majority of the UConn 2000 projects are reaching the close-out phase of the construction process, these tasks are receiving more attention. The university is just developing a formal construction quality assurance program that could incorporate the committee's recommendation.

According to university plans, the new quality assurance program will include review and updating of design standards, new procedures for enforcing warranties, and more attention to preventative maintenance programs. UConn is considering expanding its independent field inspection and testing program and possibly adding an electrical and a mechanical field inspectors to its internal code compliance unit. The university plans to set up a process for cataloging and maintaining a database for warranty and guarantee information. An upgraded computerized maintenance management system that provides warranty control, equipment inventory, and preventative maintenance programs is also being studied. The committee believes the proposed program can considerably strengthen the quality control aspect of the university's construction management process and should be actively pursued.

Chapter Three

Employment Law Compliance

Federal and state laws on employment (e.g., minimum wage, fringe benefits, overtime, work hours) and worker status (e.g., child labor, immigration) apply to all employers on UConn 2000 projects. In addition, because they are public works projects, employers are required to comply with the state's prevailing wage law. The following analysis and findings focus on the university's oversight process to ensure contractor compliance in two key areas: the state prevailing wage law and federal immigration laws regarding the hiring of undocumented workers.

Prevailing Wage

The state's prevailing wage law (G.C.S. § 31-53) is an important mandate for public works employees. The law is aimed at preventing the government low bid requirements from reducing the market price for labor to a level that may disrupt the local economy. Specifically, the prevailing wage law is intended to ensure wages commonly paid to construction workers in a particular region of the state will be the minimum wage paid to the same types of workers on public construction projects.5

The prevailing wage law applies to public works contracts for:

No single prevailing wage exists in Connecticut. Prevailing wage rates can remain in effect for a short, specified period of time or indefinitely and they differ across:

The prevailing wage is calculated based on two components: 1) total cost of the hourly base rate paid directly to the employee; and 2) fringe benefits (e.g., pension, health care, insurance, and holiday or vacation) which may be paid as contributions to an employee welfare and benefit fund administered by a union or employer or in cash directly to the employee.

Minimum hourly rates of pay are set by the state labor commission for each classification of construction worker under the federal prevailing wage law (Davis-Bacon Act) and are issued by the state Department of Labor for each public works project. For UConn 2000 projects, the university must include the DOL rate schedule in the bid packages and eventually in the project contract.

For public works contracts awarded prior to October 1, 2002, the prevailing wage and benefit contribution rates remain in effect for the duration of the project's contract. A new law (Public Act 02-69), however, requires an annual adjustment of the prevailing wage and benefit contributions each July 1 for the duration of public works contracts awarded after October 1, 2002. Contractors are required to contact the state labor commissioner for the up-dated prevailing wage rates.

A review of the prevailing wage rate schedules for completed and on-going UConn 2000 projects -- all awarded prior to October 1, 2002 and therefore not subject to annual adjustment -- showed the hourly rate of pay ranges from a low of $16.75 for a laborer to a high of $29.85 for a sprinkler fitter. Table 3 shows the prevailing wage rates for certain worker classifications on a sample of UConn 2000 projects.

Table 3. UConn 2000 Project Prevailing Wage Rates for Selected Job Classifications

 

Bio/Physics Building

South Parking Garage

Hilltop Apartments

Northwest Quad Renovation

North Campus Apartments

Classification

Rate

Fringe

Rate

Fringe

Rate

Fringe

Rate

Fringe

Rate

Fringe

Asbestos

24.25

10.76

24.25

10.76

24.25

10.76

22.95

10.76

26.25

11.36

Bricklayer

25.75

9.45

24.10

9.15

23.40

9.35

22.35

8.70

25.75

4.24

Laborer Grp 1

19.75

6.90

18.75

6.90

17.75

7.00

16.75

6.90

19.75

7.00

Carpenter

22.70

8.48

22.00

8.08

21.35

7.68

19.60

7.20

22.70

8.48

Electrician

25.60

10.98

24.60

10.44

24.60

10.44

23.80

10.13

27.60

11.54

Ironworker

25.95

13.63

24.85

13.73

24.85

13.63

24.05

13.33

27.30

14.38

Operator Grp 3

27.12

9.20

26.77

9.05

25.12

8.95

24.12

8.95

27.12

9.20

Painter brush

22.27

7.75

21.05

7.30

21.05

7.30

21.05

7.30

22.27

7.75

Plumber

26.62

9.60

25.32

9.60

25.32

9.60

24.02

9.60

27.92

9.60

Roofer

19.94

8.51

19.64

8.36

19.64

8.36

19.04

8.06

19.94

8.51

Sprinkler Fitter

28.05

8.95

27.10

8.90

27.10

8.90

26.15

8.85

29.85

9.05

Sources of Data: UConn A/E Services and Connecticut DOL Wage & Workplace Standards Division

Apprentices are not paid the full prevailing wage rate for the trade classification for which they are training. They are paid a specified percentage of the wage rate, which increases in steps as the apprentice completes the training program. (Apprentice programs are required to be licensed by the Department of Consumer Protection.) In addition, supervisory personnel and independent contractors are excluded from prevailing wage coverage. Certain other workers such as truck drivers for material delivery companies are only covered by the prevailing wage law if they spend a specified portion of their work day on the job site.

University oversight process. Implementation of the state prevailing wage law involves the parties required to comply with it, the beneficiaries of its provisions, and the entities responsible for administering it. All of these groups from the workers to the contractors to the owner to government agencies have specific functions to perform. The responsibilities of each entity are outlined below.

 

Responsibilities

Employee

  • Notify appropriate enforcement entities on a timely basis if not receiving the wages they are entitled to
  • Preserve supporting documentation (e.g., pay stubs)

Contractor & Subcontractor

  • Submit certified oath to DOL regarding wages paid on job site
  • Post prevailing wage rate schedule at job site
  • Pay correct rate to workers
  • Maintain detailed records (e.g., weekly certified payroll) regarding hours, duties, wages, and fringe benefits of employees
  • Comply with any audit or investigation conducted by enforcement agency

Owner

  • Determine applicability of prevailing wage law to project
  • Obtain appropriate wage schedule prior to project being put out to bid
  • Include prevailing wage provision in the project contract

State Labor Department

  • Primary enforcement of state prevailing wage law through routine audits and investigations of complaints
  • Calculate, collect, and distribute back wages owed to workers
  • Assess and collect civil penalties
  • Refer violators for debarment and/or criminal charges
  • Provide technical assistance and training to employers and owners

Acting as owner of the UConn 2000 construction project, the university has the obligation to require contractors doing work for it to comply with all applicable laws. As a state agency with control of a $1 billion public works program, there is an added expectation that the university be even more proactive in ensuring compliance.

University contract provisions have always required contractors and subcontractors to abide by the relevant employment laws including prevailing wage. However, prior to the summer of 2001 when the Hilltop Apartments case, discussed in detail below, resulted in significant prevailing wage violations cited by the state labor department, the university did not emphasize compliance with the prevailing wage law.

Since that time, the university has explicitly directed contractors through contract provisions, in correspondence, and during preconstruction meetings to meet the prevailing wage requirements. It also expanded its efforts to ensure compliance by implementing a tighter field and paperwork review process. Figure 3 outlines the current university process for overseeing prevailing wage compliance on all UConn 2000 projects.

In addition to the statutory mandates specific to the prevailing wage law, the university process now provides for :

On some projects, the university has required a CG/CM to be contractually obligated to dedicate staff to prevailing wage oversight of subcontractors and has also encouraged participation in state labor department prevailing wage training sessions by contractors and subcontractors.

Most recently, the university adopted a "zero-tolerance" policy toward noncompliance with the prevailing wage law. The university required a subcontractor (Johnson Roofing Company) cited for prevailing wage violations on the North Campus Housing project in November 2002, for which JPI Inc. is the design-builder, to be terminated (see following case study discussion). In addition, it sent a letter to all contractors and subcontractors currently working on campus reinforcing the university's concerns over compliance with state employment laws and informing them of its "zero-tolerance" policy.

With the implementation of its new policies and procedures, the university is taking a more active owner's role in prevailing wage compliance than the Department of Public Works (DPW) typically does. According to DPW, their construction staff review certified payroll information submitted by contractors and subcontractors for completeness on a monthly basis. Any questions related to appropriate rates or classifications are referred to the labor department for follow-up. Public works personnel do not at present conduct field audits nor has DPW requested any training from the labor department for its contractors or subcontractors.

Prevailing wage enforcement process. The Department of Labor is the only state entity with authority to enforce the state's prevailing wage and other employment laws. It is responsible for taking appropriate action when it receives complaints or referrals from workers, owners, and other interested parties (e.g., unions). Furthermore, only the labor department can impose penalties including debarment against violators.

The department's Wage and Workplace Standards Division:

Department of Labor enforcement efforts are constrained by staff resources. At present, the Wage and Workplace Standards Division is staffed by one supervisor and six field enforcement agents. The current deployment of resources for UConn 2000 projects is one field enforcement agent assigned one day (8 hours) per week. At its peak during the investigation of the Hilltop Apartments case, one agent was devoted fulltime (40 hours per week) between February and August 2001. Later between September 2001 and September 2002, the agent worked two days per week. Because of limited staff, the division tends to respond to problems and complaints rather than making assignments based on the level of construction activity on campus.

The labor department reports enforcement activity is focused on specific projects, especially those large in scope and size, and expands to include routine checks of the various phases of construction (e.g., excavation, foundation, framing, roofing, electrical, plumbing, brickwork, etc) and training and assistance when requested by the owner or contractors. While in earlier phases of the study, the labor department estimated it had a three-month caseload backlog. In December 2002 at the conclusion of the study, it estimated a nine-month caseload backlog due to an increased number of complaints. The department explained prevailing wage complaints typically increase as the economy worsens and construction work slows.

As outlined in Figure 4, the processes for handling field audits and investigations are basically the same. An investigation is initiated in response to a complaint, usually by an employee. A field audit may be routinely scheduled based on a need identified by another case or given available resources of the division.

Civil penalties may also be imposed against an employer found to be in violation of the prevailing wage law. Civil penalties collected are used to offset the administrative costs of the division. As part of its practice to encourage compliance rather than punish violators, civil penalty amounts are routinely negotiated and often reduced based on the willingness of the employer to make restitution of back wages.

Failure to make restitution can result in:

Enforcement outcomes. Data on prevailing wage violations cited on all UConn 2000 projects at the university's main and regional campuses were compiled by program review committee staff from labor department information available as of mid-December 2002. Since 1995, there have been a total of 157 prevailing wage cases with 91 substantiated, 21 unsubstantiated, and 45 pending. The most commonly cited violations on UConn 2000 projects included the underpayment of wages, fringe benefits, and overtime, the misclassification of workers, and record keeping errors on certified payrolls.

Analysis of the enforcement data additionally showed:

To compare the extent of prevailing wage violations at UConn 2000 projects with other large-scale public works construction projects, the program review committee examined state labor department enforcement statistics for the Connecticut State University (CSU) system's infrastructure building program.

CSU was selected as the program most similar to UConn 2000 because it involves a multi-million dollar public works program of higher education new construction and renovation projects. Since July 1996, the CSU program has included 101 major capital projects costing almost $488 million and another $19 million in minor deferred maintenance work.

Between 1996 and November 2002, there were 62 prevailing wage violation cases related to projects on the Central, Eastern, Southern, and Western Connecticut State University campuses. Of these, 58 were substantiated and four were unsubstantiated. Like the UConn 2000 program, the most commonly cited prevailing wage violations were: underpayment of wages, fringe benefits, and overtime; misclassification of workers: and record keeping errors on certified payrolls.

The labor department collected $640,033 in back wages (representing less than 0.5 percent of CSU construction costs to date related to the substantiated violations. A total of $105,450 in civil penalties was assessed against employers violating the law, but only $15,200 (14 percent) was collected after negotiated reductions.

Given that the CSU project is about half the size of the UConn 2000 program, the scope and severity of the prevailing wage noncompliance appears comparable. In total, CSU projects had about half the number of violations and amount of back wages owed to workers as the UConn 2000 program projects during the same time period. One area where CSU differed from UConn 2000 was in civil penalties. Employers cited for prevailing wage violations on UConn 2000 projects were assessed and paid higher civil penalties than those on CSU projects.

Prevailing wage compliance case studies. As noted earlier, the committee study was initiated largely in response to the serious prevailing wage violations that were cited on Hilltop Apartments project during the summer of 2001. A summary of the Hilltop Apartments case is provided below. During the course of the committee's review, prevailing wage issues arose related to an on-call environmental contractor and to subcontractors for an active project, NOrth Campus Apartments. Summaries of these cases are also presented to illustrate the complexity of the prevailing wage law, the difficulties in assuring compliance, and the sometimes arbitrary nature of enforcement.

Prevailing wage compliance findings. Excluding the Hilltop Apartments case, the amount of Department of Labor enforcement activity and prevailing wage violations cited have not been unusual, given the size, scope of work, duration, and budget of the UConn 2000 program. However, the potential exists for undetected violations to occur especially given the current level of enforcement efforts and practices within the construction industry.

Contractor compliance with prevailing wage requirements became a priority for the university following the Hilltop Apartments case. In response, the university has given more attention and expanded its oversight efforts to ensure compliance.

The program review committee found no evidence of widespread noncompliance with the prevailing wage law. The type of violations cited by the labor department and the amount of back wages paid to workers does not appear to be dissimilar from those found on other large public works projects throughout the state. For the most part, there are few complaints from workers and apparent compliance by employers on campus.

The prevailing wage violations cited at UConn 2000 projects, especially the Hilltop Apartments and North Campus Housing projects that were awarded to out-of-state contractors, have created a public relations problem for university. Furthermore, these incidents contribute to the already strained relationship between the university and labor unions.

Prevailing wage violations have almost no impact on the schedule, budget, or quality of a building project, which are the primary objectives of an owner. The prevailing wage law is complex and requires the completion and review of minutely detailed records (e.g., certified payroll). The process is time-consuming and labor intensive for contractors and subcontractors and in terms of owner oversight, and state enforcement activity. Achieving compliance with the prevailing wage law, therefore, takes significant resources, commitment from all parties involved, resource management, accountability, and follow-up.

Prior to the Hilltop Apartments case, the university gave prevailing wage compliance on UConn 2000 projects perfunctory attention. In response, the university strengthened its position on compliance by contractors, increased its oversight, and recently adopted a "zero-tolerance" response to contractors who violate the law. Acting as the owner of a large-scale public works project, the university responded in a timely and appropriate manner. It has taken reasonable steps in its role as project owner to ensure its contractors understand and comply with the prevailing wage law.

State labor department enforcement efforts at the unversity before the Hilltop Apartments case were routine. Following resolution of the case, DOL returned to a standard presence on UConn 2000 projects. It continues to prioritize its enforcement efforts based on available resources and the severity of the complaint. In addition, the department has responded to the university's request to provide assistance and training to contractors to improve compliance with the prevailing wage law.

The program review committee, therefore, made no recommendations regarding the university's oversight of prevailing wage compliance. As discussed above, the university has taken appropriate corrective actions as project owner to address contractor compliance issues. Statutory changes enacted under the new UConn 21st Century program will also improve oversight process and the program review committee supports provisions that require the university to:

As previously stated, enforcement of state prevailing wage requirements is the purview of the state labor department. While program review committee noted weaknesses, the effectiveness of state policies and department procedures governing the prevailing wage law were outside the scope of this study. In addition, the remedies to address prevailing wage enforcement issues would require the legislature to make resource allocation as well as policy decisions.

Immigration Laws

Federal law defines employment as any service or labor performed for any type of remuneration within the United States. Furthermore, the law:

To legally work in the United States, an employee must be a U.S. citizen, a lawful permanent resident, or an authorized temporary worker. All workers must:

The U.S. Immigration and Naturalization Service is the agency responsible for locating and removing illegal aliens and conducting worksite enforcement operations. The state labor department has no authority or jurisdiction in this area, but can refer employers and employees suspected of violating the law to the INS.

The INS has reported and an independent evaluation from the U.S. Commission on Immigration Reform have concluded the agency has relegated its responsibility for identifying illegal alien workers to a very low priority. At this time, the INS focuses its limited resources on worksite enforcement only where there is believed to be a large concentration of illegal alien workers and deporting criminal aliens. As with prevailing wage complaints, the INS reports complaints regarding undocumented workers tend to increase during times of economic downturn; increased enforcement activity may result if the job market continues to tighten or federal policy is changed.

As previously discussed, several recent UConn 2000 prevailing wage cases have included allegations related to the hiring of undocumented workers. Labor unions have often been the source of the complaints and out-of-state companies are the most common subjects. To date, three cases have been referred to INS but no allegations have been substantiated.

As part of the case studies of prevailing wage enforcement, the program review committee staff verified the required employee documentation (i.e., I-9 forms) for those subcontractors who were targets of complaints were on file with the GC/CMs for the projects. Employment documents were also reviewed for compliance by the staff of the university's contract administrator (Bechtel/Fusco). Without INS assistance, however, the documents could not be authenticated.

Potential exploitation of undocumented workers is an issue that generates strong political and public reactions. It is, however, a problem that is difficult to resolve under current federal law and enforcement policies. Allegations are difficult to substantiate because there is little federal enforcement and the state has no jurisdiction. Illegal workers are reluctant to cooperate with an investigation for fear of losing their jobs or being deported. They typically leave the state as soon as their work is completed and are then difficult to locate for investigative purposes. Finally, there are economic incentives on the part of employers as well as undocumented workers for weak enforcement.

Acting as the owner, the university has insisted on contractor compliance through its contract provisions. The university has reacted appropriately when allegations arise by ensuring the complaints are addressed and all follow-up actions such as an INS referral are taken. It cannot, however, factually refute the charges. Because allegations generally are not substantiated, suspicions linger.

The extent of the hiring of undocumented workers is unknown among contractors working on UConn 2000 projects. The only allegations made and subject to possible INS follow-up to date have involved two projects being carried out by two out-of-state companies. The University of Connecticut has ensured to the extent possible all its contractors comply with all employment laws, including the federal immigration laws, and has responded appropriately to complaints regarding the hiring of illegal aliens.

The enforcement of federal immigration laws regarding Immigration and Naturalization Service oversight of the hiring of illegal aliens is not a priority at this time. The state of Connecticut has no jurisdiction and, therefore, cannot dictate federal policy or resources.

The problem of undocumented people working in the United States reflects a historical construction industry practice influenced by labor resources. Ultimately, this problem won't be addressed until the economic forces, industry practices, and/or federal immigration laws and enforcement policies change.

Chapter Four

Safety Compliance

There are inherent hazards and potentially unsafe work conditions on construction job sites. In response, federal and state laws and regulations as well as safety standards within the industry have been adopted to:

Federal Requirements

Federal law requires construction employers to provide a workplace that is free from recognized hazards. The Occupational Health and Safety Administration within the U.S. Department of Labor has primary authority to set and enforce safety standards to ensure compliance with the law. The standards are based, in large part, on the construction industry's best practices and policies. OSHA standards are extensive and cover most aspects of construction trade activities, equipment, materials, and processes including:

OSHA jurisdiction extends to private sector job sites, which is defined based on the employer-employee relationship and not on the project funding source. UConn 2000 projects, therefore, are private sector job sites under federal jurisdiction because the construction workers are employed by private sector entities (contractors and subcontractors) and not the university.

State Requirements

Federal law requires state safety standards be "as effective as" OSHA standards. The state labor department's Division of Occupational Safety and Health (CONN-OSHA) has adopted all OSHA standards and enforcement requirements.

CONN-OSHA administers Connecticut's Public Employer Only State Plan, which enforces occupational safety and health standards applicable to all state and municipal workers. CONN-OSHA has jurisdiction on UConn 2000 projects only if a university employee or student is exposed to a hazard or imminent danger exists due to a violation of a safety or health standard. In terms of the scope of this study, CONN-OSHA's role is very limited.

University Safety Oversight Process

Safety is first and foremost within the construction industry. It is also the university's top priority according to its manuals and construction documents provided to all contractors on UConn 2000 and other construction projects.

There is a strong financial interest to all parties to work safely and prevent injury and lost worker time. Each of the parties involved in a construction project, from workers, to ontractors, owners, government agencies, and insurers, have roles and responsibilities related to occupational safety and health standards, as described below.

Party

Safety Responsibilities

Employees

  • Ultimate responsibility to follow safety standards on job site, operating equipment, using tools, and handling materials
  • Participate in trade, union, and/or employer training and regular "toolbox" safety meetings conducted by employer
  • Notify appropriate supervisory personnel or enforcement entities of hazards or safety violations

Subcontractor

  • Comply with all safety standards regarding precautionary measures, maintenance of equipment, storage and disposal of materials, signs and signals to provide safe work site, and emergency and medical evacuation procedures
  • Provide necessary safety equipment to workers (e.g., hard hats, safety glasses, respirators, safety belts)
  • Maintain liability insurance
  • Conduct regularly scheduled "toolbox" safety meetings
  • Provide necessary training based on type of work performed and materials and equipment used
  • Develop and implement a safety plan
  • Comply with contractor's and owner's safety plans

Contractor

  • In general, same responsibilities as subcontractors
  • Review subcontractors' safety plans

Owner

  • Adopt generally accepted industry safety practices and OSHA standards into safety plan
  • Provide safe work site
  • Maintain liability insurance
  • Review contractor's and subcontractors' safety plans
  • Conduct routine safety inspections, document violations, and require corrective action

OSHA

  • Primary enforcement of worksite safety standards through routine inspections and investigations of complaints, injuries, and incidents
  • Assess and collect civil penalties and track corrective action taken in response to cited violations
  • Provide technical assistance to improve compliance with standards and worksite safety

Insurer

  • Establish rating and premiums based on safety records
  • Pay claims

In addition to the safety activities common to most construction work, the university has instituted a number of its own requirements for UConn 2000 and other building projects. These include requiring:

Owner controlled insurance program. The university uses an owner controlled insurance program for most of its large UConn 2000 projects. Under this approach, which is common in the public and private sectors for major capital construction programs -- usually over $100 million -- the owner rather than a project's contractor and subcontractors buys the necessary workers compensation and general and excess liability insurance. Depending on a project's size and scope, OCIPs can reduce overhead costs since an owner can usually get broader insurance coverage at lower rates the individual contractors. An owner controlled program is also a way to make sure everyone on site is properly insured throughout a project. In addition, self-insured owners can have more control over risk management practices for a construction project including on-site safety programs.

UConn contracts with an outside firm, currently Acordia, to administer its owner controlled insurance program. The OCIP administrator advises on the purchase the necessary insurance policies (the present carrier is Kemper), oversees the enrollment of all covered employees for all participating projects, processes claims, and prepares the final close out of insurance costs when project completed. The administrator is also responsible for implementing a risk management program to control insurance losses at projects covered by OCIP.

As the OCIP administrator, Acordia has a direct and active role in safety matters for many UConn 2000 projects. Acordia staff attend the pre-bid conferences and preconstruction meetings for all OCIP projects to discuss the university's safety requirements for construction projects with contractors. For example, contractors selected for UConn 2000 projects must agree to follow the university's construction safety program as outlined in its written guidelines. The staff also review each contractor's site specific health and safety plan to determine if it is complete and in compliance with OSHA requirements and university guidelines.

The OCIP administrator monitors construction project health and safety in several ways. Acordia employs a full-time person who is responsible for auditing safety compliance at all OCIP projects at UConn. The Acordia safety consultant tries to visit each site one to two times per week to observe safety conditions and practices. More frequents visits are made to projects involving more dangerous activities (e.g., steel erection, significant trenching). The consultant may hold a special pre-meeting to go over safety concerns before work is initiated for higher risk projects and on a random basis attends various project meetings related to safety (e.g., safety training sessions, weekly "toolbox" meetings). Spots checks of safety training documentation, required licenses, inspection certificates, and similar required forms and records are also made during visits to the project site.

The consultant's safety observations are compiled in writing and discussed at each project's weekly work progress meetings. If deficiencies are noted during a on-site visit, a form is left with the contractor and the status of corrective action is tracked by the safety consultant. The consultant is authorized to stop work at a site when it appears there is the risk of serious injury or death and has done so on several occasions.

Kemper, the current OCIP insurance carrier, also has a safety person who makes site visits of UConn projects on a periodic basis. That inspector, who usually goes on-site with the Acordia safety consultant, conducts a safety review and prepares a report that is shared with the project's general contractor and UConn staff. Patterns of poor safety performance noted by the insurer are monitored and may be addressed in several way. Meetings may be held with contractors to discuss or jointly develop corrective action plans. If satisfactory progress is not made, the insurer may recommend to the university that the contractor be terminated or disqualified from future projects.

The Acordia safety consultant presents a summary report at the regularly scheduled meetings attended by key OCIP administrator personnel, a representative from the insurer carrier and UConn 2000 project management staff. The monthly OCIP meetings are used to review trends in injury and lost time claims, highlight field observations at active projects, and address any special safety problems or general issues.

Occupational safety enforcement. As noted above, federal OSHA has primary responsibility for enforcement of occupational safety and health standards on UConn 2000 projects. OSHA compliance officers conduct announced and unannounced inspections triggered by:

OSHA prioritizes its inspection workload based on the severity or proximity of the hazard to the employee. The types of inspections conducted are listed in order from high to low priority:

Based on its inspection policy, OSHA enforcement activity on UConn 2000 projects has primarily been planned inspections of a high hazard industry (i.e., construction). The OSHA regional office in Hartford, which has jurisdiction over the university's main campus, reported it continually updates its cycle of planned inspections that cover the UConn 2000 program based on the on-going construction projects.

Figure 5 shows the OSHA inspection process. It is important to note OSHA does not have authority to shut down a job site due to a safety hazard. Only a contractor or owner can stop work, although workers can refuse to expose themselves to a hazard or unsafe work condition. The same inspection process is followed by CONN-OSHA.

The four types of OSHA violations are as follows.

After an informal conference or appeal by an employer, OSHA can reduce a penalty based on:

Occupational safety outcomes. The program review committee examined OSHA case data related to all UConn 2000 projects from January 1996 to December 2002. Overall, the OSHA data show:

Information on worker compensation claims (e.g., lost time and medical) compiled by the university's OCIP administrator was also reviewed by committee staff. The analysis showed there have been 723 claims related to worker injuries on projects insured under OCIP since 1997. In regard to these cases:

At the request of the university, its OCIP administrator is examining the UConn 2000 program safety record compared to other large higher education construction programs. Complete information was not available for review within the timeframe of the committee's study. Preliminary analysis, however, indicated the extent of lost worker time and injury claims for the UConn 2000 projects is within the normal range, taking into account Connecticut's worker compensation benefit rates are at the high end relative to other states.

Construction is a dynamic process and there are inherent hazards and potentially unsafe work conditions on job sites. Safety is first and foremost within construction industry. As previously stated, the university stresses safety as its highest priority to contractors on UConn 2000 projects. It is clear the university also realizes the importance in term of public relations of maintaining safe campus not only for the construction workers but students and visitors. However, the potential for a hazardous condition or serious accident to occur on a work site will always exist.

Federal OSHA indicated to committee staff its experience on UConn 2000 projects has not prompted any special concerns or increased enforcement activity. The university's safety program has had good results (i.e., no fatalities and few serious accidents to date) in the opinion of OSHA compliance field staff and the OCIP safety manager.

Assuring compliance with safety regulations is an on-going process that also requires commitment from all parties involved in the construction process. Employees, contractors, owners, and insurers all have a strong financial interest in making safety a priority on construction projects.

As previously stated, the university self-insurers its contractors and projects through a contracted Owner Controlled Insurance Program. The program administrator (Acordia) maintains a fulltime safety manager responsible for conducting routine safety inspections of UConn 2000 job sites and tracking corrective action taken by contractors. The university is planning to review the cost effectiveness of OCIP as it prepares to implement the UConn 21st Century program and may not continue the program.

If the university does not continue OCIP for the duration of the UConn 2000 or UConn 21st Century programs, the program review committee recommends the University of Connecticut maintain a fulltime safety manager to conduct inspections, determine and oversee corrective action, educate and train contractors and workers, and identify trends in safety violations.

Chapter Five

Labor Relations

The success of a construction project depends in large part on a good working relationship between an employer and the labor force. There is a natural tension between the interests of workers who want competitive wages and benefits and owners and contractors who want to keep the costs of a construction project down.

There have been labor disputes and several cases of grievances related to projects carried out under the UConn 2000 program. Although limited in number, these incidences have contributed to the strain in the relationship between the University of Connecticut, serving as project owner, and organized labor.

Many members of of the building trades, such as electricians and plumbers, are subject to licensing requirements and unions represent most types of workers including carpenters, masons, laborers, sprinkler fitters, and operating engineers.. The building trade unions have a strong interest, particularly in times of a slow economy, in promoting employment of their members, higher wages, safe work sites, and compliance with labor laws. One of the ways unions ensure jobs for their members is through negotiation of project labor agreements (PLA) for public construction projects. Unions maintain their members typically provide a higher quality work product within budget and on schedule as a result of their training and specialized skills. Hiring union members, however, can mean less flexibility for an owner and contractor because of the unions' regulations governing the type of work performed and work site rules.

A PLA is a contract negotiated between organized labor and a public project owner that generally provides unions will not strike or protest if all contractors and subcontractors agree to:

To date, only one UConn 2000 project was constructed under a project labor agreement -- the Information Technology Engineering (ITE) Building.6 The only trade that did not sign the PLA was the carpenter union, which has a long-standing policy of not signing such agreements. In June 2002, a strike by the carpenter union on an issue unrelated to the PLA or the UConn 2000 program delayed work for about two weeks on most UConn 2000 projects including the ITE Building.

In the absence of a PLA, nonunion contractors and subcontractors may be awarded a public works project and employ nonunion workers as long as they comply with the state's employment laws including prevailing wage, which was discussed earlier in this report, and any trade licensing requirements. State labor and contracting laws do not mandate a union/nonunion preference in awarding public works projects.

Trade unions, however, are concerned nonunion (especially out-of-state) contractors and subcontractors may have an unfair advantage in securing UConn 2000 contracts. The unions claim that by not complying with the state's prevailing wage law nonunion contractors and subcontractors can submit lower bids. Additionally, the unions have alleged nonunion companies engage in other illegal employment practices such as forcing workers to "kick back" wages, reporting workers as independent contractors rather than employees, and hiring illegal aliens to cut costs.

The nonunion contractors and subcontractors maintain low bids can result from a number of legal cost cutting practices including:

Limiting public work to union companies could mean the majority of building trades workers would be excluded from state projects since it is estimated only 20 to 25 percent of such employees in Connecticut are members of unions at present.7 Further, the program committee found no clear indication the performance by union companies was superior to nonunion companies on UConn 2000 job sites in terms of available data on time, cost, quality, and safety. In addition, the committee did not find any comprehensive qualitative analysis to support the unions' position about project quality.

State labor and contracting laws do not mandate a union/nonunion preference in awarding public works projects. The university's labor relation policy for the UConn 2000 program, in accordance with state law, is neutral in this respect in awarding work to contractors and subcontractors. A change in the law to give preference to unions in future work at the university is a matter of public policy for the General Assembly to determine.

The program review committee attempted to determine the extent union companies and workers have been involved in UConn 2000 projects. The data necessary for detailed analysis of union participation in university construction is not routinely compiled by the trade unions, the state labor department, or other worker or contractor organizations and could not be developed within the timeframe of the study. However, it was possible to come up with several estimates.

Analysis of the 39 major UConn 2000 projects completed or in progress indicates about half were awarded to union and half to nonunion general contractors and construction managers. As Table 4 shows, construction work in terms of dollar value was equally distributed between union and nonunion contractors. In addition, of the five major projects that are planned or in design, only two have been awarded -- one to a union CM and one to a nonunion CM.

Table 4. Major UConn 2000 Projects by GC/CM Union Status

 

No. Projects

Dollar Value

Percent

of Total Dollars

Completed Projects

     

Union

13

$259,574,760

50.0%

Non Union

13

$259,284,927

50.0%

Total

26

$518,859,687

 

Projects In Progress

     

Union

5

$134,427,682

50.1%

Non

8

$134,003,000

49.9%

Total

13

$268,430,682

 

All Projects

     

Union

18

$394,002,442

50.0%

Non

21

$393,287,927

50.0%

Total

39

$787,290,369

 

Source: LPR&IC staff analysis

Analysis of a listing of all contractors and subcontractors that have worked on UConn 2000 projects as of September 2002 indicates at least 18 percent of the more than 1,000 different companies included in the database are union firms. The committee staff compiled the list from OCIP enrollment data and the university's prime contractor reports prepared for the Department of Revenue Services. Information on union affiliation was supplied by the Connecticut Construction Industries Association (CCIA) and supplemented with data supplied by several trade union organizations. The actual percentage of union participation is likely to be higher since information was not available for all trade groups -- it may then be closer to the 20 to 25 percent estimate.

Whether the level of union participation in the UConn 2000 program indicated by this analysis is adequate is a matter for policymakers to judge. As noted above, the Department of Labor and the two contractor associations have estimated about 25 percent or less of the building trades workers in the state are unionized.

At the committee's public hearing, representatives from several union organizations raised questions about the amount of university construction work being done by out-of-state companies. According their testimony, state public works projects should be carried out whenever possible by workers and business owners who are state residents and taxpayers. Analysis of the contractor/subcontractor listing described above showed of the 2,120 subcontractor jobs involved in the 214 projects included in the database, 1,787 jobs (84 percent) were done by Connecticut companies. Overall, 95 percent of the projects were done by subcontractors from the New England region and the remainder were carried out by companies from other states and Canada.

This information is similar to the university's own estimate that about 83 percent of construction-related UConn 2000 funding as of June 2002 has been contracted to Connecticut businesses. It appears from these data that Connecticut businesses and workers are performing most of the construction work at the university.

APPENDIX A

Agency Response

APPENDIX B

Major UConn 2000 Projects:

Description and Status

Project Name

Type

Status

(Fall 02)

Original Est.

Construction Budget (11/02)

Amount under/over

Pct. Under/over

Orig Comp Date

Actual Comp Date

Design (A/E)

GC/CM

AGRICULTURAL BIOTECHNOLOGY FACILITY PHASE 1

New

done

$ 20,000,000

$ 15,288,698

$ (4,711,302)

-23.6%

Winter 00

Winter 00

Svigals Associates

H R H / Atlas

AGRICULTURAL BIOTECHNOLOGY PHASE 2

New

in progress

$ 10,770,682

$ 11,087,143

$ 316,461

2.9%

Summer 02

Summer 02

Svigals Associates

Turner

ALUMNI QUAD RENOV (SPRINKLERS)

Reno

done

$ 18,500,000

$ 18,492,511

$ (7,489)

0.0%

Fall 02

Fall 02

W A S A

Whiting Turner

AVERY POINT RENOVATIONS

Reno

in progress

$ 5,323,000

           

MCC

AVERY PT MARINE SCIENCE & TECHNOLOGY CTR

New

done (punchlist)

$ 39,318,000

$ 41,518,638

$ 2,200,638

5.6%

Spring 00

Summer 01

S L A M

C. R. Klewin

BENTON ART MUSEUM ADDITIION

Reno -Ad/Alt

in progress

$ 3,200,000

         

Greg And Weiss

Gilbane

CENTRAL WAREHOUSE (NEW)

New

done (accepted)

$ 10,000,000

$ 11,029,541

$ 1,029,541

10.3%

Fall 00

Fall 00

Jeter Cook & Jepson

Konover

CHEMISTRY BUILDING ( NEW)

New

done

$ 57,754,200

$ 56,863,540

$ (890,660)

-1.5%

Fall 98

Fall 98

Centerbrook

Walsh

EAST CAMPUS (SPRINKLERS )

Reno

done

$ 3,000,000

$ 2,962,901

$ (37,099)

-1.2%

Fall 02

Fall 02

Wasa / P. Puhlick

Whiting Turner

FAIRFIELD RD PEDESTRIAN MALL

Util

done

$ 1,880,000

$ 7,069,967

$ 5,189,967

276.1%

Fall 98

Fall 98

Earthtech

Precision Power

GANT PLAZA DECK WATER LEAKAGE

Repair

done

$ 5,458,000

$ 8,499,586

$ 3,041,586

55.7%

Fall 01

Fall 01

Allan Dehar Associates

Whiting Turner

GENTRY BUILDING RENOVATIONS

Reno

in progress

$ 10,000,000

         

Svigals Associates

Gilbane

GRAD DORM RENOV (SPRINKLERS )

Reno

plan

$ 7,548,000

             

GREEK HOUSING COMPLEX (NEW)

New

in progress

$ 12,000,000

$ 11,598,309

$ (401,691)

-3.3%

Summer 03

 

H E N V

Capstone

HEATING PLANT UPGRADE/NORTH QUAD UTILS

Util

done

$ 20,837,000

$ 26,453,388

$ 5,616,388

27.0%

Spring 99

Spring 99

Stone & Webster

Precision Power

HILLTOP APARTMENT COMPLEX DEVELOPMENT

New

done

$ 42,000,000

$ 41,930,496

$ (69,504)

-0.2%

Fall 01

Fall 01

(design/build)

Capstone

HILLTOP DORM RENO (SPRINKLERS )

Reno

done

$ 8,700,000

$ 8,779,762

$ 79,762

0.9%

Fall 01

Fall 01

W A S A

Whiting Turner

HILLTOP DORMITORY (NEW)

New

done

$ 21,000,000

$ 20,962,977

$ (37,023)

-0.2%

Fall 01

Fall 01

Konover

Konover

ICE RINK ENCLOSURE

New

done

$ 2,790,000

$ 4,290,651

$ 1,500,651

53.8%

Fall 98

Fall 98

Design Forum

H R H/ Atlas

LITCHFIELD AGRICULTURAL CENTER

New

done

$ 1,417,000

$ 1,820,843

$ 403,843

28.5%

Fall 00

Winter 01

T L B Architecture

Hayes

MANSFIELD APARTMENTS RENOVATIONS

Reno

done

$ 2,777,000

$ 2,399,032

$ (377,968)

-13.6%

Fall 97

Fall 97

John Ruffalo

Conn-Strux

MUSIC & DRAMA/MUSIC ADDITIONS

Reno -Ad/Alt

done

$ 12,751,200

$ 17,774,194

$ 5,022,994

39.4%

Fall 99

Fall 99

Kagan Arch. & Planners

O & G

NATURAL HISTORY MUSEUM CONV..

Reno

done

$ 800,000

$ 805,613

$ 5,613

0.7%

Winter 01

Winter 01

Arbonies King Vlock

MCC Const.

NORTH CAMPUS APTS. AND SUITES

New

in progress

$ 45,000,000

$ 44,652,037

   

Summer 03

 

(design/build)

J P I

NORTH CAMPUS RENOVATIONS

Reno

in progress

$ 22,605,000

         

(in-house)

Whiting Turner

NORTHWEST QUAD RENOVATIONS

Reno+New

done (punchlist)

$ 32,001,000

$ 32,546,149

$ 545,149

1.7%

Fall 00

Fall 00

Herbert Newman

Whiting Turner

PARKING GARAGE NORTH

New

done

$ 9,658,000

$ 9,637,963

$ (20,037)

-0.2%

Winter 98

Winter 98

Macchi Engineers

O & G

PARKING GARAGE SOUTH & CO-OP

New

in progress

$ 24,000,000

$ 23,999,767

$ (233)

0.0%

G = Spring 01 C= Fall 01

G= Fall 01 C= Fall 02

Macchi Engineers

Manafort

SCHOOL OF BUSINESS - RENOVATE EXISTING BLDG/CUE

Reno -Ad/Alt

in progress

$ 9,400,000

         

Svigals Associates

Gilbane

SCHOOL OF BUSINESS (NEW)

New

done (punchlist)

$ 25,559,000

$ 27,345,744

$ 1,786,744

7.0%

Fall 01

Fall 01

Centerbrook

F I P

SCHOOL OF PHARMACY/ BIOLOGY (NEW)

New

design

$ 73,260,360

         

Davis Brody Bond

Gilbane

SHIPPEE/BUCKLEY (SPRINKLERS )

Reno

done

$ 12,000,000

$ 9,485,416

$ (2,514,584)

-21.0%

Fall 02

Fall 02

W A S A

Whiting Turner

SOUTH CAMPUS DORMS & NEW DINING HALL

New

done

$ 40,981,000

$ 46,310,651

$ 5,329,651

13.0%

Fall 98

Fall 98

S L A M

Suffolk

STAMFORD CAMPUS RELOCATION

Reno

done

$ 66,285,100

$ 72,270,646

$ 5,985,546

9.0%

Fall 98

Spring 99

Perkins Eastman

Walsh

STUDENT UNION ADDITION & RENO

Reno -Ad/Alt

in progress

$ 42,080,000

         

Cannon

Konover

TECH QUAD I-A NEW BIOLOGY & PHYSICS BLDG

New

in progress

$ 42,932,000

$ 69,558,195

$ 26,626,195

62.0%

Winter 00

(fall 02)

Allan Dehar Assoc.

Turner

TECH QUAD PHASE 2 (ITE BlLDG)

New

in progress

$ 34,120,000

$ 33,484,926

$ (635,074)

-1.9%

   

B H K R

O & G

TORREY LIFE SCIENCE RENOVATION

Reno

plan

$ 16,181,000

             

TOWERS DINING COMPLEX

New

in progress

$ 7,000,000

$ 7,671,559

$ 671,559

9.6%

     

FIP

TOWERS DORMITORY RENOVATIONS

Reno

design

$ 2,180,000

         

W A S A

Whiting Turner

WARING BLDG RENOVATIONS

Reno

done

$ 11,452,000

$ 14,388,690

$ 2,936,690

25.6%

Fall 01

Fall 01

Herbert Newman

Haynes

WEST CAMPUS RENOVATIONS

Reno

plan

$ 14,897,000

             

WHITE BLDG RENOVATIONS

Reno

done

$ 2,643,739

$ 2,682,743

$ 39,004

1.5%

Spring 99

Spring 99

Bianco Gioletto

Carlin

WILBUR CROSS BUILDING RENOVATIONS

Reno

done

$ 14,409,000

$ 17,249,347

$ 2,840,347

19.7%

I - Summer 01 II - Summer 02

I - Summer 01

II - Summer 02

Arbonies King & Vlock

Aspinet

1 Under state law, threshold projects include structures or additions at or above the following limits: (1) four stories; (2) 60 feet in height; (3) a clear span of 150 feet in width; (4) containing 150,000 square feet total gross floor area; or (5) an occuapancy of 1,000 persons as well as parking garages with spaces for 1,000 or more cars and residential facilities with 200 or more units (C.G.S. Section 29-276b).

2 The Auditors of Public Accounts are concerned the bidding process for one apartment project did not comply with UConn 2000 statutory provisions and additionally have questioned the university's authority in the design-build area. The auditors agree with the university's position that current legal requirements are subject to interpretation but are still reviewing the matter to determine whether corrective actions may be needed.

3 Authorized projects, their estimated costs, and their placement in either Phase I or II of the UConn 2000 program, are specified in statute. The board of trustees is permitted to make material revisions to projects and project additions or deletions can occur with the approval of the board and the General Assembly

4 Construction claims are official actions filed by a contractor or an owner when disputes arise over the scope of work or other contract provisions. To date, only two claims have been filed regarding UConn 2000 projects, the one by Suffolk and one by HRH/Atlas related to its dismissal from the New Bio-Physics Building project. The university has filed a counterclaim for the latter project.

5 For a detailed description of the state prevailing wage law, its enforcement, and its impact on wages, refer to the Legislative Program Review and Investigations Committee report Prevailing Wage Laws in Connecticut (1996).

6 A PLA is also in effect for the univeristy's Waterbury Campus project, which is not part of the UConn 2000 program.

7 Firm numbers on union membership in the building trades are not readily available. Estimates of union participation used in this study were provided Department of Labor staff, and two local contractors groups, the Connecticut Construction Industries Association and the Connecticut Associated Builders and Contractors, Inc. In contrast, by contractor associations about 90 percent of the heavy highway construction (e.g., roads, highways, and bridges) workers in Connecticut belong to unions at present.